Differences between wbs and product breakdown structure, Project Management

Assignment Help:

a) Draw a work breakdown structure (WBS) diagram for the project, to show all the planned tasks. This WBS should contain at least two levels.

b) Explain the main differences between this WBS and a product breakdown structure (PBS) diagram for the same project.

c) The dependencies between the 12 tasks listed above are:
B depends on A
C, E, H and J all depend on B
D depends on C
F depends on D and E
G depends on E
I depends on H
K depends on F, I and J
L depends on G and K
Draw a full Gantt chart for the project, showing all dependencies and floats and highlighting the critical path.

d) At the end of week 24, tasks A, B, C, D, H, I and J have been completed on schedule, and task E is continuing on schedule. However it is realised that task F will now take 3 weeks, starting from week 28.
Re-draw the Gantt chart to reflect this progress to date, making any necessary changes and highlighting the critical path.

a) What are the FOUR key objectives of the project manager when considering project success?
List and explain FOUR key skills that a project manager should have.

b) A project manager may bear in mind Belbin's theory when building their project team. List and explain at least SIX team roles that Belbin defines.

c) The project team has become unhappy as two popular, experienced team members have been transferred to another key project. The remaining members are required to take on the work of these two members. List THREE actions that the project manager could take to improve the morale of his team?

a) Define the word "stakeholder" in relation to an IT development project.

b) You work for a small research organisation. It is part of a federation of similar research organisations, each operating in a different part of the country. At the moment each of these organisations uses a different main computer system. It has been decided that the computer system used by your organisation should be extended and then used by all of the other organisations, to replace their existing systems. A network would be set up linked to the main server, which would be located in your organisation's offices.
List and explain at least FOUR different types of stakeholder in this new project. Identify their main concerns and their stake in the project.

c) A project sponsor has also been appointed. Name at least THREE people, or groups of people, who would then be directly responsible to the sponsor.

d) You have been appointed as the project manager and need to set up a project team. Using the Tuckman model, list and explain very briefly the four main phases that the team might go through before becoming fully effective.


Related Discussions:- Differences between wbs and product breakdown structure

Histograms, H i stograms Histograms show a visual summary of the data...

H i stograms Histograms show a visual summary of the data, which is simple to understand. Raw data is difficult to understand and a pictorial representation helps to understa

Explain about the work breakdown structure, Explain about the work breakdow...

Explain about the work breakdown structure. Work breakdown structure (WBS): The concept of work breakdown structure (WBS) is to assist plan effectively for a project by b

Peril database, PERIL Database   The Project Experience Risk Information...

PERIL Database   The Project Experience Risk Information Library (PERIL) is a database, which provides a basis for the analysis of high-tech project risk.  A project can have

Use of operational approach in development process, Q. Use of Operational a...

Q. Use of Operational approach in development process? It has been defined as the application of scientific methods, technology and tools to operation of system with optimum s

Explain about the economic order quantity and total cost, Explain about the...

Explain about the Economic Order Quantity and Total Cost with diagram. Economic Order Quantity and Total Cost: The total of Inventory procurement cost and also inventory carryi

Feasibility analysis on syringe management plan, Feasibility Analysis ...

Feasibility Analysis Market analysis Competition: To protect the community against harmful needle injuries Yarra council has already implemented the syringe manageme

Describe the contents of a project initiation document, Describe the conten...

Describe the contents of a project initiation document. Contents of a PID (project initiation document): • Terms of reference for example the concept of the report • Scop

Project for creating a restaurant utilizing electronic menu, My team's proj...

My team's project is about creating a restaurant utilizing "Electronic menu." My homework is to answer three questions about industry goals. 1. Is your industry growing? 2.

What must be the responsibility of the project manager, What must be the re...

What must be the responsibility of the project manager into relation to the business case? Idyllically, the project manager must be appointed early adequate to give to the deve

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd