Determine the head added by the pump, Civil Engineering

Assignment Help:

Primary effluent wastewater at 60oF (v = 1.217 x 10-5) is pumped to the top of a trickling filter (TF) a total of 75 vertical feet through schedule-40 welded steel pipe. The flow rate is 8.64 mgd (6,000 gpm). The suction piping is 24 in diameter straight piping (velocity of 4.8 fps), has a length of 10 ft and an energy loss of 0.03 ft. The discharge piping is 18 inch diameter (velocity of 8.6 fps), has a length of 177 ft and an energy loss of 3.6 ft. The total length of the suction and discharge piping is 187 ft. Minor losses exist in the discharge piping only and total an equivalent length of 137 ft. The wet well and TF distribution arms are open to the atmosphere. The pump efficiency is 85%. 1.  Determine the head added by the pump hA:

1. Determine the head added by the pump hA:

hA = (PD/γ - PS/ γ) + ( v2 D/2g - v2 S/2g) + ZD - ZS + hf ZD - ZS = 75 ft

v2 dis/2g = (8.6) 2 /64.4 = 1.15 ft v2 suc/2g = (4.8) 2 /64.4 = 0.35 ft

total hf = 0.03 ft + 3.6 ft = 3.62 ft

hA = 0 + (1.15 ft - 0.35 ft) + 75 ft + 3.62 ft = 79.4 ft

2.  Determine the hydraulic horsepower required:   

whp = hAQ(sp gr)/3956=((79.4 ft)(6000 gpm)(1))/3956 = 120 HP

3.  Determine the brake horsepower required:

bhp = whp/pump efficiency = 120 HP / 0.85 = 142 HP

4.  The friction or heat horsepower is

bhp-whp = 142 HP - 120 Hp = 22 HP


Related Discussions:- Determine the head added by the pump

Briefly explain about artificial cut offs, Q. Briefly explain about Artific...

Q. Briefly explain about Artificial cut offs? Alignment of a cut off is chosen so that approach and exit ends remain more or less tangential to the river course. A cut off can

Applied physics, Write the principle of reversibility of light.

Write the principle of reversibility of light.

Explain the unit hydrograph - hydrology, Define Unit Hydrograph Hydrogr...

Define Unit Hydrograph Hydrograph of one inch or 1cm of precipitation over a drainage basin area (watershed). It is the base hydrograph from which other hydrographs can be dete

Enumerate the variation in tendon stress, Enumerate the Variation in tendon...

Enumerate the Variation in tendon stress In post-tensioned construction, several tendons are simultaneously stretched and anchored at the ends. It is assumed that all tendons

Roads in hilly areas, Roads in Hilly Areas: (a)        The alignment s...

Roads in Hilly Areas: (a)        The alignment selected should attain the changes in elevation by adopting the ruling gradient to the maximum length. Limiting and exceptional

Lime, what is stone lime shall lime and kankar lime

what is stone lime shall lime and kankar lime

What are the causes of building collapse, The Passage of time is single rea...

The Passage of time is single reason. Buildings also collapse because of weak foundations. Earthquakes, hurricanes and other natural disasters can also damage the structure of the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd