Determine the thermal stress in the bar, Civil Engineering

Assignment Help:

Determine the thermal stress in the bar:

A stepped bar made of aluminum is held between two supports. The bar is 900 mm in length at 38ºC, 600 mm of which is having a diameter of 50 mm, while the rest is of 25 mm diameter. Determine the thermal stress in the bar at a temperature of 21ºC, if

(a) The supports are unyielding, and

(b) When the supports move towards each other by 0.1 mm.

Given E for aluminum = 74 kN/mm2

α for aluminum = 23.4 × 10-6 K-1

Solution

When the Supports are Unyielding

We have, L1 = 600 mm; diameter d1 = 50 mm

Thus,  A1 = π(50) 2/4 mm2

Also,   L2 = 300 mm; diameter d2 = 25 mm

Therefore, A2 = π(25) 2/4 mm2

and     ΔT = 38 - 21 = 17ºC

Therefore, free contraction, ΔL = L α ΔT = 900 × 23.4 × 10- 6 × 17 = 0.358 mm. Let σ1 be the stress in 50 mm φ part and σ2 be the stress in 25 mm φ part.

Then,

σ1 =   ΔTEA2 αL/A1L2 +A2L1 = 900 × 23.4 × 10 -6  × 17 × 74 × 103 × π × (25) 2/4(π × (50)2/4× 300 + π × (25) 2/4 × 600)

= 14.72 N/mm2

σ2 = σ1 (A1 + A2) =14.72 × (50) 2/ (25) 2= 58.88 N/mm2

These stresses are tensile in nature

When the Supports Move towards Each Other by 0.1 mm

Here,  ΔL´ = 0.1 mm.

∴          σ1 =   EA2 [ΔL - ΔL′]/ A1L2 + A2 L1 = 74 × 103 × π × (25) 2 × (0.358 - 0.1)/4(π × (50) 2/4 × 300 + π × (25) 2 /4× 600)

= 10.61 N/mm2

∴          σ2 = 10.61 × (50) 2/ (25) 2 = 42.44 N/mm2

Both these stresses are tensile.


Related Discussions:- Determine the thermal stress in the bar

What is objective method of assessment, Q. What is objective method of asse...

Q. What is objective method of assessment? Track recording consists of objective method of assessment of the quality of track with the help of sophisticated equipments. A conti

How are freeway bridges built, After measuring the anticipated traffic for ...

After measuring the anticipated traffic for the bridge, cement/reinforced- with- rebar stanchions are spaced over the freeway to accommodate the bridge. An 'off-ramp' from the free

Define the pre-tensioned concrete construction, Define the pre-tensioned co...

Define the pre-tensioned concrete construction We understand that in the pre-tensioned concrete construction, stretched tendons are provided in the concrete moulds at the time

Overtaking sight distance, Overtaking Sight Distance: Overtaking sight...

Overtaking Sight Distance: Overtaking sight distance is calculated on the assumption that the overtaking vehicle (i) travels behind the overtaken vehicle to perceive the clear

Explain basic need of design of shock transmission unit, Explain the Basic ...

Explain the Basic requirement of Design of shock transmission unit? The STU must withstand the specified design load. The stroke of the piston must be bigger than the movement

GRILLAGE FOUNDATION, WHY ONLY I-SECTIONS ARE USED IN CONSTRUCTING GRILLAGE ...

WHY ONLY I-SECTIONS ARE USED IN CONSTRUCTING GRILLAGE FOUNDATION

Define truss analysis-stability, Define Truss analysis-stability   ...

Define Truss analysis-stability   Identify whether a truss is determinate or indeterminate. Identify if the truss is stable or unstable   m = number of membe

Heat and work, How to prove that heat and work are the path functions?

How to prove that heat and work are the path functions?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd