Differences between open shield and closed shield, Civil Engineering

Assignment Help:

Q. Differences between open shield and closed shield?

Open shield type TBM refers to those providing lateral support only. They can be further classified into single shield and double shield.  

Closed shield type TBM refers to those providing lateral support and frontal support. Some common TBM method under this category includes compressed air TBM, slurry shield TBM, earth pressure balance machine and mixed confinement shield. 

Compressed air TBM is suitable for cohesive soils under water table (e.g. ground with low permeability with no major discontinuities). Slurry shield TBM is suitable for soft ground and soft rock under water table and also for ground for high permeability. Earth pressure balance machine is suitable for soft ground and soft rock under water table. It is not recommended for very abrasive and hard ground.


Related Discussions:- Differences between open shield and closed shield

How can you design side slope of bank, Q. How can you design Side Slope of ...

Q. How can you design Side Slope of bank? Angle of bank should be flatter than angle of repose of pitching material. Angle of repose of sand is 2:1 while that of stone is about

Estimate Bridge Pier Concrete, Takeoff the 3 elements for the following bri...

Takeoff the 3 elements for the following bridge pier components: 1. Pier Footing, 2. Pier Column, 3. Pier Cap (Top). • Misc Items to include Shear Key. • Misc Items to exclude Reba

Physics, A point charge q2 = -2.3 µC is fixed at the origin of a co-ordinat...

A point charge q2 = -2.3 µC is fixed at the origin of a co-ordinate system as shown. Another point charge q1 = 4.0 µC is is initially located at point P, a distance d1 = 6.0 cm fro

Define the approach velocity, Define the Approach Velocity Typical prob...

Define the Approach Velocity Typical problems have negligible approach velocity.  v 1 = Q/A, where A = the cross-sectional area of flow in the channel. The value is not the ve

Computation of settlement, Q. Computation of Settlement? The settlement...

Q. Computation of Settlement? The settlement  in any soil mass under an applied stress is given by s = s i + s c + s s where, S  =  total settlement, S i =  imm

Interface between base plates and footings, Interface between base plates a...

Interface between base plates and footings Surface of footings is generally quite rough so that some levelling has to be carried out for base plates. Interface between base pl

Function of reinforced concrete infill, Function of reinforced concrete inf...

Function of reinforced concrete infill in marine piling system of steel tubular pile with reinforced concrete infill Reinforced concrete is designed to fill void space inside

What do you mean by elastomeric bearings, Q. What do you mean by Elastomeri...

Q. What do you mean by Elastomeric bearings? Steel bearings are good but suffer from problems of corrosion and high level of maintenance. Due to these problems of steel bearing

Calcculate the material costs, A capital improvement project requires the i...

A capital improvement project requires the installation of a property line fence along the 250-ft Northern boundary line.The decorative aluminum fence is constructed of posts space

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd