Question
Why is it best to design storm water drains to match soffit?

Answer
Storm water drains gather storm water in their corresponding catchment areas throughout rainstorm and express collected water through outlets to sea. So, in considering hydraulic designing of storm water drains, previous than regular drainage pipe ability to be taken into consideration, one have to check backwater effect due to tidal condition at outlets if drains are situated quite close to downstream end of outlets.

Storm water drains are usually calculated to match soffit to keep away from surcharging by backwater result or when downstream pipes are organization full. Usually pipe size increase from upstream to downstream. For in case of matching drain invert, while outlet pipes are fully surcharged by tidal effect of sea or while downstream pipes are fully filled with storm water, pipe sections right away upstream of outlet are as well surcharged .though, for in case of matching pipe soffit, immediate upstream sections of outlet pipes are not entirely surcharged although downstream pipes are running full. But, it is not always practical to uphold soffit for all pipelines since it requires enough drop to achieve this.

Furthermore, flow of storm water is mostly by gravity in plan of storm water drains. In case drains are designed to equal invert, next it stands a high prospect that flow in upstream smaller pipes has to be free next to a head.

 


Related Discussions:- Design storm water drains to match soffit

Structural analysis & design, This is an optional team assignment. This gra...

This is an optional team assignment. This grade will replace your lowest two homework grades. You may work in teams of 3-4 students. Design the lightest concrete cantilever beam

Foundation, Explain briefly shallow foundation?

Explain briefly shallow foundation?

Paint system to protect steelwork from corrosion, Q. Paint system to protec...

Q. Paint system to protect steelwork from corrosion? In a typical painting system, there are generally three main layers primer, undercoat and finishing coat. Primer acts as th

Engineering Science, 1(a)Explain the difference between a concurrent and a ...

1(a)Explain the difference between a concurrent and a non concurrent force system . (b)If a non coplanar force system is acted upon by equal and opposite forces,it must be in equil

Defect of timber, due to defectiveseasoning and conversion

due to defectiveseasoning and conversion

Higway engineering, Ask question Design the pavement by group index method ...

Ask question Design the pavement by group index method for heavy traffic using following subgrade data Soil passing 75micron sieve =65%,liquid limit =40%plastic limit =20% #Min

Soil compaction test, Question In soil compaction test , if test resul...

Question In soil compaction test , if test result exceeds 100%, should engineers accept result? Answer Soil compaction is method of increasing soil density by re

Amount of borrow needed to bring area to elevation of 90-ft, Surveyed eleva...

Surveyed elevations are shown in Figure for a 50' x 50' grid at a proposed parking lot location. The amount of borrow needed to bring the area to an elevation of 90-ft is most near

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd