Differences between wbs and product breakdown structure, Project Management

Assignment Help:

a) Draw a work breakdown structure (WBS) diagram for the project, to show all the planned tasks. This WBS should contain at least two levels.

b) Explain the main differences between this WBS and a product breakdown structure (PBS) diagram for the same project.

c) The dependencies between the 12 tasks listed above are:
B depends on A
C, E, H and J all depend on B
D depends on C
F depends on D and E
G depends on E
I depends on H
K depends on F, I and J
L depends on G and K
Draw a full Gantt chart for the project, showing all dependencies and floats and highlighting the critical path.

d) At the end of week 24, tasks A, B, C, D, H, I and J have been completed on schedule, and task E is continuing on schedule. However it is realised that task F will now take 3 weeks, starting from week 28.
Re-draw the Gantt chart to reflect this progress to date, making any necessary changes and highlighting the critical path.

a) What are the FOUR key objectives of the project manager when considering project success?
List and explain FOUR key skills that a project manager should have.

b) A project manager may bear in mind Belbin's theory when building their project team. List and explain at least SIX team roles that Belbin defines.

c) The project team has become unhappy as two popular, experienced team members have been transferred to another key project. The remaining members are required to take on the work of these two members. List THREE actions that the project manager could take to improve the morale of his team?

a) Define the word "stakeholder" in relation to an IT development project.

b) You work for a small research organisation. It is part of a federation of similar research organisations, each operating in a different part of the country. At the moment each of these organisations uses a different main computer system. It has been decided that the computer system used by your organisation should be extended and then used by all of the other organisations, to replace their existing systems. A network would be set up linked to the main server, which would be located in your organisation's offices.
List and explain at least FOUR different types of stakeholder in this new project. Identify their main concerns and their stake in the project.

c) A project sponsor has also been appointed. Name at least THREE people, or groups of people, who would then be directly responsible to the sponsor.

d) You have been appointed as the project manager and need to set up a project team. Using the Tuckman model, list and explain very briefly the four main phases that the team might go through before becoming fully effective.


Related Discussions:- Differences between wbs and product breakdown structure

Explain the objectives of a procurement development model, Problem: (a)...

Problem: (a) Explain the objectives of a Procurement Development Model. (b) Explain one Procurement Development Model you are familiar with. (c) "In certain organisation

Areas of key risk in project management, Areas of key risk in Project Manag...

Areas of key risk in Project Management Companies believe that the most critical risk they face is market or competitive risk. There are various other risks faced by organisati

Potential side effects of the tqm initiative, Question: "Total Quality ...

Question: "Total Quality Management is regarded as a quick fix solution by many organizations.This has led various companies to start on the road to total quality improvement i

Evaluation of the prototype, At this stage of design the designer will...

At this stage of design the designer will invariably by under tremendous pressure to quickly finish the design and pass it on for production. This is so because even w

Illustrate an example of a critical path given by activity, Illustrate an e...

Illustrate an example of demonstrating a network or critical path by given activity and duration. Activity                      Duration (Wks)                   Precede

Scope of materials management, Scope  of Materials  Management Material...

Scope  of Materials  Management Materials  management  embraces all  functions  concerning  planning  purchasing  production  control  stores  traffic and physical distribution

How to measures defect ratios for the product, Defects found after product ...

Defects found after product delivery per function point Defects found after product delivery per LOC Pre-delivery defects: yearly post-delivery defects Defects per functio

Essential pre-requisites of a grievance procedure, Problem 1: Show the ...

Problem 1: Show the essential pre-requisites of a grievance procedure. Essential pre-requisites of a grievance procedure Problem 2: What are the objectives of Trade

Methods used to performance appraisal of workers, What are the methods used...

What are the methods used to performance appraisal of workers? The methods used within performance appraisal of workers are ranking method, Paired Comparison Technique, Forced

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd