Determine concentration of total solids and volatile solids, Civil Engineering

Assignment Help:

The following test results were obtained for a 100 ml wastewater sample taken at the inlet to wastewater treatment plant.  The tests were performed using the standard methods. Determine the concentration (mg/l) of total solids, total volatile solids, total suspended solids, fixed suspended solids, total dissolved solids and fixed dissolved solids.

Tare mass of evaporating dish     = 54.6422 g

     "+ Residue after evaporation of sample at 105°C = 54.7022 g

     "+ Residue after ignition at 550°C   = 54.6842 g  

Same volume of sample is used to determine the suspended solids also.  

Tare mass of filter     = 1.5348 g

      "+ Residue after drying at 105°C = 1.5553 g

       "+ Residue after ignition at 550°C = 1.5453 g

Ans: Volume of sample = 100 mL = 0.1 L  

Total Solids (TS) = [(54.7022- 54.6422) g *1000 mg/g ]/0.1 L  = 600 mg/l  

Total Volatile Solids (TVS) = (54.7022 - 54.6842)g *1000 mg/g ]/0.1L  = 180 mg/l  

Total Fixed Solids (TFS) = (54.6842 - 54.6422)g *1000 mg/g ]/0.1L  = 420 mg/l

It can also be estimated from TFS = TS-TVS = 600-180= 420 mg/l  

Suspended Solids (TSS or SS) = (1.5553-1.5348)g*1000 mg/g ]/0.1L= 205 mg/l  

Fixed Suspended Solids (FSS ) = (1.5453-1.5348)g*1000 mg/g ]/0.1L  = 105 mg/l  

Volatile Suspended Solids (VSS) = (1.5553-1.5453)g*1000 mg/g ]/0.1L  = 100 mg/l

Or it can also be estimated by VSS = TSS-FSS = 205- 105 = 100 mg/l  

Dissolved solids can be determined from the difference between total solids and suspended solids. However, laboratories routinely determine the dissolved solids also experimentally and verify the accuracy of the results.


Related Discussions:- Determine concentration of total solids and volatile solids

Function of waterproof membrane for concrete carriageway, Q. Function of wa...

Q. Function of waterproof (or separation) membrane for concrete carriageway A layer of waterproof (or separation) membrane is usually placed between sub-base and concrete slab

Foundation, What are different type of foundation and their suitablity

What are different type of foundation and their suitablity

Structures, Derivation of Moment-Area Method

Derivation of Moment-Area Method

Concrete , advantage and disadvantage of concrete

advantage and disadvantage of concrete

Project, I want to do project using ul design directory

I want to do project using ul design directory

What is meaning of maintenance period, Question If contractor is likely...

Question If contractor is likely for defective works for 12 years with pact under seal, then what is meaning of Maintenance Period? Answer Faulty works constitute a br

Earth work in high embankments, Q. Earth work in high embankments? (a) ...

Q. Earth work in high embankments? (a) Borrow pits must not be dug close to telegraph poles, electric poles, level crossings, bridges a culverts, or within 800 meters of the bo

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd