Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Modified accelerated cost recovery system, Assume new instruments for a fir...

Assume new instruments for a firm cost $18,000 with an additional installation fee of $2,000, both of which are depreciable. Finish the depreciation schedule shown below using the

Plot janitorial labor cost produced on a scattergraph, The number of workd...

The number of workdays varies from month to month due to the number of weekdays, holidays, days of vacation, and sick leave taken in the month. The number of units produced in a

Journal entry to record this transaction, XYZ Corporation recieves $100,000...

XYZ Corporation recieves $100,000 from investors for issuing them shares of its stock. XYZ's journal entry to record this transaction would include a a debit to investment b

Determine the rate of return, A forecasted increase in metal prices has enc...

A forecasted increase in metal prices has encouraged the ABC Resource Company to consider the expansion of the capacity in one of its mine operations in Northern Ontario. For this

Using the dupont formula for rate of return on investment, The vice preside...

The vice president of operations of six layer computer Inc. is evaluating the performance of two divisions organized as investments centers. Invested assets and condensed income st

What are total fixed cost, Corporation has determined the contribution marg...

Corporation has determined the contribution margin ratio is 35% and the income tax rate is 40%. Required: A) Assume break-even volume in dollars is $1,500,000. What are total fixed

Compute the price of each bond, P1 Given the following data: ...

P1 Given the following data:   German Bond U.S. T- Bonds

First in first out or fifo method - work in progress, First In First Out or...

First In First Out or FIFO Method - Work in Progress This method considers merely those costs incurred throughout the recent period.  Equivalent units are calculated given a

Comparison between marginal and absorption costing, Comparison between Marg...

Comparison between Marginal Costing and Absorption Costing There are accountants who favour all costing method. Arguments in favour about absorption costing are specified a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd