Determine the head added by the pump, Civil Engineering

Assignment Help:

Primary effluent wastewater at 60oF (v = 1.217 x 10-5) is pumped to the top of a trickling filter (TF) a total of 75 vertical feet through schedule-40 welded steel pipe. The flow rate is 8.64 mgd (6,000 gpm). The suction piping is 24 in diameter straight piping (velocity of 4.8 fps), has a length of 10 ft and an energy loss of 0.03 ft. The discharge piping is 18 inch diameter (velocity of 8.6 fps), has a length of 177 ft and an energy loss of 3.6 ft. The total length of the suction and discharge piping is 187 ft. Minor losses exist in the discharge piping only and total an equivalent length of 137 ft. The wet well and TF distribution arms are open to the atmosphere. The pump efficiency is 85%. 1.  Determine the head added by the pump hA:

1. Determine the head added by the pump hA:

hA = (PD/γ - PS/ γ) + ( v2 D/2g - v2 S/2g) + ZD - ZS + hf ZD - ZS = 75 ft

v2 dis/2g = (8.6) 2 /64.4 = 1.15 ft v2 suc/2g = (4.8) 2 /64.4 = 0.35 ft

total hf = 0.03 ft + 3.6 ft = 3.62 ft

hA = 0 + (1.15 ft - 0.35 ft) + 75 ft + 3.62 ft = 79.4 ft

2.  Determine the hydraulic horsepower required:   

whp = hAQ(sp gr)/3956=((79.4 ft)(6000 gpm)(1))/3956 = 120 HP

3.  Determine the brake horsepower required:

bhp = whp/pump efficiency = 120 HP / 0.85 = 142 HP

4.  The friction or heat horsepower is

bhp-whp = 142 HP - 120 Hp = 22 HP


Related Discussions:- Determine the head added by the pump

Pressure distribution under rigid and flexible footings, Pressure distribut...

Pressure distribution under rigid and flexible footings For rigid and thick footings, pressure distribution under the footings is generally presumed to be linear. If symmetric

Working from whole to part in survey, a clear illustration about working to...

a clear illustration about working to part principle and some examples

Determine the major and minor principal effective stresses, The stresses ac...

The stresses acting on the plane of maximum shearing stress by a given point in sand are as follows: total normal stress = 250 kN/m 2 ; pore-water pressure = 88.5 kN/ m 2 ; shearin

Solis mensuration, the two side are 17 cm and 28 cm long. and the lenght of...

the two side are 17 cm and 28 cm long. and the lenght of the drawn to the third side is equal to 19.5cm. find tghe distance from an endpoint of this medianto the longest s8ide

Earth Pressure Theories.., While calculating Active Earth Pressure, do Colo...

While calculating Active Earth Pressure, do Coloumb''s Theory and Rehbann''s theory yield same results? I''ve tried and didn''t get the same results. Where might be the mistake?

State the ground water levels, Ground Water Levels The location of the...

Ground Water Levels The location of the ground water level is essential for deep excavation, water-logged areas. The existing wells in the nearby vicinity of the proposed site

Show the overlays on concrete bridge deck, Q. Show the Overlays on concrete...

Q. Show the Overlays on concrete bridge deck? After years of servicing, some overlays can be applied on the top surface of bridges. Overlays on concrete bridge decks achieve th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd