Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
Question
In case if there is a delay of bituminous laying on top of sub-base, have to tack coat be applied on the top surface of sub-base?
Answer
When there is a delay between bituminous laying of different bituminous layers such as roadbase, base course. A tack coat is applied on top of bituminous layers as it helps to improve better bonding between bituminous materials. If there is not enough bonding between adjacent bituminous layers, they perform as separate independent layers which are able to barely resist traffic loads. When applying tack coat, it have to be sprayed uniformly on bituminous surface and allowed for enough curing. Hot bituminous material laid on top of coat would soften it, enabling tack coat to partly fill voids in bituminous materials. For emulsified asphalt category tack coats, they are usually diluted with water in order to achieve an additional uniform application without excessive usage of asphalt. After subsequent compaction is carried out, coat would be interlocked with bituminous materials. On other hand, care should be taken to make sure that excessive coat will not be laid, or else slippage or shear cracks in bituminous material would occur due to relative thick layer of tack coat applied.
Though, for sub-base surface, priming coat in its place of tack coat might be applied in event of a delay in laying of bituminous layer on top of sub-base layer. Function of primer serves to maintain existing surface condition for a longer period and it also provides an impervious surface to stop ingress of water or water beating by evaporation.
Besides, it fills surface voids and protects sub-base from adverse weather setting. In adding up, it and helps to promote adhesion between adjacent road layers and to harden surface.
A concrete batch plant provided the Design Strength for the engineer's mix design to match the project's specification requirement for a 4000 psi Tremie pump mix. The Water-cement
Explain the Normal Depth Equation The equation is derived from the Chezy-Manning equation. As written below it determines the diameter of a circular storm or sanitary sewer wh
Define in biref about the Final Prestress The stress which exists after all losses of prestress have occurred substantially is known as final prestress. This may be calculated
what is friction damper and there types?
In engineering, the code-allowable withdrawal force is zero, due to the wood expands and contracts over time and the nail pullout force can decrease to zero
Tube levels explains
Question If construction of concrete carriageway is carried out in summer, be capable of expansion joints be omitted? Answer If construction of concrete carriageway
How do we overcome obstacle like river in chain survey?
What is civil engineering?
Distinguish between dry and wet corrosion
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd