Designing of retaining walls, Civil Engineering

Assignment Help:

Question
What is function of shear keys in designing of retaining walls?

Answer
In formative external constancy of retaining walls, failure modes similar to bearing failure, sliding and overturning are usually considered in design. In considering criterion of sliding, sliding resistance of retaining walls is derived from base friction between wall base and foundation soils. To enlarge sliding conflict of retaining walls, rather than providing a large self-weight or a large retained soil mass, shear keys are to be installed at wall base. Opinion of shear keys is as follows-

Main purpose of installation of shear keys is to enhance an extra passive resistance industrial by height of shear keys. However, active pressure industrial by shear keys increases at the very same time. Success of shear keys lies in the information that enhance of passive pressure go over increase in active pressure, resulting in an improvement of sliding conflict.

On other hand, friction between wall base and foundation soils is usually about a fraction of an angle of interior resistance as in about 0.8φ where φ is an angle of inner friction of foundation soil. When a shear key is installed at base of the retaining wall, failure surface is changed from wall base or soil horizontal plane to a plane within foundation soil. Therefore, friction angle mobilized in this case is φ in its place of 0.8φ in earlier case and sliding resistance be capable of be enhanced.

 


Related Discussions:- Designing of retaining walls

Surveying, Describe the two fundamental purposes of surveying

Describe the two fundamental purposes of surveying

State the loss of prestress, State the Loss of prestress Loss of prestr...

State the Loss of prestress Loss of prestress due to elastic shortening definitely occurs in pre-tensioned concrete members. But in post-tensioned members it does not occur if

Rolling - binder, Rolling - Binder: The layer thickness is 40-50 mm. R...

Rolling - Binder: The layer thickness is 40-50 mm. Rolling is done in three stages : Initial Rolling By 80-100 kN smooth wheeled roller. Intermediate Rolling B

Storm water drainage - Road drainage and maintenance, Storm Water Drainage:...

Storm Water Drainage: In city streets, the disposal of rain water has to be done through a system of underground storm water drains. The water is collected at the roadside ke

Airpot, how to design a new airport

how to design a new airport

Assignment, Need assignment for structure concrete work

Need assignment for structure concrete work

Define chlorides - underwater inspection of bridge, Define Chlorides - unde...

Define Chlorides - underwater inspection of bridge? Chlorides do not attack plain concrete when present in the concentrations that normally exist in seawater, but may greatly a

Sub-surface drainage, Sub-surface Drainage: Sub-surface drainage is i...

Sub-surface Drainage: Sub-surface drainage is intended to take away the water seeping through the pervious layers of the soil, causing a high water table, or in cut slopes of

Estimation of design flood discharge, Q. Estimation of design flood dischar...

Q. Estimation of design flood discharge? These methods are also in vogue for estimating maximum discharge. Discharge estimated using the above three methods may be compared wit

Formation of holes in pipelines, Question While branch pipelines are co...

Question While branch pipelines are connected to pipelines, now and then Y-junctions or fitting branched pipelines to key pipelines by formation of holes in pipelines are u

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd