Determine the wbs shown below, Operation Management

Assignment Help:

Consider the WBS shown below:

1.00.00
1.1.0
1.1.1
1.1.2
1.2.0
1.2.1
1.2.2

If the total program costs $100,000 and 1.2.1 and 1.2.2 are each $20 K, then the cost of 1.1.0 is:

Answer

$20 K

$40 K

$60 K

Cannot be determined


Related Discussions:- Determine the wbs shown below

Mb0044, What do you understand by “line balancing”? What happens if balance...

What do you understand by “line balancing”? What happens if balance doesn’t exist?

Explain negotiated a non-deliverable forward contract, Johnson, Inc., a U.S...

Johnson, Inc., a U.S.-based MNC, will need 10 million Thai baht on August 1. It is now May 1. Johnson has negotiated a non-deliverable forward contract with its bank. The reference

Explain transportation problem, How many constraints are there in a transpo...

How many constraints are there in a transportation problem which has 5 supply points and 4 demand points?

Explain what recommendations would you make and why, 1. Draw a process flow...

1. Draw a process flow diagram of the process described in the case. Be sure to identify the key resources involved and the task times at each step. 2. What is utilization at ea

Which one technique i recommend is because, Complete the below table. Which...

Complete the below table. Which one of these techniques would you recommend to use and indicate your rationale. Technique Ave Bias Ave MAD MSE Ave MAPE Naïve 4 Per MA Exp Smooth Th

Explain all four geographic markets during years, The market for branded at...

The market for branded athletic footwear is projected to grow a 7-9% annually worldwide during the Year 11-Year 20 period. b 9-11% annually in Latin America and the Asia-Paci

Describe what is the total cost of a package, The Fido Dog Food Company wis...

The Fido Dog Food Company wishes to introduce a new brand of dog biscuits (composed of chicken and liver-flavoured biscuits) that meets certain nutritional requirements. The liver-

Explain the precedence relationships and the estimated times, A project con...

A project consists of activities A, B, C, D, E, F, and G. The precedence relationships and the estimated times to complete each activity are given below: Activity Preceding Activit

Need help for assignment, Prob: The 21st Century Studios is about to begin ...

Prob: The 21st Century Studios is about to begin the production of its most important (and most expensive) movie of the year accepted#

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd