Determine the statement about construction earthwork, Civil Engineering

Assignment Help:

Which of the following statements about construction earthwork are true:

I.  The volume of earth known in its natural state is known as bank-measure; in-situ; in-place; virgin soil. 

II. The volume during transport is known as loose-measure; fluffed; swell; bulk.  

III. The volume after compaction is known as compacted-measure.

IV. The change in volume of earth from its natural to loose state is known as swell.  Swell is expressed as a percentage of the natural volume.

V.  The decrease in volume from its natural state to its compacted state is known as shrinkage.  Shrinkage is expressed as percent increase from the natural state.

Solution:Item V - "Shrinkage is expressed as percent decrease from the natural state".


Related Discussions:- Determine the statement about construction earthwork

Online job, I am M tech in civil engg looking for online assignment job.

I am M tech in civil engg looking for online assignment job.

Determine the major role of construction, Determine the major role of const...

Determine the major role of construction A major part of civil engineering construction involves the use of cement concrete. Concrete has a good compressive strength and works

Dissimilarity in methods of compaction, Question Are there any dissimil...

Question Are there any dissimilarity in methods of compaction between clayey soil material and sandy material ? Answer The three key actions of compaction are static

Highway and traffic, am currently doing my masters degree in highway,pleas...

am currently doing my masters degree in highway,please suggest for me topics i will research on

Mechanics of solid, determine the end slope and deflection in the beam

determine the end slope and deflection in the beam

Determine the reliable moment capacity, Figure 2 details a typical T-beam u...

Figure 2 details a typical T-beam unit in a beam and slab floor with a span of L = 10 m. Determine the reliable moment capacity M ′ for the T-section shown. Take f c ′ = 32

Determining the amount of pre-camber, 1. Domes - You are a construction man...

1. Domes - You are a construction manager in the UAE in charge of a project that involves constructing domes.  Discuss briefly, giving examples, a range of different types of dome

Binomial distribution - exact probability, Binomial Distribution - exact pr...

Binomial Distribution - exact probability: For the binomial distribution having n = 10, y = 0.4, find p (X ≤ 4) using equations and verify that equation gives a better approxi

Dissimilarities between pipe culverts and box culverts?, Question What are ...

Question What are main dissimilarities in applications between pipe culverts and box culverts ? Answer Essentially, culvert resources covered hydraulic structure that conveys fl

What is uniformly distributed surcharge, A retaining wall with a smooth ve...

A retaining wall with a smooth vertical back, 4.5 m high, retains a dry cohesionless backfill level with the top of the wall. γ = 18.6 kN/m 3 and φ = 30°. The backfill carries a u

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd