Determine the cost of compensation, Civil Engineering

Assignment Help:

The soil in a borrow pit has a void ratio of 0.90. A fill-in-place volume of 20,000 m3 is to be constructed with an in-place dry density of 18.84 kN/m3.

If the owner of borrow area is to be compensated at Rs. 1.50 per cubic metre of excavation, verify the cost of compensation

 


Related Discussions:- Determine the cost of compensation

Benchmark, 1. Where permanent bench of india located ? 2. use of Permanent ...

1. Where permanent bench of india located ? 2. use of Permanent BenchMark ?

Maintenance of concrete roads, Maintenance of Concrete Roads: The mai...

Maintenance of Concrete Roads: The main defects that show up in a concrete road are : (a) cracks (b) loss of sealant (c) spalling at joints (d) loss of texture

Surveying, what is the trignomerty leveling

what is the trignomerty leveling

Plane table sureying, discuss the resection method of plane table sureying ...

discuss the resection method of plane table sureying in detail

#title., Ask question #Minimum 100 words accepted2812539076# you

Ask question #Minimum 100 words accepted2812539076# you

Theory of structure, How to convert uniformly varying load to point load

How to convert uniformly varying load to point load

Paints., contituents of paints

contituents of paints

Relation of the angle of contact between pipe invert, Relation of the angle...

Relation of the angle of contact between pipe invert and bedding material to the load resisting capacity of pipe Minimum crushing strength is a generally adopted parameter for

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd