Determine the project duration and critical path, Civil Engineering

Assignment Help:

Critical Path - Activity on Node

The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for starts and finishes, use a critical path analysis to determine the project duration and Critical Path.

1029_determine the project duration and Critical Path 1.png

Where there are multiple paths between subsets of activities, analyze the subsets to find the longest time path, then string together the longest subset paths to complete the critical path from start to finish.  To clarify the situation, sketch the project network, showing activities, durations, and the critical path.

a)    Total days to Finish = 41. 

 b)    The critical path is as follows:  START, A, B, C, D, F, G, FINISH

2076_determine the project duration and Critical Path 2.png


Related Discussions:- Determine the project duration and critical path

Chain surveying, describe setting out right angle at given point on a chain...

describe setting out right angle at given point on a chain line and when the point lies outside the chain line

Estimation, What are the various methods of recording measurements? List fi...

What are the various methods of recording measurements? List five items each for various methods of recoding measurements?

Define major ions present in the water, Define Major Ions present in the wa...

Define Major Ions present in the water  Cations:  Calcium, Magnesium, sodium, potassium Anions: Bicorabonate, sulfate, chloride Other ions present: Iron. Manganese, Fluor

Bridge designing, Could someone please help me understand the basics of bri...

Could someone please help me understand the basics of bridge designing

Forces reactions at that point, Mad/Sir What would be the Horizontal and ve...

Mad/Sir What would be the Horizontal and vertical component from this acting force see diagram

Determine the diameter of the footing, A circular footing is resting on a s...

A circular footing is resting on a stiff saturated clay with qu = 250 kN/m 2 . The depth of foundation is 2 m. Verify the diameter of the footing if the column load is 600 kN. S

Statics, Determine the moment of inertia with respect to the x axis for the...

Determine the moment of inertia with respect to the x axis for the shaded area shown (Figure 2) . The dimension is a = 2.00m

Calculate equivalent uniform annual cost for the excavator, Calculate Equiv...

Calculate Equivalent Uniform Annual Cost for the Excavator An earthwork contractor is considering the purchase of a new excavator.  Based on 10% interest, the equivalent unifor

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd