Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Elements of cost, Elements of Cost Nearly there are three elements of c...

Elements of Cost Nearly there are three elements of cost - labor, material, and expenses. These are additional divided into indirect and direct material, indirect and direct la

CVP Break even analysis, Bottoms Up company produces high quality sports eq...

Bottoms Up company produces high quality sports equipment. the companie''s racket division manufactures three tennis rackets- the Standard, Deluxe and the Pro that are widely used

Cash, This is difficult to perceive cash maintained in the vault as an inve...

This is difficult to perceive cash maintained in the vault as an investment. Fairly, you would be thinking that if we invest cash, then how can cash itself be an investment? Howeve

Accounting, What are the basic characteristics of a relevant cost? Why are ...

What are the basic characteristics of a relevant cost? Why are future costs not always relevant? Are all relevant costs found in accounting records?

Cost profit volume analysis, COST PROFIT VOLUME ANALYSIS Cost profit vo...

COST PROFIT VOLUME ANALYSIS Cost profit volume (CVP) analysis is an essential tool for profit planning. It can be explained  as - ' a managerial tool showing the relationship a

General ledger, Jp Rhodes started a bowling club called " bowl them over". ...

Jp Rhodes started a bowling club called " bowl them over". The following transactions took place 4 March 2012. 1. Bowling LTD transferred R20 000 bank account of the club as an in

Distribution and selling cost budget, Distribution and Selling Cost Budget ...

Distribution and Selling Cost Budget This is the forecast of all costs incurred in distributing and selling the company's product throughout the budget period. This is closel

Sales revenue variance (srv), SALES REVENUE VARIANCE (SRV) The word 'Sa...

SALES REVENUE VARIANCE (SRV) The word 'Sales Variance' is indicated by the expression 'operating profit variance due to sales' by ICMA.  It is described as 'the difference betw

Identify the relevant per-unit costs, Bakers Bagels LLC produces and sells ...

Bakers Bagels LLC produces and sells 20 types of bagels by the dozen. Bagels are priced at $6.00 per dozen (or $0.50 each) and cost $.020 per unit to produce. The company is consid

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd