Determine the preliminary settlement analysis, Civil Engineering

Assignment Help:

Preliminary settlement analysis for a building indicated a settlement of 50 mm in 4 years and an  ultimate  settlement  of  250 mm.  The average pressure increment in the clay stratum was 30 kN/m2.

If the following variations occurred in the assumptions, verify the revised value of ultimate settlement and the settlements at the end of the loading period and that at 3 years after the completion of the building.

(i) The loading period was 2 years, which was not considered in the preliminary analysis.

(ii) Borings shown 25% more thickness for the clay layer than originally assumed.

(iii) The water table got lowered permanently during construction by 1.5 metres.

 


Related Discussions:- Determine the preliminary settlement analysis

Determine the equivalent of free float, The free float is equal to: a. L...

The free float is equal to: a. Latest allowable event occurrence time + Early finish time b. Earliest event occurrence time + early finish time c. Latest allowable event o

Instruments, description and details about distomat

description and details about distomat

Kings of the world, i want to know more about civil engineering

i want to know more about civil engineering

Levelling, how to establish temporary benchmark

how to establish temporary benchmark

Equllibrium, how to know about he sign convention for equllibrium forces

how to know about he sign convention for equllibrium forces

Municipal Hydraulics, Hello I have an assignment due feb 1st at 3 pm. I wan...

Hello I have an assignment due feb 1st at 3 pm. I wanted to know if it was possible that it gets solved

Torpedo splice triple wedges, Torpedo splice triple wedges In a Torpedo...

Torpedo splice triple wedges In a Torpedo splice triple wedges, shown in Figure, are provided to firmly hold tendon wires. Whole assembly of the splice is housed in a sleeve. L

#frames, confusion on shear force diagram, bending moment diagram

confusion on shear force diagram, bending moment diagram

Temperature requirements for bituminous material, Question In all-purpo...

Question In all-purpose Specification for Civil Engineering Works, it details temperature requirements for bituminous material all through and after mixing. What is cause beh

Road base and base course in flexible carriageway, Road base vs. base cours...

Road base vs. base course in flexible carriageway Roadbase is the most significant structural layer in bituminous pavement. It's designed to take up the function of distributi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd