Common ways to present the project schedule include all except:
a. Gantt charts
b. Milestone charts
c. PERT charts
D. Project Network Diagrams with dates added
Solution: A PERT chart represents task dependencies but does not represent activity durations or dates.
A contractor has selected a W14x74 simply supported beam for a high rise construction project. The span length for the provided beam is set at 30 feet. The maximum factored appli
who to we calculate the RL at first point.
what is the application of silica,aluminaand magnesium in bricks?
how does wrong calculations in normal stress cause partial or total collapse of a building?
how to calculate the size of drainage(box) width and height?
Q. Minimum and maximum distance between bars? Minimum distance between bars and maximum distance between bars In some codes, a minimum distance amid bars is specified to
gabbion retaining wall design
The cross-section of exogenous tree is as shown in given figure.The following components are visible to the naked eye: Cross-section of exogeneous tree 1. P
is the seismic joints like falling joints ? thanks :)
Explain the Variable Conditions of River Flow and Health State? The variable conditions of river flow and health state of structure demands constant supervision. Although scou
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd