Design pumps for plant layout, Mechanical Engineering

Assignment Help:

Q. Design Pumps for plant layout?

Pumps handling flammable or combustible materials are relatively frequent sources of leakage and should therefore be located as far as practical from continuous ignition sources. They should not be located beneath other equipment, such as towers, drums, or pipe racks in order to avoid fire involvement of such equipment. Also, they should be located clear of overhead obstructions so they can be reached by a small crane. Where pumps are located within multi-level structures and portable crane access is not possible, monorails shall be installed for removal of the pump or internals during maintenance. A preferred location for pumps is on the opposite side of towers, away from fired heaters. In-line pumps should be treated the same as regular pumps for spacing purposes.

Hot pumps handling flammable materials present an increased fire risk because of the high likelihood of auto-ignition if a leak occurs. Pumps containing hydrocarbons operating above 316 °C (600 °F) or above its auto-ignition temperature (whichever is lower) should preferably not be located under or within multi-level structures. If unavoidable, fire protection measures such as passive fire protection or water sprays are required for equipment and structures above the pumps. However, the best choice is not to locate such pumps under or within structures.

Spacing separates pumps with higher fire potential and provides access for fire fighting. When a pump and its spare are exposed to a common fire hazard, additional separation between them may be justified to minimize the risk of losing both of them during a fire.

Pumps at grade should have prepared foundations with a paved area sloped to take spillage away from the pumps. Where pumps are required to be located in a structure, drip trays and anti-vibration mountings should be considered. For severe weather protection or noise reduction purposes some exposed pumps in critical service may be located in an enclosed or semi-enclosed shelter. In off-site areas, pumps should be grouped together outside the tank bermed areas.


Related Discussions:- Design pumps for plant layout

Feed speed-spindle rpm-cutting time material removal rate, A hole of 25 mm ...

A hole of 25 mm diameter and 62.5 mm depth is to be drilled. The suggested feed is 1.25 mm/rev.and the cutting speed is 60 m/min. Assume the clearance height is 5 mm. Determine: f

Thermal engineering, Air enters the compressor of an ideal air standard Bra...

Air enters the compressor of an ideal air standard Brayton cycle at 100kPa, 250C with a volumetric flow rate of 8m3/s and is compressed to 1000kPa. The temperature at the inlet to

Calculate total deflection -two close-coiled helical springs, Calculate tot...

Calculate total deflection -two close-coiled helical springs: Two close-coiled helical springs are compressed among two parallel plates by a load of 1000 N. The springs contai

Cooling period of furnace pipe, We shutdown our furnace and always encounte...

We shutdown our furnace and always encountered crack on our piping at the weld joints. I investigated that upon shutdown the furnace cracking, our maintenance immediately remove th

Design approach of human mobility device, In ME1, you are beginning to deve...

In ME1, you are beginning to develop knowledge of design, materials, and basic machine elements (e.g., power screws, bolted joints, bearings, gears). In addition, you are becoming

Heat treatment of tool steels, Heat Treatment of Tool Steels This trea...

Heat Treatment of Tool Steels This treatment in case of tool steels in a significant step before actually employing the tool. Most properties are attained after heat treatment

Open and closed thermodynamic system, Steam flowing at a rate of 3200 lbm/h...

Steam flowing at a rate of 3200 lbm/hr enters an adiabatic nozzle. The initial condition of steam is: P1 = 250 psi, v1=620 ft/min, v1 = 2.4 ft3/lbm and u1 = 1125.5 Btu/lbm. The ste

Determine the cop and power required, In a 15 TR ammonia refrigerator plant...

In a 15 TR ammonia refrigerator plant the condensing temperature is 25 0 C and the evaporative temperature is -10 0 C. The refrigerant ammonia is subcooled by 50C before passing th

Safety functions - industrial safety, Safety Functions - Industrial Safety ...

Safety Functions - Industrial Safety In the statement about safety organization various functions have been mentioned. Yet, a clear description is lacking. Without much elabor

Relation between intensity bending moment and shear force, Relation between...

Relation between intensity bending moment and shear force: What is the relation between load intensity bending moment and shear force Consider the beam subjected to any t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd