Determine the head added by the pump, Civil Engineering

Assignment Help:

Primary effluent wastewater at 60oF (v = 1.217 x 10-5) is pumped to the top of a trickling filter (TF) a total of 75 vertical feet through schedule-40 welded steel pipe. The flow rate is 8.64 mgd (6,000 gpm). The suction piping is 24 in diameter straight piping (velocity of 4.8 fps), has a length of 10 ft and an energy loss of 0.03 ft. The discharge piping is 18 inch diameter (velocity of 8.6 fps), has a length of 177 ft and an energy loss of 3.6 ft. The total length of the suction and discharge piping is 187 ft. Minor losses exist in the discharge piping only and total an equivalent length of 137 ft. The wet well and TF distribution arms are open to the atmosphere. The pump efficiency is 85%. 1.  Determine the head added by the pump hA:

1. Determine the head added by the pump hA:

hA = (PD/γ - PS/ γ) + ( v2 D/2g - v2 S/2g) + ZD - ZS + hf ZD - ZS = 75 ft

v2 dis/2g = (8.6) 2 /64.4 = 1.15 ft v2 suc/2g = (4.8) 2 /64.4 = 0.35 ft

total hf = 0.03 ft + 3.6 ft = 3.62 ft

hA = 0 + (1.15 ft - 0.35 ft) + 75 ft + 3.62 ft = 79.4 ft

2.  Determine the hydraulic horsepower required:   

whp = hAQ(sp gr)/3956=((79.4 ft)(6000 gpm)(1))/3956 = 120 HP

3.  Determine the brake horsepower required:

bhp = whp/pump efficiency = 120 HP / 0.85 = 142 HP

4.  The friction or heat horsepower is

bhp-whp = 142 HP - 120 Hp = 22 HP


Related Discussions:- Determine the head added by the pump

Time to remove formwork to cater for early thermal movement, Q. Time to rem...

Q. Time to remove formwork to cater for early thermal movement? Let's take a circular column as an illustration to explain effect of internal restraint to thick sections.  W

Cost estimating, I would like to know if anyone can help me with my const e...

I would like to know if anyone can help me with my const estimating project

Theodolote, List out the permanent adjustments of dumpy level.

List out the permanent adjustments of dumpy level.

Whole barings, Ask question #Minexaple of wholeiwhole baring 100 words acce...

Ask question #Minexaple of wholeiwhole baring 100 words accepted#

Transportatoin engineening, explain the construction while aligning roads o...

explain the construction while aligning roads on hilly areas

Bricks, BRICKS Brick is obtained by moulding good clay into a block, wh...

BRICKS Brick is obtained by moulding good clay into a block, which is dried and then burnt. It is the oldest building block to replace stone. Manufacture of brick started havin

Distomat, short note of distomat

short note of distomat

Construction of the building, a) Certain data for the materials used in the...

a) Certain data for the materials used in the construction of the building, e,g, insulation, building materials, air spaces, etc.  b)  Draw, with appropriate dimensions, the cro

Dense bituminous macadam, Dense Bituminous Macadam: A Dense Bituminou...

Dense Bituminous Macadam: A Dense Bituminous Macadam (DBM) is a close-graded premix material having a voids content of 5-10 per cent. Two gradings are normally adopted :

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd