Preliminary settlement analysis for a building indicated a settlement of 50 mm in 4 years and an ultimate settlement of 250 mm. The average pressure increment in the clay stratum was 30 kN/m2.
If the following variations occurred in the assumptions, verify the revised value of ultimate settlement and the settlements at the end of the loading period and that at 3 years after the completion of the building.
(i) The loading period was 2 years, which was not considered in the preliminary analysis.
(ii) Borings shown 25% more thickness for the clay layer than originally assumed.
(iii) The water table got lowered permanently during construction by 1.5 metres.
In some nations such as Britain, specification for concrete doesn'tusually require cube tests for standard mixes of concrete. Quality control of standard mixes in Britain is achiev
what is quick cement? its manufacture and uses? in which building it is used?
Question In General Specification for Civil Engineering Works, designing of roadbase material is based on recipe approach. Give reason. Answer Designing of roadbase
Question Explain components of a typical expansion joint? Answer Dowel bar-This is major component of joint. It serves to guide direction of movement of concrete growth. Therefo
designofboredunderreamedpiles
Question During piling works, normally founding levels of bored piles are definite by using total core recovery or rock quality designation (RQD). Are there any problems by
A flow rate of 200 gpm of oil with u=1.5 x 10-3 lb-sec/ft2 and p=1.7 slug/ft3 occurs in a 4-in pipe. Determine the Reynolds number. Classify the flow as laminar or turbulent. What
Q. Internal force of preloaded fasteners? Force in a bolt in a bolted joint relies on the preloading force applied to it at the time of the tightening operation. For example, w
What are the problems in under water concreting?
matlab applications
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd