Differences between wbs and product breakdown structure, Project Management

Assignment Help:

a) Draw a work breakdown structure (WBS) diagram for the project, to show all the planned tasks. This WBS should contain at least two levels.

b) Explain the main differences between this WBS and a product breakdown structure (PBS) diagram for the same project.

c) The dependencies between the 12 tasks listed above are:
B depends on A
C, E, H and J all depend on B
D depends on C
F depends on D and E
G depends on E
I depends on H
K depends on F, I and J
L depends on G and K
Draw a full Gantt chart for the project, showing all dependencies and floats and highlighting the critical path.

d) At the end of week 24, tasks A, B, C, D, H, I and J have been completed on schedule, and task E is continuing on schedule. However it is realised that task F will now take 3 weeks, starting from week 28.
Re-draw the Gantt chart to reflect this progress to date, making any necessary changes and highlighting the critical path.

a) What are the FOUR key objectives of the project manager when considering project success?
List and explain FOUR key skills that a project manager should have.

b) A project manager may bear in mind Belbin's theory when building their project team. List and explain at least SIX team roles that Belbin defines.

c) The project team has become unhappy as two popular, experienced team members have been transferred to another key project. The remaining members are required to take on the work of these two members. List THREE actions that the project manager could take to improve the morale of his team?

a) Define the word "stakeholder" in relation to an IT development project.

b) You work for a small research organisation. It is part of a federation of similar research organisations, each operating in a different part of the country. At the moment each of these organisations uses a different main computer system. It has been decided that the computer system used by your organisation should be extended and then used by all of the other organisations, to replace their existing systems. A network would be set up linked to the main server, which would be located in your organisation's offices.
List and explain at least FOUR different types of stakeholder in this new project. Identify their main concerns and their stake in the project.

c) A project sponsor has also been appointed. Name at least THREE people, or groups of people, who would then be directly responsible to the sponsor.

d) You have been appointed as the project manager and need to set up a project team. Using the Tuckman model, list and explain very briefly the four main phases that the team might go through before becoming fully effective.


Related Discussions:- Differences between wbs and product breakdown structure

What are the advantages of division of labour, What are the Advantages of D...

What are the Advantages of Division of Labour? Advantages of Division of Labour: As very similar worker does the same work frequently:- a. It gains proficiency and ski

Illustrate an example of a critical path given by activity, Illustrate an e...

Illustrate an example of demonstrating a network or critical path by given activity and duration. Activity                      Duration (Wks)                   Precede

H U D guidelines, For an initial secure order under HUD guidelines, are yo...

For an initial secure order under HUD guidelines, are you authorized to remove exterior debris automatically?

Search and remove modules, Seven process modules are placed on our model, a...

Seven process modules are placed on our model, and they represent the basic functions in the model. These process modules simulate important operations such as specifying wheel cha

System engineering and deployment of Envirobat, i need a 5000 words report,...

i need a 5000 words report, i have already submitted a project plan from a material. i want report from already available material and some portion from yours as well.

Secondary stakeholders and major risks in WAM organisation, The WAM Organis...

The WAM Organisation is one of the very successful supermarket chains within its own country. Reputation for innovation of it is unparalleled into its own country along with the wi

Product development tools, Qualities by design tools that decrease tota...

Qualities by design tools that decrease total product development time utilize high powered software and the latest in desktop computers. The primary qualities by design to

Organisation''s sustainability targets, Explain how operations management m...

Explain how operations management might contribute towards achieving an organisation's sustainability targets.  Operations management may be contribute to achieving an organisa

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd