Differences between epoxy grout, cement grout and cement mortar?
Epoxy grout comprises epoxy resin, epoxy hardener and aggregates/sand.As a matter of fact, there are various types of resin used in construction industry such as epoxy, polyester, polyurethane etc. Though epoxy grout appears to imply presence of cement material by its name, it doesn't contain any cement at all. Instead epoxy hardener serves to initiate the hardening process of epoxy grout. It is normally used for repairing hairline cracks and cavities in concrete structures and may be adopted as bonding agent or primer.
Cement grout is formed by mixing cement powder with water in that the ratio of cement of water is more or less similar to that of concrete. Due to relatively high water content, mixing of cement with water creates a fluid suspension that can be poured under base plates or into holes. Hardening and setting are the significant processes that affect the performance of cement grout. Furthermore presence of excessive voids would also affect the stiffness, strength and permeability of grout. It is versatile in application of filling voids and gaps in structures.
Cement mortar is generally a mixture ofsand, cement and water (typical proportion by weight is 1:0.4:3). It is proposed that cement mortar is constructed by placing and packing instead of by pouring. They are employed as bedding for concrete kerbs in roadwork. They areoccasionally placed under base plates where a substantial proportion of load is designed to be transferred by bedding to other members.
how to convert UVL to UDL
Derivation of Moment-Area Method
short note of distomat
describe in detail the uses of concrete
write a program to design two way slab
how can we post tension a raft foundation? what design procedure should we follow to post tension raft foundation in order to decrease the concrete and steel volume and increase th
What are borrow pits?
State about the pre-tensioned concrete beam A pre-tensioned concrete beam, 200 mm wide and 300 mm deep, is prestressed by straight wires carrying an initial force of 150 kN at
Perimeter of a hexagonal pyramid
what is the total volume required for the gravel material of 6.5mx2314mx0.1m with a relative density of 2.919 and a loose bulk density of 1668kg/m3
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd