Determine the common ways to present the project schedule, Civil Engineering

Assignment Help:

Common ways to present the project schedule include all except:

a. Gantt charts

b. Milestone charts

c. PERT charts

D. Project Network Diagrams with dates added  

Solution:  A PERT chart represents task dependencies but does not represent activity durations or dates.


Related Discussions:- Determine the common ways to present the project schedule

Deep foundation, At what places deep foundation are made?

At what places deep foundation are made?

Show the specification of bricks, Q. Show the Specification of Bricks? ...

Q. Show the Specification of Bricks? Specification of Ist class Bricks- 1. Table moulded and wire cut. 2. It should have edges and parallel faces. 3. If struck with ha

Void ratio and dry density of a soil, Q. Define water content, void ratio ...

Q. Define water content, void ratio and dry density of a soil. If wet density of a soil is 1.9 gm per cm at a moisture content of 24%, what will be its dry density?  Ans. - W

Building Technology, which IS code give details about Strength of Brick?

which IS code give details about Strength of Brick?

Function of a separation membrane amid concrete pavement, Question What...

Question What is main function of a separation membrane amid concrete pavement slab and sub-base ? Answer Division membrane between concrete pavement slab and sub-bas

R.c.c square overhead tank, problems in estimating especially in reinforcem...

problems in estimating especially in reinforcement works

Specification of flooring for heavy repair shed, Q. Specification of Floori...

Q. Specification of Flooring for heavy repair shed? Scope for use - For flooring for heavy repair shed, Surface hardened concrete flooring can used. In this type of flooring,

Theodolite, convert whole circle bearing to reduce bearing formula

convert whole circle bearing to reduce bearing formula

Temporary repairs to rail fracture, Q. Temporary Repairs to rail fracture? ...

Q. Temporary Repairs to rail fracture? If a welding party is not readily available, the fracture shall be repaired by using a cut-rail (not less than 4 meter long) and clamped/

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd