Depict an aon diagram of the project, Operation Management

Assignment Help:

The following is a table of activities associated with a project at Bill Figg Enterprises, their durations and what activities each must precede-

Activity Duration (weeks) Precedes

A (start) 1 B, C

B 1 E

C 4 F

E 2 F

F(end) 2

a) Draw an AON diagram of the project, including activity durations

b) Define the critical path, listing all critical activities in chronological order

c) What is the project duration (in weeks)?

d) What is the slack (in weeks) associated with any and all noncritical paths through the project?


Related Discussions:- Depict an aon diagram of the project

Explain roles and function of an hr professional, 1. What do you see as th...

1. What do you see as the most interesting part of HR as a career field? 2. What do you think are the roles and function of an HR professional?

Explain what structural change is indicated at the plaza inn, What structur...

What structural change is indicated at the Plaza Inn? Explain clearly why

Explain ethics training back to the workplace be maximized, Define the term...

Define the term, transfer of learning. (2) A critical issue in training is the transfer of training, and ethics training is no exception. How could the transfer of ethics training

Activities to a subsidiary in another country, Transferring some part of an...

Transferring some part of an organisation's activities to a subsidiary in another country is an example of  offshoring.

Quality management, what are stra thetegies used in TQM to deal with issue ...

what are stra thetegies used in TQM to deal with issue of cost of quality

Explain shipment to foreign markets, A U.S. manufacturer that exports goods...

A U.S. manufacturer that exports goods made at its U.S. plants for shipment to foreign markets

Explain low level coding in mrp indicates, Q 1 Low level coding in MRP indi...

Q 1 Low level coding in MRP indicates the exact status of each item managed by the system in "real time." Q 2 Which of the following is considered a secondary report in an MRP s

, What happens if balance doesn’t exis

What happens if balance doesn’t exist

Explain best time for performance appraisal, Is there one best time for per...

Is there one best time for performance appraisal? Explain

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd