Determine the head added by the pump, Civil Engineering

Assignment Help:

Primary effluent wastewater at 60oF (v = 1.217 x 10-5) is pumped to the top of a trickling filter (TF) a total of 75 vertical feet through schedule-40 welded steel pipe. The flow rate is 8.64 mgd (6,000 gpm). The suction piping is 24 in diameter straight piping (velocity of 4.8 fps), has a length of 10 ft and an energy loss of 0.03 ft. The discharge piping is 18 inch diameter (velocity of 8.6 fps), has a length of 177 ft and an energy loss of 3.6 ft. The total length of the suction and discharge piping is 187 ft. Minor losses exist in the discharge piping only and total an equivalent length of 137 ft. The wet well and TF distribution arms are open to the atmosphere. The pump efficiency is 85%. 1.  Determine the head added by the pump hA:

1. Determine the head added by the pump hA:

hA = (PD/γ - PS/ γ) + ( v2 D/2g - v2 S/2g) + ZD - ZS + hf ZD - ZS = 75 ft

v2 dis/2g = (8.6) 2 /64.4 = 1.15 ft v2 suc/2g = (4.8) 2 /64.4 = 0.35 ft

total hf = 0.03 ft + 3.6 ft = 3.62 ft

hA = 0 + (1.15 ft - 0.35 ft) + 75 ft + 3.62 ft = 79.4 ft

2.  Determine the hydraulic horsepower required:   

whp = hAQ(sp gr)/3956=((79.4 ft)(6000 gpm)(1))/3956 = 120 HP

3.  Determine the brake horsepower required:

bhp = whp/pump efficiency = 120 HP / 0.85 = 142 HP

4.  The friction or heat horsepower is

bhp-whp = 142 HP - 120 Hp = 22 HP


Related Discussions:- Determine the head added by the pump

Determine the total active thrust by rebhann''s method, A retaining wall 3....

A retaining wall 3.6 m high supports a dry cohesion less backfill with a plane ground surface sloping upwards at a surcharge angle of 20° from the top of the wall. The back of the

What is the cost of phoenix activity, Q. What is the cost of phoenix activi...

Q. What is the cost of phoenix activity? Phoenix activity has a range of impacts on the Australian economy. Employees lose entitlements when phoenix activity has occurred and w

Edge piles take up more loads than central piles, Edge piles take up more l...

Edge piles take up more loads than central piles in rigid cap Because of the effect of interaction of individual piles, central piles tend to settle more than the edge piles w

Calculate the total labor cost per cubic yard, A contractor will place 90-c...

A contractor will place 90-cubic yards of concrete for a housekeeping pad on the rooftop of a 36-ft tall building. Site conditions dictate that the safest and best method of placem

Define the degree of saturation and soil moisture content, Establish the r...

Establish the relationship among degree of saturation, soil moisture content, definite gravity of soil particles, and void ratio. The volume of an undisturbed clay sample having

Free- fall concrete placement in bored piles, Q. Free- fall concrete placem...

Q. Free- fall concrete placement in bored piles? Based on the research by STS Consultants Ltd it was found that concrete placed by free falling below 120 feet will not suffer f

Bending stress distribution diagram, i want to know how bending stress dist...

i want to know how bending stress distribution in c section

Shear moment diagram, how to draw shear moment diagram for cantileaver beam...

how to draw shear moment diagram for cantileaver beam

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd