Determine the output voltage, Electrical Engineering

Assignment Help:

Q. In a differentiating circuit, R=10 kW,and C=2.2μF.If the input voltage goes from 0V to 10 V at a constant rate in 0.4s, determine the output voltage.

Solution:

e0 = RC x d/dt(ei)
     =  RC x dei/dt

R = 10 kW, C = 2.2μF

dei/dt = (10-0)/0.4 = 25 V/s
e0 = (10 x103) x (2.2 x 10-6 ) x 25 = 0.55 V


Related Discussions:- Determine the output voltage

Slip-power controlled wound-rotor induction-motor drives, Q. Slip-power con...

Q. Slip-power controlled wound-rotor induction-motor drives? Slip power is that portion of the air-gap power that is not converted into mechanical power. The methods involving

Measuring equipment of ac-dc voltage and waveforms, Procedures and methods ...

Procedures and methods of the experiments A).      In order to measure the true RMS values of the currents and voltages, students used the true RMS multimeter. It requires two

Explain overhead lines and transformers, Explain Overhead Lines and Transfo...

Explain Overhead Lines and Transformers? Overhead lines absorb reactive power when fully loaded. A line with a current I A, a line reactance of X L ?/phase absorbs I 2 X L V

Characteristics of magnetic field / flux lines, Characteristics of magnetic...

Characteristics of magnetic field / flux lines: i.  Forming a closing loop ii. Did not crossed against each other iii. Has a certain direction iv. Repel among one anot

For the given circuit determine voltage, Q. For the circuit shown in Figure...

Q. For the circuit shown in Figure, determine v out (t).

Explain the construction of jfet, Q. Explain the construction of JFET? ...

Q. Explain the construction of JFET? The basic construction of the p-channel JFET is shown in figure. The major part of the structure is the p-type material that forms the chan

Long-term plans for technical loss reduction, Long-Term Plans for Technical...

Long-Term Plans for Technical Loss Reduction Long-term measures for technical loss reduction include all measures that require to be taken for the improvement of quality and r

Give example for non-maskable interrupts, Trap is called as Non-Maskable in...

Trap is called as Non-Maskable interrupts, which is used in emergency condition.

Off line ups system - power supplies , Off line UPS System Again the tw...

Off line UPS System Again the two  switches  are used in this  type of ups  as online  ups. The difference  is that  here  the main  static  switch  remains normally  ON and UP

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd