Differences between wbs and product breakdown structure, Project Management

Assignment Help:

a) Draw a work breakdown structure (WBS) diagram for the project, to show all the planned tasks. This WBS should contain at least two levels.

b) Explain the main differences between this WBS and a product breakdown structure (PBS) diagram for the same project.

c) The dependencies between the 12 tasks listed above are:
B depends on A
C, E, H and J all depend on B
D depends on C
F depends on D and E
G depends on E
I depends on H
K depends on F, I and J
L depends on G and K
Draw a full Gantt chart for the project, showing all dependencies and floats and highlighting the critical path.

d) At the end of week 24, tasks A, B, C, D, H, I and J have been completed on schedule, and task E is continuing on schedule. However it is realised that task F will now take 3 weeks, starting from week 28.
Re-draw the Gantt chart to reflect this progress to date, making any necessary changes and highlighting the critical path.

a) What are the FOUR key objectives of the project manager when considering project success?
List and explain FOUR key skills that a project manager should have.

b) A project manager may bear in mind Belbin's theory when building their project team. List and explain at least SIX team roles that Belbin defines.

c) The project team has become unhappy as two popular, experienced team members have been transferred to another key project. The remaining members are required to take on the work of these two members. List THREE actions that the project manager could take to improve the morale of his team?

a) Define the word "stakeholder" in relation to an IT development project.

b) You work for a small research organisation. It is part of a federation of similar research organisations, each operating in a different part of the country. At the moment each of these organisations uses a different main computer system. It has been decided that the computer system used by your organisation should be extended and then used by all of the other organisations, to replace their existing systems. A network would be set up linked to the main server, which would be located in your organisation's offices.
List and explain at least FOUR different types of stakeholder in this new project. Identify their main concerns and their stake in the project.

c) A project sponsor has also been appointed. Name at least THREE people, or groups of people, who would then be directly responsible to the sponsor.

d) You have been appointed as the project manager and need to set up a project team. Using the Tuckman model, list and explain very briefly the four main phases that the team might go through before becoming fully effective.


Related Discussions:- Differences between wbs and product breakdown structure

Risk managemet, How do I create a risk management plan

How do I create a risk management plan

What is productivity, What is productivity? Productivity: Product...

What is productivity? Productivity: Productivity may be described as the ratio between input and output. Output implies the amount produced or the number of items produce

Confidentiality, confidential document in civil project

confidential document in civil project

Uses and benefits of risk breakdown structure, Uses and Benefits of RBS  ...

Uses and Benefits of RBS  The main uses and benefits of the RBS are outlined in this section.  Risk identification aid  Risk Breakdown Structure is used as a list that

Project management project for project managemen class, I have project assi...

I have project assignmet for project management and the submition due date is 5th may can you help me with it ?

Explain the gantt charts in risk management, Explain the Gantt Charts in ri...

Explain the Gantt Charts in risk management. Gantt Charts: By Henry Gantt a time chart devised into 1917s, an American engineer. This chart is a horizontal bar chart ut

Roles of b as the project sponsor and r, DG Company has made a significant ...

DG Company has made a significant investment in a project to develop a new client management IT system, which when implemented should help give the company a competitive edge.  How

Different stages in the negotiation process, In the face of rising costs, t...

In the face of rising costs, the senior management in PT Company has decided that significant cuts will be needed in the budgets of some of its departments. The promotional budget

Organizing-process management, Organizing Which is the process of group...

Organizing Which is the process of grouping resources and activities in a logical fashion. The function of organizing involves: grouping similar activities together (depa

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd