Differences between wbs and product breakdown structure, Project Management

Assignment Help:

a) Draw a work breakdown structure (WBS) diagram for the project, to show all the planned tasks. This WBS should contain at least two levels.

b) Explain the main differences between this WBS and a product breakdown structure (PBS) diagram for the same project.

c) The dependencies between the 12 tasks listed above are:
B depends on A
C, E, H and J all depend on B
D depends on C
F depends on D and E
G depends on E
I depends on H
K depends on F, I and J
L depends on G and K
Draw a full Gantt chart for the project, showing all dependencies and floats and highlighting the critical path.

d) At the end of week 24, tasks A, B, C, D, H, I and J have been completed on schedule, and task E is continuing on schedule. However it is realised that task F will now take 3 weeks, starting from week 28.
Re-draw the Gantt chart to reflect this progress to date, making any necessary changes and highlighting the critical path.

a) What are the FOUR key objectives of the project manager when considering project success?
List and explain FOUR key skills that a project manager should have.

b) A project manager may bear in mind Belbin's theory when building their project team. List and explain at least SIX team roles that Belbin defines.

c) The project team has become unhappy as two popular, experienced team members have been transferred to another key project. The remaining members are required to take on the work of these two members. List THREE actions that the project manager could take to improve the morale of his team?

a) Define the word "stakeholder" in relation to an IT development project.

b) You work for a small research organisation. It is part of a federation of similar research organisations, each operating in a different part of the country. At the moment each of these organisations uses a different main computer system. It has been decided that the computer system used by your organisation should be extended and then used by all of the other organisations, to replace their existing systems. A network would be set up linked to the main server, which would be located in your organisation's offices.
List and explain at least FOUR different types of stakeholder in this new project. Identify their main concerns and their stake in the project.

c) A project sponsor has also been appointed. Name at least THREE people, or groups of people, who would then be directly responsible to the sponsor.

d) You have been appointed as the project manager and need to set up a project team. Using the Tuckman model, list and explain very briefly the four main phases that the team might go through before becoming fully effective.


Related Discussions:- Differences between wbs and product breakdown structure

Plan, Plan A plan is a blueprint or framework used to describe how an o...

Plan A plan is a blueprint or framework used to describe how an organization expects to achieve its goals. Planning is the process of developing plans or determining how best t

Quality - total quality management - elements of tqm, Quality is customer d...

Quality is customer defined: Quality of service or service excellence is a desire to maintain or strengthen the commitment to the library's philosophy of service to users. Qua

Benefits of quality, B enefits of quality The benefits of quality in p...

B enefits of quality The benefits of quality in project performance are: C ustomer satisfaction: is the result of a quality product or project. If customers requirem

Process of taking disciplinary action, T, a member of the finance team, has...

T, a member of the finance team, has been constantly arriving late to work and in recent months he has consistently made significant errors in his work. A number of colleagues have

Analysis of line balancing problems, Analysis of Line Balancing Problems ...

Analysis of Line Balancing Problems The procedure involves the followings steps: Determine the number of work stations and time available at each work stations.

Factors can make competitive rivalry between organisation, DF Company, a re...

DF Company, a relatively new company, is in the business of designing and building farm equipment and machinery. Whilst it has been winning in its first few years of operation, sal

Project Initiation and Planning Report, Task As the project manager you ar...

Task As the project manager you are required to present an initial project report to the project sponsor that shows how you propose to implement this project. As the project manag

Disadvantages of fms, Disadvantages of FMS Limited ability t...

Disadvantages of FMS Limited ability to adapt to changes in product Substantial preplanning and capital Tooling and fixture requirements

Product based layout, Product Based Layout Also called the straight li...

Product Based Layout Also called the straight line layout or layout for serialized manufacture, product layout involves the arrangement of machines in one line depending upon

Procurement , Functions of Purchasing Department

Functions of Purchasing Department

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd