Determine the direct materials cost variance, Cost Accounting

Assignment Help:

Question

PART A

Borrico ltd manufacture a single product and they had currently introduced a system of budgeting and variance analysis.

The subsequent information is available for the month of July 2011:

1.

 

Budget

 

Rs

Actual

 

Rs

 

Direct materials

200,000

201,285

 

Direct labour

313,625

337,500

 

Variable manufacturing overhead

141,400

143,000

 

Variable sales overhead

64,400

69,500

 

Fixed manufacturing overhead

75,000

71,000

 

Administration costs

150,000

148,650

2. Standard costs were:

Direct labour 48,250 hours at $6.50 per hour

Direct materials 20,000 kg at $10 per kg

3. Actual manufacturing costs were:

Direct labour 50,000 hours at $6.75 per hour. Direct materials 18,900 kg at $10.65 per kg

4. Budgeted sales were 20,000 units at $50 a unit.

Actual sales were:

15,000 units at $52 a unit

5,200 units at $56 a unit

5. There was no work in progress or inventory of finished goods

Required:

(a) Determine the direct materials cost variance, direct materials usage variance and direct materials price variance.

(b) Evaluate the direct labour cost variance, direct labour efficiency variance and direct labour rate variance.

(c) What  use  can  the  management  of  Borrico  Ltd  make  of  the  variances calculated in (a) and (b) above.

PART B

XYZ company manufacture and market a specific product which they sell at $20 per unit. Current production is 400,000 units per month which represents 80% of capacity. They have the opportunity to utilize their surplus capacity by selling their product at Rs 13 per unit to an outside buyer.

Total costs for the last month were $5,600,000 of which $1,600,000 were fixed cost. This represented a total cost of $14 per unit.

Required:

Based on the provided financial information only, should XYZ company accept the order?

PART C

Describe the opportunity cost concept and why it is used in decision making.


Related Discussions:- Determine the direct materials cost variance

Requirements of uniform costing, Requirements of Uniform Costing 1. Un...

Requirements of Uniform Costing 1. Uniform costing systems must process the given features as: 2. Cost reports and statements should be organized and laid out in a same for

Tracking direct materials, Tracking Direct Materials Jack keeps full re...

Tracking Direct Materials Jack keeps full records of the material released to each job. When Donnie gathered up light bulbs, tape, breakers, wire, and wire nuts on the morning

Modified accelerated cost recovery system, Assume new instruments for a fir...

Assume new instruments for a firm cost $18,000 with an additional installation fee of $2,000, both of which are depreciable. Finish the depreciation schedule shown below using the

Demerits of break even point, DEMERITS OF BREAK EVEN POINT 1. It pays n...

DEMERITS OF BREAK EVEN POINT 1. It pays no attention to considerations like effect of government policy changes, changes in the marketing environment etc 2. Fixed cost, enti

Determine the optimum cost-time schedule , You have just been assigned to r...

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted,

Changes in variable cost and selling price per unit, Changes in Variable Co...

Changes in Variable Cost and Selling Price per Unit The contribution sales ratio is affected by any change in variable cost or selling price per unit. This ratio is a mea

P/v ratio., The sale turnover and profit during two period were as followin...

The sale turnover and profit during two period were as following Period 1=Sales Rs.20 Laks, and Profit Rs.2 Laks Period 2=Sales Rs.30 Laks, and Profit Rs.4.Laks Calculate P/V Ratio

How would i calculate the debt amortization, How would I calculate the debt...

How would I calculate the debt amortization for a bond issued at discount with a maturity of 12 years, market interest rate at issue 10% annually, 5% semi annually, and has a state

Attainable standards and current standards, Attainable Standards and Curren...

Attainable Standards and Current Standards Although the standard must be set high sufficient that achievable and it has to be worked for. Attainable standards must provide a c

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd