Determine the head added by the pump, Civil Engineering

Assignment Help:

Primary effluent wastewater at 60oF (v = 1.217 x 10-5) is pumped to the top of a trickling filter (TF) a total of 75 vertical feet through schedule-40 welded steel pipe. The flow rate is 8.64 mgd (6,000 gpm). The suction piping is 24 in diameter straight piping (velocity of 4.8 fps), has a length of 10 ft and an energy loss of 0.03 ft. The discharge piping is 18 inch diameter (velocity of 8.6 fps), has a length of 177 ft and an energy loss of 3.6 ft. The total length of the suction and discharge piping is 187 ft. Minor losses exist in the discharge piping only and total an equivalent length of 137 ft. The wet well and TF distribution arms are open to the atmosphere. The pump efficiency is 85%. 1.  Determine the head added by the pump hA:

1. Determine the head added by the pump hA:

hA = (PD/γ - PS/ γ) + ( v2 D/2g - v2 S/2g) + ZD - ZS + hf ZD - ZS = 75 ft

v2 dis/2g = (8.6) 2 /64.4 = 1.15 ft v2 suc/2g = (4.8) 2 /64.4 = 0.35 ft

total hf = 0.03 ft + 3.6 ft = 3.62 ft

hA = 0 + (1.15 ft - 0.35 ft) + 75 ft + 3.62 ft = 79.4 ft

2.  Determine the hydraulic horsepower required:   

whp = hAQ(sp gr)/3956=((79.4 ft)(6000 gpm)(1))/3956 = 120 HP

3.  Determine the brake horsepower required:

bhp = whp/pump efficiency = 120 HP / 0.85 = 142 HP

4.  The friction or heat horsepower is

bhp-whp = 142 HP - 120 Hp = 22 HP


Related Discussions:- Determine the head added by the pump

Length is constructed in first phase of construction, In construction of a ...

In construction of a two-span bridge (span length = L) by using span-by-span construction, why is the length of about 1.25L bridge segment is constructed in first phase of construc

How to find back bearings?, Example: The following fore bearings were ...

Example: The following fore bearings were observed respectively for lines, AB, BC, CD, DE, EF and FG. Find out their back bearings: (i) 148°                          (ii

Role of rebate in typical construction joint, Question What is role of reba...

Question What is role of rebate in typical construction joint ? Answer Construction joints are formed on sites to facilitate construction procedure. Though, if improperly constr

Methods of constructing roads in marshy areas, Methods of Constructing Road...

Methods of Constructing Roads in Marshy Areas: The following methods are adopted for constructing roads in marshy areas: (a) Removal of soft soil and replacement with good

Application of quadratic equation, list some applications of quadratic equa...

list some applications of quadratic equation in civil engineering

Passenger terminal building, Passenger Terminal Building: Importanc...

Passenger Terminal Building: Importance In a civil airport, the passenger terminal building is the centre of all activities. It services both inbound and outward boun

Raft and beam foundation, why is weight of raft not considered in structura...

why is weight of raft not considered in structural design of raft and beam

Spacing of manholes in straight sections, Question Spacing of manhole...

Question Spacing of manholes in straight sections for diverse pipe sizes is stated in Storm water Drainage Manual. How are figures arrived on? Answer For pipe size

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd