For the project network shown, the late start time (day) for activity "Q" is most nearly:
Solution: List the paths leading to "Q" and calculate the duration for each.
L M = 4 + 7 = 11-days
L N P = 4 + 3 + 3 = 10-days
Q's early start time is 10-days
Q's late start time is 11-days
Explain coulomb''s wedge theory-definition and derivation
structure of exogenous trees
what is torsional moment of resistance
In engineering, the code-allowable withdrawal force is zero, due to the wood expands and contracts over time and the nail pullout force can decrease to zero
what are port facilities
Ask question #Minimum 100E. The regulations and specifications that followed for compaction works for earth dam in Oman words accepted#
brief detail about ships stresses
#questionwhat is the shear force and bending moment..
a lighthouse standing on the cliff observed from two open boats A and B in a vertical plane thourgh the lighthouse.the angle of elevation of the top of the lighthouse viewed from B
Q. How can you design Side Slope of bank? Angle of bank should be flatter than angle of repose of pitching material. Angle of repose of sand is 2:1 while that of stone is about
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd