Q. Design the Drainage pipes system in reclamation areas?
In reclamation areas drainage pipes are generally laid at flatter gradients when compared with upstream stormwater pipes. The fact that nature of flow in stormwater drain is by gravity makes the downstream pipes in reclamation areas comparatively deep below ground surface. It's predominant to have outfall of drains above the tidal influence level and this accounts for the relative flatter gradient of drain pipes in reclamation area.
Attention has to be paid to possible occurrence of differential settlement in reclamation area. For pavement design, flexible pavement is predominant to rigid pavement to cater for settlement problems. In the same way, in the design of drains flexible joints such as spigotand socket joints and movement joints in box culverts have to be provided to guard against the effect of differential settlement.
friction circle method of stability of slope
individual wall methods benefits?
what is the heat of hydration and gel space ratio?
a soil sample is 38mm in diameter and 76mm and in its natural condition weighs 168g.when dried completely in an oven weighs 13o.5g.the value of Gs is 2.73.what is the degree of sat
Q. Discontinuity of joint – position of bearing? Expansion joints in a bridge structures cater for movements inlongitudinal, transverse, vertical and rotational forms. Layout a
Analyse the state of stress at the critical section: A prismatic bar of circular section with 80 mm diameter is subjected to bending moment of 5 kN-m and a torque of 7 kN-m. A
Q. What is the minimum prescribed track structure for LWR / CWR on Broad Gauge? Ans.- 1. General - The minimum length of LWR depends upon - i. Range of temporary variati
Manhole covers - triangular halves Manhole covers are usually made up of two pieces of triangular plates to form a square cover. One can wonder why two rectangular halves are u
criteria for economical span length in bridge
I want to know the necessary material list during replacement of Expansion Joint
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd