Differences between wbs and product breakdown structure, Project Management

Assignment Help:

a) Draw a work breakdown structure (WBS) diagram for the project, to show all the planned tasks. This WBS should contain at least two levels.

b) Explain the main differences between this WBS and a product breakdown structure (PBS) diagram for the same project.

c) The dependencies between the 12 tasks listed above are:
B depends on A
C, E, H and J all depend on B
D depends on C
F depends on D and E
G depends on E
I depends on H
K depends on F, I and J
L depends on G and K
Draw a full Gantt chart for the project, showing all dependencies and floats and highlighting the critical path.

d) At the end of week 24, tasks A, B, C, D, H, I and J have been completed on schedule, and task E is continuing on schedule. However it is realised that task F will now take 3 weeks, starting from week 28.
Re-draw the Gantt chart to reflect this progress to date, making any necessary changes and highlighting the critical path.

a) What are the FOUR key objectives of the project manager when considering project success?
List and explain FOUR key skills that a project manager should have.

b) A project manager may bear in mind Belbin's theory when building their project team. List and explain at least SIX team roles that Belbin defines.

c) The project team has become unhappy as two popular, experienced team members have been transferred to another key project. The remaining members are required to take on the work of these two members. List THREE actions that the project manager could take to improve the morale of his team?

a) Define the word "stakeholder" in relation to an IT development project.

b) You work for a small research organisation. It is part of a federation of similar research organisations, each operating in a different part of the country. At the moment each of these organisations uses a different main computer system. It has been decided that the computer system used by your organisation should be extended and then used by all of the other organisations, to replace their existing systems. A network would be set up linked to the main server, which would be located in your organisation's offices.
List and explain at least FOUR different types of stakeholder in this new project. Identify their main concerns and their stake in the project.

c) A project sponsor has also been appointed. Name at least THREE people, or groups of people, who would then be directly responsible to the sponsor.

d) You have been appointed as the project manager and need to set up a project team. Using the Tuckman model, list and explain very briefly the four main phases that the team might go through before becoming fully effective.


Related Discussions:- Differences between wbs and product breakdown structure

Critical path method, HyperAV is a Manchester based company which is a reta...

HyperAV is a Manchester based company which is a retailer of home cinema equipment. They sell a variety of products including speakers, amplifiers, Blu-ray/DVD players and cables.

Project cost accounting, P o w e rful cost reduction The project co...

P o w e rful cost reduction The project cost accounting will track the quality-related costs which can be an important management tool. For example, suppose there are some

Code of professional conduct, A 28 year old quadriplegic man is admitted to...

A 28 year old quadriplegic man is admitted to the hospital with pneumonia and severe pressure ulcers.  You are the enrolled nurse caring for him and hear him asker the doctor that

Determine the supporting project activities for estimate, Describe differen...

Describe different types of supporting project activities for estimating. Estimate the given supporting project activities are as follows: 1.    Project management 2.    Team lea

Strategic internatic international business management, 1. Identify a poten...

1. Identify a potential target market for BNP Paribas’ retail banking’s future international expansion strategy

Define the resource histograms in short, Define the Resource Histograms in ...

Define the Resource Histograms in short. Resource histograms A resource histogram is a column (or bar) chart which demonstrates the number of resources allocated to a pro

Project management cycle, It is essential that you study the list below to ...

It is essential that you study the list below to ensure that you understand the terminology used in assignment and examination questions. The successful outcome of your assessment

What is dummy activity in job operation of a project, What is dummy activit...

What is dummy activity in job operation of a project? Dummy Activity: All projects consist of a number of job operations or tasks that are termed as activities. An activi

Identify a governmental and a not-for-profit program, One of the characteri...

One of the characteristics unique to governmental and not-for-profit organizations is the inability to eliminate unprofitable activities. Clearly, in the case of these activities,

Tolerance and surface finish, Tolerance and Surface Finish Design engi...

Tolerance and Surface Finish Design engineers are always blamed of specifying closer tolerances than necessary. It  is obvious that to achieve a tolerance of ± 0.001 mm is mor

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd