Differences between wbs and product breakdown structure, Project Management

Assignment Help:

a) Draw a work breakdown structure (WBS) diagram for the project, to show all the planned tasks. This WBS should contain at least two levels.

b) Explain the main differences between this WBS and a product breakdown structure (PBS) diagram for the same project.

c) The dependencies between the 12 tasks listed above are:
B depends on A
C, E, H and J all depend on B
D depends on C
F depends on D and E
G depends on E
I depends on H
K depends on F, I and J
L depends on G and K
Draw a full Gantt chart for the project, showing all dependencies and floats and highlighting the critical path.

d) At the end of week 24, tasks A, B, C, D, H, I and J have been completed on schedule, and task E is continuing on schedule. However it is realised that task F will now take 3 weeks, starting from week 28.
Re-draw the Gantt chart to reflect this progress to date, making any necessary changes and highlighting the critical path.

a) What are the FOUR key objectives of the project manager when considering project success?
List and explain FOUR key skills that a project manager should have.

b) A project manager may bear in mind Belbin's theory when building their project team. List and explain at least SIX team roles that Belbin defines.

c) The project team has become unhappy as two popular, experienced team members have been transferred to another key project. The remaining members are required to take on the work of these two members. List THREE actions that the project manager could take to improve the morale of his team?

a) Define the word "stakeholder" in relation to an IT development project.

b) You work for a small research organisation. It is part of a federation of similar research organisations, each operating in a different part of the country. At the moment each of these organisations uses a different main computer system. It has been decided that the computer system used by your organisation should be extended and then used by all of the other organisations, to replace their existing systems. A network would be set up linked to the main server, which would be located in your organisation's offices.
List and explain at least FOUR different types of stakeholder in this new project. Identify their main concerns and their stake in the project.

c) A project sponsor has also been appointed. Name at least THREE people, or groups of people, who would then be directly responsible to the sponsor.

d) You have been appointed as the project manager and need to set up a project team. Using the Tuckman model, list and explain very briefly the four main phases that the team might go through before becoming fully effective.


Related Discussions:- Differences between wbs and product breakdown structure

Search and remove modules, Seven process modules are placed on our model, a...

Seven process modules are placed on our model, and they represent the basic functions in the model. These process modules simulate important operations such as specifying wheel cha

Explain feasibility analysis and product development process, Q. Explain Fe...

Q. Explain Feasibility Analysis and Product development process? Once the product concepts have been  formed, the feasibility studies are conducted. This study involves the fol

External factors of syringe management , External Factors Opportunit...

External Factors Opportunity This plan will build a good image for Maribyrnong Council, even Melbourne. The opportunity for Maribyrnong Council, there maybe will attrac

Project management value initiative, Project Management Value Initiative ...

Project Management Value Initiative The project management initiative program is a six step process which is designed to bring about a measurement team from the introduction to

Cost management, Dr. Sherry Bird is employed by Dental Associates. Dental A...

Dr. Sherry Bird is employed by Dental Associates. Dental Associates recently installed a computerized job-order costing system to help monitor the cost of its services. Each patien

Flow chart, how do I calculate forward pass and backward pass?

how do I calculate forward pass and backward pass?

Explain the sources of power of a project manager, Question 1: (a) Powe...

Question 1: (a) Power is one of the most important human variables in the project management process as it sets the framework for directing and influencing human resources. Exp

Small project, Q. If I only have a small project, do I really need to bothe...

Q. If I only have a small project, do I really need to bother with all of that? In any of project of any size all of these ten attributes requires some degree of attention. But

Inventory and stores control, 1. Inventory  and Stores Control : Inventor...

1. Inventory  and Stores Control : Inventory  control is  a systematic procedure  for  ensuring  the  availability  of items necessary to meet the  production  requirements  at o

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd