Determine the late start time for activity, Civil Engineering

Assignment Help:

For the project network shown, the late start time (day) for activity "Q" is most nearly:

1829_Determine the Late Start Time for Activity.png

Solution:  List the paths leading to "Q" and calculate the duration for each.

 L M      = 4 + 7 = 11-days 

L N P     = 4 + 3 + 3 = 10-days  

Q's early start time is 10-days

Q's late start time is 11-days


Related Discussions:- Determine the late start time for activity

Illustrate bituminous surfacing over concrete structures, Q. Illustrate Bit...

Q. Illustrate Bituminous surfacing over concrete structures? Usage of bituminous surfacing over concrete structures (for instance existing concrete roads) is widespread to impr

Classification of timber based on grading, Classification Based on Grading:...

Classification Based on Grading: IS 883-1970 classifies the structural timber into 3 grades-select grade, grade I and grade II. The classification is depend on, defects, permi

Define cast iron substructure - inspection of bridge, Define Cast iron subs...

Define Cast iron substructure - Inspection of bridge? Cast Iron also has the problem of corrosion due to atmosphere, which is similar to that of steel. However, in acidic or br

Compass surveying, Compass Surveying: You have studied about the compa...

Compass Surveying: You have studied about the compass and its use for bearings of measuring survey lines. The angular measurements are carried out with prismatic compass that

Relation of the angle of contact between pipe invert, Relation of the angle...

Relation of the angle of contact between pipe invert and bedding material to the load resisting capacity of pipe Minimum crushing strength is a generally adopted parameter for

Determine the reliable moment capacity, Figure 2 details a typical T-beam u...

Figure 2 details a typical T-beam unit in a beam and slab floor with a span of L = 10 m. Determine the reliable moment capacity M ′ for the T-section shown. Take f c ′ = 32

Dynamics, A vehicle for landing on the moon has a mass of 4500kg. The dampe...

A vehicle for landing on the moon has a mass of 4500kg. The damped spring undercarriage system of the vehicle has a stiffness of 450kn/m and a damping ratio of 0.2. The rocket lift

Briefly explain the concept of wind-driven ventilation, Problem (a) Br...

Problem (a) Briefly explain the concept of wind-driven ventilation and outlines its benefits over mechanical/electrical means of ventilation. (b) Various factors and guidel

How double drainage occur, The loading period for a building extended from ...

The loading period for a building extended from Feb., 1957 to Feb., 1959. In Feb., 1962, the average measured settlement was found to be 117 mm. The ultimate settlement was expecte

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd