Determine the wbs shown below, Operation Management

Assignment Help:

Consider the WBS shown below:

1.00.00
1.1.0
1.1.1
1.1.2
1.2.0
1.2.1
1.2.2

If the total program costs $100,000 and 1.2.1 and 1.2.2 are each $20 K, then the cost of 1.1.0 is:

Answer

$20 K

$40 K

$60 K

Cannot be determined


Related Discussions:- Determine the wbs shown below

Describe what are the different types of strategies, What are the different...

What are the different types of strategies? What are the differences among these strategies? How do you determine which type of strategy is most appropriate for your organization?

Explain objective of value stream mapping is to improve data, 1) Bill of ma...

1) Bill of material errors can cause serious problems for MRP system calculations of dependant demands 2) No matter what forecasting technique is used, the probability of a prod

Human Factors in Aircraft Maintenance releated incidents, Need someone to e...

Need someone to edit my capstone project i have written and make the required changes

Describe installing and servicing personal computer business, You work for ...

You work for a computer parts and software distributor. Your co-worker and friend is starting up a second business installing and servicing personal computers. She asks you not to

Explain challenges in leading a multi-generational workforce, Challenges in...

Challenges in leading a multi-generational and/or multi-cultural workforces: Need a complete summary for the listed assignment, references. Please at least one page of information

What is the ex post redistribution, 1. Two individuals, Vic and Val, are bo...

1. Two individuals, Vic and Val, are both working. Vic faces a 10 percent chance of becoming unemployed for three months and losing $12,000 of income. Val's probability of becoming

Explain job design be used to create a motivated workforce, How can job des...

How can job design be used to create a more motivated workforce? Be specific.

Explain the chocolate raw material safety stock christian, Christian runs a...

Christian runs a small chocolate shop. He manages his chocolate raw material using a periodic review system. Daily demand has a mean of 100 pounds and standard deviation of 10 poun

Describe system safety program plan, You are writing a System Safety Progra...

You are writing a System Safety Program Plan (SSPP). What are some of the key elements/tasks you should include in the SSPP to make this plan effective?

Differentiation scheme that focuses on quality products, XYZ's Inc. Schedul...

XYZ's Inc. Scheduling System Started in Jacksonville, Indiana in 1983 at Mick's Lounge, where Papa John, John Schnatter, started a pizza delivery business within his father'

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd