Determine the grade rod reading at station, Civil Engineering

Assignment Help:

A section view of a proposed roadway is shown in Figure 1 with an existing grade point elevation of 100-ft. The proposed roadbed finish grade elevation at station 50+00 is 95.00-ft and slopes at 2% grade. The grade rod reading at station 55+00 is most nearly:

Solution:

The Height of Instrument elevation can be calculated:

HI = 100.00-ft + 8.5-ft = 108.5-ft

The grade rod reading at station 50+00 is calculated by:

HI - station 50+00 elevation = 108.50-ft - 95.00-ft = 13.50-ft

The distance between station 50+00 and 55+00 is 500-ft

The slope is set at 2%, therefore; 2% x 500-ft = 10-ft elevation difference between stations.

Add the results of the proposed roadbed slope which is 10-ft to the grade rod reading at station 50+00 to obtain the grade rod reading at station 55+00 which is 23.50-ft.


Related Discussions:- Determine the grade rod reading at station

Critical-depth relationship, If y1 and y2 are alternate depths of a rectang...

If y1 and y2 are alternate depths of a rectangular channel show that Yc³ =2y1²y2²/(y1+y2) Also specific energy E = y1²+y1y2+y2²/(y1+y2)

Analysis of the two stage construction, A County is planning to build a new...

A County is planning to build a new roadway connector in the rapidly developing area of the county. The road can be built at a reduced capacity now for $30 million and can be widen

Continuous prestressed concrete beam design , Assignment:-Continuous Prestr...

Assignment:-Continuous Prestressed Concrete Beam Design A cast in-place 3-span prestressed concrete T-beam is to be designed. The T-beam concsists of an 8-in thick reinforced

Explain the coordinate system, Explain the Coordinate System 1. A Bench...

Explain the Coordinate System 1. A Benchmark provides only elevation data. 2. Coordinate System provides northing and easting coordinates within a defined system. 3. Coor

Equipments required for under water inspection of bridge, Define Equipments...

Define Equipments and tools required for under water Inspection of Bridge? Since the underwater inspection of stone masonry substructures involve only a cursory inspection of t

Human values, give the two aspects of honesty& explain

give the two aspects of honesty& explain

Shear and tensile strength, What is the difference between shear and tensil...

What is the difference between shear and tensile strength? Ans) Tensile Strength for a Bolt is explained by applying a Force along it long axis. Shear Strength for a Bolt is exp

Explain box jig, Explain Box jig? a) The box jig is so named because of...

Explain Box jig? a) The box jig is so named because of its box shaped construction, closed from most of the sides. b) It is normally designed for those components having awk

Elimination of formwork with reasons, Question For a l ong slender structur...

Question For a l ong slender structure similar to beams, propping is compulsory after elimination of formwork with reasons? Answer After concreting, time at which arresting of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd