Design nominal reinforcement to piles, Civil Engineering

Assignment Help:

Question

Is it true that there is no essential to design nominal reinforcement to piles.


Answer

In BS8110 and BS5400 Pt.4, they need provision of nominal reinforcement for columns. Though, for pile design requirement of nominal reinforcement might not be essential. Initially, as piles are located underground, occurrence of startling loads to piles is rarely. Secondly, shear failure of piles is considered not important to structure because of severe collision. Also, failure of piles by buckling because of fire is unlikely as fire is rarely ignited secretive.

 

 

 


Related Discussions:- Design nominal reinforcement to piles

Retaining wall, whether the wall has adequate sliding resistance

whether the wall has adequate sliding resistance

Ocf, location of hydrolic jump

location of hydrolic jump

Brigdes, infomation about differnt brigdes

infomation about differnt brigdes

Cross drainage work, Cross Drainage Work: Several natural streams, ri...

Cross Drainage Work: Several natural streams, rivers and canals cross the road. They have to be led across the road through culverts and bridges. That given structures is kno

#titl, Two readings ie 1.64m and 0.73m were taken during leveling procedure...

Two readings ie 1.64m and 0.73m were taken during leveling procedure to define the slope of a centerline of a bridge at points A and B. If distance AB=50 m, find the slope of line

Compute the safe bearing capacity of a square footing, Compute the safe bea...

Compute the safe bearing capacity of a square footing 1.5 m × 1.5 m, located at a depth of 1 m below the ground level in a soil of average density 20 kN/m 3 .   = 20°, N c = 17.7,

.levelling, differentiate between Dumpy level:The Wye or Y level:Cooke''s r...

differentiate between Dumpy level:The Wye or Y level:Cooke''s reversible level: Cushing''s level:Tilting level and Automatic level

Tack rivet, tack rivet figures with connections

tack rivet figures with connections

Define bank volume to be stockpiled and used for backfill, An earthwork con...

An earthwork contract was awarded to excavate and backfill the foundation of a proposed 50-ft by 50-ft office building.  The existing grade elevation is 437.5-ft while the sub-base

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd