Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Activity Based Costing, Multiple Versus Single Overhead Rates, Activity Dri...

Multiple Versus Single Overhead Rates, Activity Drivers Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year: Deoro p

Cost units - terms used in cost accounting, Cost Units - Terms Used in Cost...

Cost Units - Terms Used in Cost Accounting It is the quantitative units of the service or product in relation to those costs are ascertained. The cost unit will be determined

Account analysis method of cost estimation, Account Analysis Method of Cost...

Account Analysis Method of Cost Estimation By Utilizing account analysis, the accountant classifies and examines each ledger account like variable mixed or fixed. Into their v

Long - term capital loss, The Smiths have a long-term capital loss carryove...

The Smiths have a long-term capital loss carryover of $10,000 from 2010. On May 9, 2007, David's uncle, Joe, gave him the family antique gun collection. Based on family records

Absorption costing, Absorption Costing, Marginal Cost and Marginal Costing ...

Absorption Costing, Marginal Cost and Marginal Costing Absorption costing is most often utilized for routine profit reporting and must be utilized for financial accounting rea

Determine equivalent units of the product, Determine Equivalent Units of th...

Determine Equivalent Units of the Product Let assume there are 4,000 units of a product in ending inventory out of that 60 percent are fully complete whereas the remaining are

Determine the interest expense is deductible, Assume the same facts as in 1...

Assume the same facts as in 1A above, except that the interest payment checks were placed on the shareholders' office on December 31, 2012. However, the shareholders are not in the

Direct labour efficiency variances, Direct Labour Efficiency Variances ...

Direct Labour Efficiency Variances It is the difference between the standard hours allowed for the actual production achieved and the hours actually worked, all valued at THE

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd