Common ways to present the project schedule include all except:
a. Gantt charts
b. Milestone charts
c. PERT charts
D. Project Network Diagrams with dates added
Solution: A PERT chart represents task dependencies but does not represent activity durations or dates.
diffrence between cumilative compensative error
does felid scope in civil eng. if we start consiltancy job
define of couple
An oven-dry soil sample of volume 225 cm3 weighs 3.90 N. If the grain specific gravity is 2.72, determine the void-ratio and shrinkage limit. What will be the water content which w
use of rapid sand filter in grey water treatment units
triangle of force
meaning of scale factor
DOES A GAUGE BOX OF THE SIZE LIKE 50,40,30 MM EXISTS?
Dense Bituminous Macadam: A Dense Bituminous Macadam (DBM) is a close-graded premix material having a voids content of 5-10 per cent. Two gradings are normally adopted :
State the term - calculation of deformation of concrete For the calculation of deformation of concrete at some stage before the maximum shrinkage is reached, it may be assumed
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd