The following information is available for three MPS (Master Product Scheduling) items:

Product A                            An 80 unit order is to be started in Week 3.

                                          A 55 unit order is to be started in week 6.

Product B                           A 125 unit order is to be started in week 5

Product C                           A 60 unit order is to be started in week 4.

Develop the material requirements plan for the next 6 weeks for items D, E, and F.  The BOMs (Bill of Materials) are shown in the below figure (1), and the data from the inventory records are shown in table 2.  (Warning: A safety stock requirement applies to item F.  Be sure to plan a receipt for any week in which the projected on-hand inventory becomes less than the safety stock.)

 


Related Discussions:- Develop the material requirements plan

Monolithic, What is monolithic and its diagram

What is monolithic and its diagram

What are overlays?, What are over lays? If a large process enters which...

What are over lays? If a large process enters which is huge than the available memory we are able to use overlays. In this we can divide process into pieces .which is recognize

What is a process control block?, What is a Process Control Block? Ever...

What is a Process Control Block? Every process in the operating system is represented by a process control block as well called a task control block. It contains several pieces

Pages into physical memory, For reading, most operating systems use demand ...

For reading, most operating systems use demand paging. This means that pages are only read from the disk into physical memory when they are needed. In the page table, there is a re

Allocating new pages, Processes have valid and invalid entries on their pag...

Processes have valid and invalid entries on their page tables. The valid entries all point to some where "real" (e.g. a physical page, or some portion of disk in case of non-reside

What are the drawbacks of spiral model, What are the drawbacks of spiral mo...

What are the drawbacks of spiral model? I. It is based on customer communication. If the communication is not proper then the software product that gets developed will not be t

What are two probable uses of these multiple modes, Q. Several CPUs provide...

Q. Several CPUs provide for more than two modes of operation. What are two probable uses of these multiple modes? Answer: Although most systems merely distinguish between use

Explain the worker model, Explain the Worker Model The Worker Model of ...

Explain the Worker Model The Worker Model of client-server application architecture provides a very good understanding of threads and their power to the developer. This exercis

Explain signal handling, Signal handling A signal is used in UNIX syste...

Signal handling A signal is used in UNIX systems to inform a process that a particular event has occurred. 1. A signal is produced by the occurrence of a particular event.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd