Common ways to present the project schedule include all except:
a. Gantt charts
b. Milestone charts
c. PERT charts
D. Project Network Diagrams with dates added
Solution: A PERT chart represents task dependencies but does not represent activity durations or dates.
The integration of strain over the depth is settlement. The method of producing the settlement is non-recoverable when the intensity of stress is removed. Hence, a permanent reduc
Question What are major ways to undertake negative skin friction ? Answer (i) Utilize slender pile sections since smaller pile area when subject to same working load
gabbion retaining wall design
Define Wastewater treatment Processes The wastewater treatment processes that we design mimic the processes that occur in the nature (for example processes that occur in a flow
Question Will it advantageous to use concrete of very high power for example exceeding 60MPa? What are potential problems connected with high strength concrete ? Answer To in
whast prime coat?
Atomic radius of HCP
IS CODES FOR BUILDING MATERIALS AND CONSTRUCTION The following is the list of some of the IS code giving requirements for building materials: IS 269-1989. Specification for ord
three point problem
Q. What is the minimum prescribed track structure for LWR / CWR on Broad Gauge? Ans.- 1. General - The minimum length of LWR depends upon - i. Range of temporary variati
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd