Design pumps for plant layout, Mechanical Engineering

Assignment Help:

Q. Design Pumps for plant layout?

Pumps handling flammable or combustible materials are relatively frequent sources of leakage and should therefore be located as far as practical from continuous ignition sources. They should not be located beneath other equipment, such as towers, drums, or pipe racks in order to avoid fire involvement of such equipment. Also, they should be located clear of overhead obstructions so they can be reached by a small crane. Where pumps are located within multi-level structures and portable crane access is not possible, monorails shall be installed for removal of the pump or internals during maintenance. A preferred location for pumps is on the opposite side of towers, away from fired heaters. In-line pumps should be treated the same as regular pumps for spacing purposes.

Hot pumps handling flammable materials present an increased fire risk because of the high likelihood of auto-ignition if a leak occurs. Pumps containing hydrocarbons operating above 316 °C (600 °F) or above its auto-ignition temperature (whichever is lower) should preferably not be located under or within multi-level structures. If unavoidable, fire protection measures such as passive fire protection or water sprays are required for equipment and structures above the pumps. However, the best choice is not to locate such pumps under or within structures.

Spacing separates pumps with higher fire potential and provides access for fire fighting. When a pump and its spare are exposed to a common fire hazard, additional separation between them may be justified to minimize the risk of losing both of them during a fire.

Pumps at grade should have prepared foundations with a paved area sloped to take spillage away from the pumps. Where pumps are required to be located in a structure, drip trays and anti-vibration mountings should be considered. For severe weather protection or noise reduction purposes some exposed pumps in critical service may be located in an enclosed or semi-enclosed shelter. In off-site areas, pumps should be grouped together outside the tank bermed areas.


Related Discussions:- Design pumps for plant layout

Airport drainage, Airport Drainage: Rainwater should be quickly taken...

Airport Drainage: Rainwater should be quickly taken away from the runway, taxiway and apron areas. For drainage of runway and taxiway, a cross-slope of 1.5 per cent on either

Horizontal vessels and vertical vessels, Q. Horizontal Vessels and Vertical...

Q. Horizontal Vessels and Vertical Vessels? Horizontal Vessels A horizontal vessel, designed to support a full weight load of water, shall be tested while resting on its sup

Subcontractor submittals, The Supplier/Subcontractor shall submit, for acce...

The Supplier/Subcontractor shall submit, for acceptance, their Material Traceability and PMI program and procedures, which shall comply with this specification, prior to the sourci

What is the aim of pdes, What is the aim of PDES The aim of PDES is to ...

What is the aim of PDES The aim of PDES is to provide an interface which permits the exchange of data of the entire product development cycle and production cycle, see also PDE

Evaluate the composite transformation matrix, A triangle ABC with vertices ...

A triangle ABC with vertices A (30,20), B(90,20), C(30,80) is to be scaled by a factor of 0.5 about a point X(50,40). Calculate :- (i) The composite transformation matrix; and

The motorcycle , Motorcycle, we have learnt about the various parts of a mo...

Motorcycle, we have learnt about the various parts of a motorcycle and their functions. Technical specifications of various models of motorcycles launched by the HHML were also not

Determine the economic order quantity, Determine the economic order quantit...

Determine the economic order quantity: Determine the economic order quantity and the reorder point. Given Annual demand (D) = 2,000 units Average daily demand (d) = 2,00

Calculate the kic from the data - thick cylinder, Calculate the KIC from th...

Calculate the KIC from the data - thick cylinder: In a fracture test a 3-point bend specimen of thickness 20 mm and depth 25 mm is supported over a span of 100 mm. The specime

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd