Design a operations management system, Operation Management

Assignment Help:

The purpose of operations management is to make the best use of productive resources. It entails the design and control of all the systems for the productive use of various raw materials, equipment, human resources, and facilities so that products and/or services get delivered in an efficient manner. The way by which various productive resources (like labor, capital) are managed is critical for growing, making profits, and competing.

Operations management is highly responsible for making strategic (long-term) decisions that affect the entire organization. These decisions should not only support the mission but should also be aligned to the overall strategy of the organization. The operations strategy involves a plan to use all the production resources to support the long-term competitive strategy of the organization.

Manufacturing of an automotive product requires good operations management skills. It is a big process which involves many activities. By managing the operations, we could find following advantages:-Decreasing total costs.
• Decreasing working capital.
• Increasing the return on assets-doing more with less.
• Leveraging the value chain for tax advantages.
• Growing revenue-using our operations portfolio to uncover latentrequirements (features or capabilities that customers do not expector maybe even imagine).

Manufacturing of bicycle will involve following phases:
1) Product strategy
2) Planning
- Product Design
- Product Scheduling and Analysis
- Product Costing
- Risk Assessment
- Process Performance Matrix
3) Product Development
4) Product Testing
5) Importance of project management and teamwork in all these phases

2. Product Strategy
• Market Segment: School going children
• Product or service requirement: Light weight cycles
• No of cycles to be sold: 1000 cycles in a month

3. Planning

Formal project planning and scheduling can go a long way toward increasing the probability of successfully completing the project. The manufacturing of bicycles will involve following phases for better planning so that the production gets completed in time:
a) Product Design
The design process would consist of four phases:

1. Idea development or generation (Brain Storming)
There will be a team of product manager, engineers, customer representatives, suppliers and distributors. The product manager will be coordinating the whole design team. The manager will first take some suggestions from the customer about the product they are interested in. He will use the background analysis their marketing team has already done to find the final requirement. He will also see what products are available by competitors in the market. Then he will check with engineers and suppliers as well. In this session, the main purpose will be to get more and more ideas. Quantity will matter over the quality.

2. Screening of ideas

After getting all the ideas of manufacturing a bicycle, he will work on each idea, think about positives and negatives. Few basic questions that will arise are related to required employee skills, product material sourcing, and potential customers. After a thorough discussion the product manager will finalize the design along with the various components and their measures. It will involve the size of tyres, size of pedals, chains, handles, metallic frame and other accessories. He will also decide the size and dimension , material to be used, and quantity of each material etc of each part. He will check with suppliers also about the material availability.

3. Preliminary design testing

A prototype of the cycle to be made is first manufactured. This would be again checked with all the engineers and customers whether they were looking for similar product. Post this few raw pieces of the bicycle will be made which will entail the testing of the design. The parameters like speed, weight, sitting area balance etc will be taken care of during this phase. Depending on the testing results, the design is dropped, modified, or passed on to the final design phase

4. Final design

Once the preliminary testing is complete, the design will be finalized. The following parameters will be taken care of especially during this.
- Simplification-reducing the number of features and parts: It would be assured to reduce the complexity. Adopting the simpler design of bicycle. To ensure light weight, the cover on the tires will be removed.
The number of spokes will be of same size in both the tires.
- Standardization-using common and interchangeable part, design for handling, stocking, and shipping: For eg. Same size of nuts and bolts would be preferred as applicable across various assemblies. It would be tried to use same moldings for different parts. Same material will be used for multiple products for eg. Steel frame, carrier, will be of same material. Same way pedals and handle will be of same material.

b) Product Scheduling:
Define activities:
a) Design bicycle
b) Obtain Financing
c) Order material
d) hire employees
e) employee training
f) manufacturing of tyres
g) manufacturing of bicycle frame
h) manufacturing of cycling system
i) Assembling of parts
j) Select paint
k) Finish Work

Sequence activities: A work break down structure (WBS) will be followed to expedite the manufacturing process. A WBS identifies the work to be done in a systematic, hierarchical way. It clearly defines actions and helps everyone involved understand the project's vision and progression, essentially preparing the project team for scheduling. It makes the project less overwhelming and is also a good way to involve ad hoc members in the project, leveraging their experience and expertise in the planning phase. Following flow chart shows how various processes are connected. This helps all the participants like manager, engineer, and employeeetc to understand the various phases.


Related Discussions:- Design a operations management system

Explain ethnocentric, Select an MNE with which you are familiar and determi...

Select an MNE with which you are familiar and determine which staffing approach (ethnocentric, polycentric, geocentric, or regiocentric) would be most beneficial to that enterprise

Operations management, a small assembly line for the assembly of power stee...

a small assembly line for the assembly of power steering pumps needs to be balanced. exhibit 8.11 is the precedence diagram. the cycle time is determined to be 1.5 minutes. how wou

Explain type of antennas issues signals with equal strength, Name the type ...

Name the type of antennas issues signals with equal strength and clarity in all directions? a. directional b. bi-directional c. tri-directional d. omni-directional

Explain choosing a new piece of equipment, The following table shows the cr...

The following table shows the critical factors in a company's decision on choosing a new piece of equipment. Calculate the breakeven volume and utilization for each option and then

Evaluate the performance of a bank holding company, The purpose of the proj...

The purpose of the project is to evaluate the performance of a bank holding company of your choice. 1. Choose a bank holding company. You can choose from Top 50 BHCs or find a b

North west corner rule, advantages and disadvantages of north west corner r...

advantages and disadvantages of north west corner rule

Digitra; cell phone, Ask que Prepare Paul Jordan’s report to John Smithers ...

Ask que Prepare Paul Jordan’s report to John Smithers using regression analysis. Provide a summary of the cell phone industry outlook as part of Paul’s response. stion #Minimum 100

Responsiveness - customer satisfaction and service quality, Responsiveness ...

Responsiveness - Customer Satisfaction and Service Quality Concerns the willingness or readiness of employees to provide service. It involves timeliness of service: mailing a

Explain develop an aggregate production plan, ABC Company, a manufacturer o...

ABC Company, a manufacturer of roofing supplies, has developed monthly forecasts for roofing tiles. The forecasted demand and the expected production days for months March to Augus

Forward scheduling - scheduling techniques, Forward Scheduling - Scheduling...

Forward Scheduling - Scheduling Techniques Forward scheduling means assigning customers orders or job to various work centers based on the as early as possible approach. Thus

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd