A chemical works produces an aqueous effluent at above ambient temperature. The Environmental Agency insists that before the effluent is discharged to the river, it must be cooled.
A forced draught counter current cooling tower is available. When tested it provided the following results:
Determine the approximate number of gas transfer units achieved. DATA:
Heat capacity of liquid water: 4.19 kJ kg K .
[It may be assumed that the resistance to heat transfer in the liquid phase is negligible].
Principal Planes and Principal Stresses: Define the Principal Planes and Principal Stresses. Sol.: When an element in strained body is under action of plane stresses, it i
as diesel engine gives more milege than petrol engine then why we are using petrol engine..
Multiple Spot Welding This is a modification of spot welding, in which two or more than two welds can be obtained simultaneously from each transformer secondary. For specific pro
slidder crank chain / reciprocating engine mechanism pics
First Law for Closed System Undergoing Change of State - thermodynamics: In accordance to first law, when system undergoes a thermodynamic process (change of state) heat and w
Q. Mechanical design of the blowdown systems? Mechanical design of the blowdown systems shall be sized for a continuous blowdown of a minimum of 1.0% of MCR. Fabricator may re
Q. Define Current for electrical resistance welding? - With other parameters kept constant, the temperature in resistance welding is regulated by controlling the magnitude a
a compound cylinder is composed of a tube of 250mm internal diameter at 25mm wall thickness.it is shrunk on to a tube of 200mm internal diameter. the radial pressure at the junctio
a masonry pier 3m*4m supports vertical load of 600kn at point (1.2,1),find stresses at corner of pier
Q. Inspection and testing of vessels? The Vendor shall be responsible for all inspection and testing. WorleyParsons reserves the right to inspect vessels or parts of vessels at
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd