Common ways to present the project schedule include all except:
a. Gantt charts
b. Milestone charts
c. PERT charts
D. Project Network Diagrams with dates added
Solution: A PERT chart represents task dependencies but does not represent activity durations or dates.
Q. Indirect tensile strength in water-retaining structures ? Crack width formation is dependent on the early tensile strength of concrete. Principle of critical steel ratio als
Example: Convert the following reduced bearings into whole circle bearings: (i) N 65° E (ii) S 43° 15′ E (iii) S 52° 30′ W (iv)
layout of harbour
Explain the Tertiary Treatment for Wastewater Tertiary Treatment: in cases where secondary treatment is not adequate (particularly if the discharges are into a sensitive water
#questio
fixed beam processer
Q. Write short note on Surplus Store? Comprise stores which are surplus to requirements and include materials released from renewals and replacements as well as from dismantled
State the effect of stretched tendons The effect of stretched tendons inside the concrete components is just like a stretched spring. If a spring is stretched it would like to
The wet weight of a sample is missing in a Proctor test. The oven-dry weight of this sample is 189 N. The volume of the mould used is 1000 cm 3 . If the degree of saturation of
flow chart for wet process
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd