Common ways to present the project schedule include all except:
a. Gantt charts
b. Milestone charts
c. PERT charts
D. Project Network Diagrams with dates added
Solution: A PERT chart represents task dependencies but does not represent activity durations or dates.
Q. What is Material at site Return? The authority is executive charge of a work should be responsible for holding in safe custody for controlling the consumption and to the ext
define alternative depths
What is the shrinkage factor
define couple
Grading Limits for Fine Aggregates graph drawings
State the process to calculate the Transmission Length It is the distance required at the end of a concrete member for developing the maximum tendon stress by bond.
Cleaning and greasing of steel sliding bearings : Following equipments are required for greasing of steel sliding bearings: 1. Jacks (50 ton capacity) - 2 nos. 2. Hard wo
find the pressure head at 2-2 if the rate of flow in pipe is 0.36m^3/s
i need simple ans for this question tell me precaution of dampness
Question What is consideration in selecting an orientation of wing walls in designing of bridge abutments ? Answer There are three familiar arrangements of wing walls in
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd