Design an equalization basin with a safety factor, Civil Engineering

Assignment Help:

A storm occurs with rain of varying intensity falling over a commercial area. The area has a combined sewer system. Two interceptor sewers direct flow to the wastewater treatment plant (WWTP). The hourly flow volumes measured in the two interceptor sewers immediately upstream of the WWTP are listed in the table below. The WWTP has a peak flow capacity of 12.5 MG/hr. Using the data generated for this storm:

1885_Design an equalization basin with a safety factor.png

1) Design an equalization basin with a safety factor of 1.2 to store the excess flow for later treatment, thus preventing a combined sewer overflow of untreated wastewater to the environment;

2) Determine the hour during which the peak MG above the plant capacity occurs.

Solution:

1) Plotting the straight, constant sloped cumulative capacity line, and the curved total interceptor volume line results in data producing the last column in the table "Net + or - MG". This data represents the position of the cumulative interceptor MG, either above or below the cumulative plant capacity line. The greatest variance in cumulative hourly data (net MG) occurs between hour 1and hour 3 (- 0.5 and + 1.2). The equalization basin volume needed to prevent a combined sewer overflow during this storm is 1.7 MG. With a safety factor of 1.2, design for (1.7 MG) (1.2) = 2.0 MG basin.

2) Peak MG above the plant capacity occurs at hour 2 (14.0 MG vs. 12.5 MG).

919_Design an equalization basin with a safety factor 1.png


Related Discussions:- Design an equalization basin with a safety factor

Fluid mechanism, tell me something about velocity profile?

tell me something about velocity profile?

Rectangular tie, how would you perform a rantangular tie ,using an optical ...

how would you perform a rantangular tie ,using an optical square

coursework (commercial management), Ask que1. Identify the risks involved ...

Ask que1. Identify the risks involved in this project related to cost in the perspective of the customer and analyse the probability of acceptance of such a project by customers. 2

Explain the limitations of rebound hammer, Explain the Limitations of Rebou...

Explain the Limitations of Rebound Hammer? The following characteristics of concrete can affect the correlation of the rebound number with the actual surface hardness and shoul

Air pollution, chlorosis in plants is caused by

chlorosis in plants is caused by

Fly levelling, we are given a project on field.i''d like to know about how...

we are given a project on field.i''d like to know about how to start n proceed vd fly levelling in the field

Increasing concrete cover beyond contractual, Question If contractor sugges...

Question If contractor suggests increasing concrete cover beyond contractual such as 40mm to 70mm shall engineers accept suggestion? Answer In contractual part, based on requir

Functions of water stops in joints of box culverts, Question What will func...

Question What will functions of water stops in joints of box culverts and drainage channels ? Answer Principal function of water stops is to stop liquids, water-borne materials

Mosaic and p v c tiles, Q. Mosaic and P V C Tiles? The water sink at wa...

Q. Mosaic and P V C Tiles? The water sink at water points may be provided with mosaic lining at other than important station. Mosaic tiles also may be provided in flooring of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd