Design storm water drains to match soffit, Civil Engineering

Assignment Help:

Question
Why is it best to design storm water drains to match soffit?

Answer
Storm water drains gather storm water in their corresponding catchment areas throughout rainstorm and express collected water through outlets to sea. So, in considering hydraulic designing of storm water drains, previous than regular drainage pipe ability to be taken into consideration, one have to check backwater effect due to tidal condition at outlets if drains are situated quite close to downstream end of outlets.

Storm water drains are usually calculated to match soffit to keep away from surcharging by backwater result or when downstream pipes are organization full. Usually pipe size increase from upstream to downstream. For in case of matching drain invert, while outlet pipes are fully surcharged by tidal effect of sea or while downstream pipes are fully filled with storm water, pipe sections right away upstream of outlet are as well surcharged .though, for in case of matching pipe soffit, immediate upstream sections of outlet pipes are not entirely surcharged although downstream pipes are running full. But, it is not always practical to uphold soffit for all pipelines since it requires enough drop to achieve this.

Furthermore, flow of storm water is mostly by gravity in plan of storm water drains. In case drains are designed to equal invert, next it stands a high prospect that flow in upstream smaller pipes has to be free next to a head.

 


Related Discussions:- Design storm water drains to match soffit

Design the transverse reinforcement, Figures (a) and (b) respectively give ...

Figures (a) and (b) respectively give details of a simply-supported bridge beam and its (idealised) cross-section. In addition to the dead load of 25 kN/m (including self weight),

Use of admixtures in concrete, Use of Admixtures in Concrete The use of...

Use of Admixtures in Concrete The use of chemical admixtures may be made in prestressed concrete construction. But the admixture should not contain chlorides in any form. This

Show the settlement due to excavation, Q. Show the Settlement due to Excava...

Q. Show the Settlement due to Excavation? If  an excavation is made in a sandy soil,  the structure founded near the excavation will be affected and it will cause extra settlem

Raft and beam foundation, why is weight of raft not considered in structura...

why is weight of raft not considered in structural design of raft and beam

Batching of concrete, Introdaction , volume batching , weighat batchin...

Introdaction , volume batching , weighat batching , mesaring of water

Problems in turbid water - underwater inspection of bridge, Define Problems...

Define Problems in turbid water - underwater inspection of bridge? There are three main problems, which limit the viewing performance of an underwater camera. These are: -

Stone, Explain briefly physical classifications of stone

Explain briefly physical classifications of stone

Calculate the deposited amount - construction management, An engineer depos...

An engineer deposits an "X" amount every 6 months for 3 years so that she'll have $10,000 at the end of this period. The interest rate is 5% per year which is rebalanced every 6-mo

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd