Differences between wbs and product breakdown structure, Project Management

Assignment Help:

a) Draw a work breakdown structure (WBS) diagram for the project, to show all the planned tasks. This WBS should contain at least two levels.

b) Explain the main differences between this WBS and a product breakdown structure (PBS) diagram for the same project.

c) The dependencies between the 12 tasks listed above are:
B depends on A
C, E, H and J all depend on B
D depends on C
F depends on D and E
G depends on E
I depends on H
K depends on F, I and J
L depends on G and K
Draw a full Gantt chart for the project, showing all dependencies and floats and highlighting the critical path.

d) At the end of week 24, tasks A, B, C, D, H, I and J have been completed on schedule, and task E is continuing on schedule. However it is realised that task F will now take 3 weeks, starting from week 28.
Re-draw the Gantt chart to reflect this progress to date, making any necessary changes and highlighting the critical path.

a) What are the FOUR key objectives of the project manager when considering project success?
List and explain FOUR key skills that a project manager should have.

b) A project manager may bear in mind Belbin's theory when building their project team. List and explain at least SIX team roles that Belbin defines.

c) The project team has become unhappy as two popular, experienced team members have been transferred to another key project. The remaining members are required to take on the work of these two members. List THREE actions that the project manager could take to improve the morale of his team?

a) Define the word "stakeholder" in relation to an IT development project.

b) You work for a small research organisation. It is part of a federation of similar research organisations, each operating in a different part of the country. At the moment each of these organisations uses a different main computer system. It has been decided that the computer system used by your organisation should be extended and then used by all of the other organisations, to replace their existing systems. A network would be set up linked to the main server, which would be located in your organisation's offices.
List and explain at least FOUR different types of stakeholder in this new project. Identify their main concerns and their stake in the project.

c) A project sponsor has also been appointed. Name at least THREE people, or groups of people, who would then be directly responsible to the sponsor.

d) You have been appointed as the project manager and need to set up a project team. Using the Tuckman model, list and explain very briefly the four main phases that the team might go through before becoming fully effective.


Related Discussions:- Differences between wbs and product breakdown structure

Principal problems of managing projects in organisation, What are the princ...

What are the principal problems of managing projects in a fully functional organisation structure? The major problems of functional organisations are to perform with what may b

Critical path method, HyperAV is a Manchester based company which is a reta...

HyperAV is a Manchester based company which is a retailer of home cinema equipment. They sell a variety of products including speakers, amplifiers, Blu-ray/DVD players and cables.

Explain the utility of base costs, Question 1: (a) ‘One of the most pow...

Question 1: (a) ‘One of the most powerful concept as advocated by Total Quality Management is that of the internal customer and supplier.' With reference to examples you ar

Factors of quality, Factors of Quality The implications here are tha...

Factors of Quality The implications here are that quality is to be viewed in its totality and not restricted only to the quality of production or products or some aspects

How could huge supermarket chain use in information system, When you knew a...

When you knew about an organisation’s strategy, that could you suggest IS applications which would support this? For illustration, how could a huge supermarket chain utilize inform

Work breakdown structure, Work breakdown structure: The work breakdown ...

Work breakdown structure: The work breakdown structure, as its name suggests, represents an organised and logical break down of the project into its component parts. Thus break

Quality standards, Quality Standards Quality Standards form a framework...

Quality Standards Quality Standards form a framework that helps organisations worldwide to develop products and services in the most efficient way. A quality Standard is a norm

Objectives of materials management, Objectives  of Materials Management: ...

Objectives  of Materials Management: 1. Low  prices: Obtaining  the least possible  price  for purchased materials is the  most  obvious  purchasing  objectives and certai

Project communication management processes, Question: (a) The greatest ...

Question: (a) The greatest threats to many projects are failures to communicate effectively. (i) Elaborate on the Project Communication Management processes (ii) Briefly

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd