Determine condition of activity in the network flow diagram, Civil Engineering

Assignment Help:

Determine the condition of each activity in the network flow diagram shown below

 

898_Determine the condition of each activity in the network flow diagram.png

Ans:

a. Activity C can be started only after the completion of activities A and B

b. Activity D can be started only activity B is completed

c. Activity E can be started only when activities A, B, C and D have been completed

 


Related Discussions:- Determine condition of activity in the network flow diagram

Determine the maximum pressure at the base of the wall, A masonry retaining...

A masonry retaining wall of trapezoidal section with the vertical face on the earth side is 1.5 m wide at the top and 3.5 m wide at the base and is 5.0 m high. It retains a sand fi

Explain tension and compression anchorage length, Q. Explain Tension and co...

Q. Explain Tension and compression anchorage length? Tension anchorage length vs. compression anchorage length Tension anchorage length of steel reinforcement in concrete

Protection of line in case of stop dead restriction, Q. Protection of line ...

Q. Protection of line in case of ‘STOP DEAD RESTRICTION' for carrying out a work of short duration on a single line section on a B.G. route  Ans. Protection in block sectio

Unloaded propped, Ask questa) In an unloaded propped cantilever, the proppe...

Ask questa) In an unloaded propped cantilever, the propped end sinks vertically relative to the fixed end by an amount ? due to poor construction of the foundation of the prop. Wha

Foundation depth and arrangement, Foundation Depth and Arrangement: Th...

Foundation Depth and Arrangement: There are two types of foundations, viz, (a) Shallow foundations, also known as open foundations, and (b) Deep foundations. Slab cul

Define air chamber and surge tank, Q. Air chamber vs. surge tank in pressur...

Q. Air chamber vs. surge tank in pressurized pipelines? Air chambers and surge tanks are generally installed in water main to ease the stress on the system when valves or pumps

Surveying, What is the least count of prismatic and surveyor compass

What is the least count of prismatic and surveyor compass

Wmm, why use wmm upon gsb can be laid dbm directly upon gsb

why use wmm upon gsb can be laid dbm directly upon gsb

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd