The free float is equal to:
a. Latest allowable event occurrence time + Early finish time
b. Earliest event occurrence time + early finish time
c. Latest allowable event occurrence time - Early finish time
d. Earliest event occurrence time - Early finish time
Ans: Earliest event occurrence time - Early finish time
The obstacles that the students of civil engineering face when it comes to produce a good piece of writing in English
Question Soil nails are mostly designed for stabilization of key slips . How can designer cater for stability of minor slips? Answer There are many methods to treat mi
Q. How to determine the frequency of flood? Flood frequency may be estimated preferably from flood records, if available, for a number of years or they may be based on rainfall
Surface Dressing: Surface dressing is an application of a thin film of bituminous binder followed by a coat of aggregates of single size, rolled into position. Surface dressi
the importance of softening point of a bitumen material in the design of a pavement
How to use plaster cement in sand? Cement sand plaster is a layer of cement & sand mortar that is applied over walls made of brickwork, cement block work, RCC walls and RCC co
Explain Hydrology and Evaporation Hydrology: Study of the circulation of water in nature. Evaporation: Water in the liquid state transforms to vapor. Evaporation occurs f
Q. What do you mean by Distressing? Distressing is the operation under taken with or with out rail tensors to secure stress free condition in the LWR at a desired rail temperat
The force exerted to the Tacoma narrows bridge was initially the wind resistance. The wind resistance cause the entire bridge to act as a system with forced vibration with damping.
Explain the Statements about the Construction Contract Process I. Surety bond assures the project owner a guarantee of funds equivalent to a promissory note. The surety bond is
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd