Depict a project network for the activities, Operation Management

Assignment Help:

A senior MIS design class project team has developed the following schedule of activities for their project, using their best estimate of completion times. Both written and oral reports are required. Draw the project network. Can they complete the project in the 38 class days remaining until the end of the semester? Identify the critical activities. Identify the non-critical activities and their relevant slack times

Activity Immediate Activity Time

Predecessors
A --- 3
B --- 5
C A, B 2
D C 6
E C 5
F E 3
G C 4
H D, G, F 3
I D, F 4
J H 2
K I, J 2

(a) Draw a project network for the above activities.

(b) Determine which activities are critical

(c) Determine which activities are non-critical and their respective slack times.

(d) How long will the project take to accomplish?


Related Discussions:- Depict a project network for the activities

Maintenance, discuss the pross and cons of hiring multi-craft maintenance p...

discuss the pross and cons of hiring multi-craft maintenance personnel

Was due process denied describe, A state statute empowered public school pr...

A state statute empowered public school principals to suspend students for up to ten days without any notice or hearing. A student who was suspended for ten days challenges the con

Describe the risks associated with levelling resources, Explain the risks a...

Explain the risks associated with levelling resources, compressing or crashing projects, and imposed durations, or catch-up, as the project is being implemented.

Operational strategies for balancing capacity and demand, What are the Oper...

What are the Operational strategies for balancing capacity and demand? Operational strategies for balancing supply (capacity) and demand: a. Level capacity strategies b.

Explain bill could protect the data and systems, Make a list of five ways t...

Make a list of five ways that Bill could protect the data and systems that he is going to put in place. Consider the type of data and systems that would be relevant to Bill's pizz

Explain line balancing, Explain Line Balancing. Line Balancing: It m...

Explain Line Balancing. Line Balancing: It means balancing the line between the product lines or assembly lines. This aims at grouping facilities and workers in an efficient

How much hours of production time would you schedule for x, Plans are being...

Plans are being made to produce a product that requires 40 minutes on Resource X and 30 minutes on resource Y. Assume that there is only one of each of these resources, and that ma

Explain what is change management, 1. Explain What is change management? 2...

1. Explain What is change management? 2. Explain What is the ultimate goal of change management?

Factors affecting scheduling - external factors, Factors Affecting Scheduli...

Factors Affecting Scheduling - External Factors The following factors govern the scheduling and are to be considered before establishing scheduling plan: External Factors:

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd