Determine the stage of cracking moment of pre-stress, Civil Engineering

Assignment Help:

Determine the stage of Cracking moment of pre-stress

 At the stage of transfer of pre-stress in the pre-stressed beam element, only the pre-stressing force and the self weight of the beam may be assumed to act. At this stage, the beam soffit (bottom side) may be assumed to be under compression as the stresses, due to self weight only, are of low magnitude. As the extenal imposed loads are applied on the beam, the compressive stresses (due to pre- stressing) shall decrease due to the tensile stresses generated by external loads. A time comes when these stresses of opposite nature balance each other. At this stage, the soffit of the beam shall be subjected to zero stresses. If extenal loads are further increased, the soffit of the beam shall come under tension. At a particular value of tensile stress the concrete at the location of the soffit of the beam shall crack and visible cracks appear. This tensile stress, at this stage, may be taken to be equal to the modulus of rupture of concrete. The visible cracks have crack widths of the order of 0.01 - 0.02 mm.

 


Related Discussions:- Determine the stage of cracking moment of pre-stress

Embankment construction, Embankment Construction: Selection of Soil...

Embankment Construction: Selection of Soil Soil is the material used for embankment construction, though other materials like rock and fly-ash are also used in specia

Mechanics of solids, what is difference between design moment, nominal, req...

what is difference between design moment, nominal, required, resisting and ultimate moment ?

Moment of Inertia of a T Beam, Calculate the moment of inertia and section ...

Calculate the moment of inertia and section modulus (top and bottom of the beam) about the z-axis of the beam cross section of Fig.

Advantages of casings for mini-piles, Question Advantages of casings ...

Question Advantages of casings for mini-piles ? Answer Left-in casings for mini-piles have next advantages as follows- (i) recover resistance to corrosion of ma

Theories of failure - cases of solids, Theories of Failure - cases of solid...

Theories of Failure - cases of solids: Let us now consider the solid shown in Figure (b). (a)        As the principal stresses are within 260 MPa, the solid is safe ac

Trusses design, does the truss pitch relate to the building''s height?

does the truss pitch relate to the building''s height?

Main problems related with prestressed concrete piles, Question What ar...

Question What are main problems related with prestressed concrete piles ? Answer Origin of Daido piles comes from Japan where these prestressed actual piles are used

Phase, Each physical homogeneous type (solid, liquid orvapour) is a phase. ...

Each physical homogeneous type (solid, liquid orvapour) is a phase. Two or three phases may coexist.  e.g. Ice and water at 0 o C.  Mixtures of gases (e.g. Air) can only be

Acid test - tests on stones, Acid Test: This test is usually carried...

Acid Test: This test is usually carried out on sand stones to examine the presence of calcium carbonate that weakens the weather resisting quality. In this particular  test,

Define lead lag relationships - construction management, Define Lead Lag Re...

Define Lead Lag Relationships 1. A lead is when the successor task begins before the predecessor task is complete 2. A lag is when a successor task does not

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd