Question
In designing of service reservoirs, straight reinforcement in walls of reservoirs is placed at external layer. Give some specific and main reasons?
Answer
As service reservoirs are designed as water-retaining structures with stringent condition of crack width control, design of reinforcement of service reservoirs is under control of serviceability boundary state. For walls of service reservoirs, contraction and development of concrete are extra significant in horizontal direction of walls since of their relatively long lengths as compared with heights. In association, in order to diminish usage of reinforcement, horizontal bars are placed at furthest layer so that distance of reinforcement bars to concrete surface is condensed.
As shorter is the distance to point of concern, smaller is crack width and therefore with such reinforcement agreement recompense are taken if the reinforcement bars in significant direction are placed neighbouring to concrete surface.
What is the easiest way to give proof the varignon''s theorem? Help please guys
Briefly explain the difference between compaction and consolidation of soil. What is the effect of compaction on soil properties? Ans.- Compaction - The process of increas
difference between BM and BC in black topping
rebound hammer working mechanism with detailed specifications of the images
Define Divers in a team for Underwater inspection of Bridge? One team of divers should have minimum three members. This is a requirement of safe working. The idea is while a mi
define distribution factor and shape factor
definition
Extreme fiber stresses at the mid span section of the beam A pre-stressed concrete beam, of cross section 300 mm x 500 mm and 8 m span, is pre-stressed with a parabolic tend
what is the procedure for gsb proctor test for matrial sampling for lab density
Critical Path - Activity on Node The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for start
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd