Differences between wbs and product breakdown structure, Project Management

Assignment Help:

a) Draw a work breakdown structure (WBS) diagram for the project, to show all the planned tasks. This WBS should contain at least two levels.

b) Explain the main differences between this WBS and a product breakdown structure (PBS) diagram for the same project.

c) The dependencies between the 12 tasks listed above are:
B depends on A
C, E, H and J all depend on B
D depends on C
F depends on D and E
G depends on E
I depends on H
K depends on F, I and J
L depends on G and K
Draw a full Gantt chart for the project, showing all dependencies and floats and highlighting the critical path.

d) At the end of week 24, tasks A, B, C, D, H, I and J have been completed on schedule, and task E is continuing on schedule. However it is realised that task F will now take 3 weeks, starting from week 28.
Re-draw the Gantt chart to reflect this progress to date, making any necessary changes and highlighting the critical path.

a) What are the FOUR key objectives of the project manager when considering project success?
List and explain FOUR key skills that a project manager should have.

b) A project manager may bear in mind Belbin's theory when building their project team. List and explain at least SIX team roles that Belbin defines.

c) The project team has become unhappy as two popular, experienced team members have been transferred to another key project. The remaining members are required to take on the work of these two members. List THREE actions that the project manager could take to improve the morale of his team?

a) Define the word "stakeholder" in relation to an IT development project.

b) You work for a small research organisation. It is part of a federation of similar research organisations, each operating in a different part of the country. At the moment each of these organisations uses a different main computer system. It has been decided that the computer system used by your organisation should be extended and then used by all of the other organisations, to replace their existing systems. A network would be set up linked to the main server, which would be located in your organisation's offices.
List and explain at least FOUR different types of stakeholder in this new project. Identify their main concerns and their stake in the project.

c) A project sponsor has also been appointed. Name at least THREE people, or groups of people, who would then be directly responsible to the sponsor.

d) You have been appointed as the project manager and need to set up a project team. Using the Tuckman model, list and explain very briefly the four main phases that the team might go through before becoming fully effective.


Related Discussions:- Differences between wbs and product breakdown structure

Processes by market orientation , Processes by Market Orientation Pro...

Processes by Market Orientation Processes can  also be categorized on the basis  of four  marker orientations: Make to Stock (MTS): the goods usually are standard mat

Explain the fundamental quality management principles, Question: (a) Ex...

Question: (a) Explain the eight fundamental Quality Management Principles of the standard ISO 9001: 2008. (b) Explain the relevance of the various requirements in terms of M

Determine elapsed time of critical path, Determine elapsed time of critical...

Determine elapsed time of critical path when The critical path is given by points BCFG and the elapsed time 17 weeks. There D can over running by up to 3 weeks without

Scoping a project, QUESTION While scoping a project, as much informatio...

QUESTION While scoping a project, as much information as possible should be gathered about the wants and concerns of sponsors and end-users. What are the useful channels of

What are the purposes of budgets in risk management, What are the purposes ...

What are the purposes of budgets in risk management? The purpose of budgets: P   Planning R  Resource employment or responsibility accounting I   Integration and/o

What are the causes of poor industrial relations, What are the Causes of Po...

What are the Causes of Poor Industrial Relations? Purposes of Poor Industrial Relations situation for good IR are as follows: a. Inadequate fixation of wages and wage struct

Mapping project - mapping system, i. Select a small mapping project appl...

i. Select a small mapping project applicable to your 'mapping' system that aims to present a theme or specific solution (e.g. tourist map, farm map, habitat map, etc.). ii.

What are the advantages of critical path analysis, What are the advantages ...

What are the advantages of critical path analysis? Advantages of critical path analysis (CPA): a. Classifies interrelationships in between various activities or tasks

Communication strategy, Communication Strategy: Communication str...

Communication Strategy: Communication strategy, beginners as a concept in the 1980s by communication expert Mary Munter, provides as the basis for all management communic

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd