Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Issues to consider when making decisions, Q. Issues to consider when making...

Q. Issues to consider when making decisions? At activity level A it can be seen from diagram that sales revenue line intersects the total cost line specifying that this is the

Required the research of the statement of cash flows, This question tested ...

This question tested their knowledge of intended reporting but more importantly requisite them to apply their knowledge and consider the impact from the investors' perspective.

Process costing.., the following information relates to process 3 of a thre...

the following information relates to process 3 of a three stage production process for the month of january 2014. opening inventury 300 units comlete as to; material from proces

Balance sheet, The following information is provided to you concerning Lydi...

The following information is provided to you concerning Lydia Ltd as at 30 June 2012.  Assume a company tax rate of 30%. (i) The balance of rent received in advance in the balan

ECONOMICS, #ques Case Study Electron Control, Inc., sells volt...

#ques Case Study Electron Control, Inc., sells voltage regulators to other manufacturers, who then customize and distribute the products to quality assurance labs for

Marginal costing from financial information for management, prepare a trad...

prepare a trading and profit and loss accounts for the period using marginal costing and absorption costing

Traditional Costing System and Job Order Costing System, Hello, I''m curren...

Hello, I''m currently doing a research on a company and planning an Activity Based Costing system since the company is using Traditional Costing system to allocate the overhead to

Paramecium, Place a prepared slide of Paratuecium under the microscope and...

Place a prepared slide of Paratuecium under the microscope and focus it under low power (5x x 5x) and observe the following: i) It has a cigar-shaped or slipper-shaped body

Method of measuring costs associated with production, Which method of measu...

Which method of measuring costs associated with production is more widely used in practice A. Normal Costing  B. Actual Costing  C. Both are used equally  D. Neither one

Cost accountign, Hi, i need the solution manual for cost accounting manager...

Hi, i need the solution manual for cost accounting managerial emphasis 12 edition

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd