Common ways to present the project schedule include all except:
a. Gantt charts
b. Milestone charts
c. PERT charts
D. Project Network Diagrams with dates added
Solution: A PERT chart represents task dependencies but does not represent activity durations or dates.
The classification as soft wood and hard wood has commercial significance. The difference between soft wood and hard wood is described below: The color of soft wood is light
Pavement of evaluation
CRACKS
Water Bound Macadam: Water Bound Macadam (WBM) is a dense and compact course of a road pavement composed of stone aggregates held together by a film consisting of gravel or s
underground installations
Question Is it resourceful that engineers rely solely on Hiley's formula in designing of H-piles? Answer About 90 percent of H-piles accept Hiley's formula for desig
3-d figure of line ranger
fabrication methods of ironmongery
Question What is dissimilarity between air chamber and surge tank ? Answer Air chambers and surge tanks are usually set up in watermain to ease stress on schem
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd