Determine the allowable pressue, Civil Engineering

Assignment Help:

The data profile as shown in Figure is obtained. A best average of N values gave N10 = 21, column loads including dead and live loads ranged from 500 kN to 950 kN. Determine the allowable pressue if settlement is to be restricted to 25 mm. Find tentative value of qn.

2418_Effect of Footing Size on Stress Zone.png


Related Discussions:- Determine the allowable pressue

Explain about vierendeel girder, Q. Explain about Vierendeel girder? Vi...

Q. Explain about Vierendeel girder? Vierendeel girder design is sometimes adopted in design of footbridges. Traditionally truss design, triangular shape of truss is generally u

Compute the safe bearing capacity of a square footing, Compute the safe bea...

Compute the safe bearing capacity of a square footing 1.5 m × 1.5 m, located at a depth of 1 m below the ground level in a soil of average density 20 kN/m 3 .   = 20°, N c = 17.7,

Concrete mixers, what do you mean by buttering mixers

what do you mean by buttering mixers

Timber design, design of timber in flexural members in terms of extreme fib...

design of timber in flexural members in terms of extreme fibre stress in bending, maximum horizontal shear stress, deflection and bearing stress perpendicular to the grain. the ful

Hydraulics assignment , I have assignment for hydraulics can you help for t...

I have assignment for hydraulics can you help for that

Explain the activitated sludge (aeration tank), Explain the Activitated Slu...

Explain the Activitated Sludge (Aeration Tank)? The activated sludge treatment process is a biochemical oxidation process. Organic solids are stabilized through the oxidation p

Sub-base layer be served as a drainage layer , Question Would a sub-bas...

Question Would a sub-base layer be served as a drainage layer to take away water from pavement? Answer As well providing load distribution in post-construction stage a

Determine concentration of total solids and volatile solids, The following ...

The following test results were obtained for a 100 ml wastewater sample taken at the inlet to wastewater treatment plant.  The tests were performed using the standard methods. Dete

Define non-destructive inspection of concrete substructures, Define Non-des...

Define Non-destructive inspection of Concrete Substructures? If there is evidence of significant deterioration, then a Level III inspection, involving either non-destructive or

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd