Depict the project network using aon, Operation Management

Assignment Help:

Task time estimates for a production line setup project at Robert Klassens Ontario factory are as follows: Activity Time (in hours) Immediate Predecessors A 6.0 B 7.2 C 5.0 A D 6.0 B, C E 4.5 B, C F 7.7 D G 4.0 E, F a) Draw the project network using AON. b) Identify the critical path. c) What is the expected project length?


Related Discussions:- Depict the project network using aon

Explain utilitarian and a libertarian view, Compare a Utilitarian and a Lib...

Compare a Utilitarian and a Libertarian view on the importance and enforcement of consumer rights (to choose, to safety, to be informed, to be heard, to redress and to privacy).

Explain what do you think is the best approach to use, In considering emplo...

In considering employee recruitment in your own business, what do you think is the best approach to use? Why do you think that is the best approach?

Method which benefit from standardization of ihrm activities, Examine two i...

Examine two issues of standardization and localization in general for MNEs. Determine two ways in which an organization would benefit from standardization of IHRM activities and tw

Managing organizational change, Applying models and concepts from the cours...

Applying models and concepts from the course, analyze a significant change initiative you have observed, have been affected by or have had a hand in implementing in your organizati

Opportunity costs of cells - transportation problem, Having determined all ...

Having determined all ui and vj values calculate for each unoccupied cell ij = ui + vj - cij. The ij represent the opportunity costs of various cells. After obtaining the opportuni

Explain detect the presence of assignable causes, If the time order of prod...

If the time order of production has not been recorded in a set of data from a process is it possible to detect the presence of assignable causes?

#titCAREING FOR TODDLERle.., HOW TO CARE FOR A TODDLERn #Minimum 100 words ...

HOW TO CARE FOR A TODDLERn #Minimum 100 words accepted#

Sequence problem, how to calculate idletime of each row

how to calculate idletime of each row

Prepare fraud risk factor for company - fraud risk asessment, A formal frau...

A formal fraud risk assessment ("FRA") is an important element of an entity's' antifraud programs and controls. Companies must specifically consider their controls to prevent and d

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd