Define the shock transmission unit, Civil Engineering

Assignment Help:

Define the Shock Transmission Unit?

Ever since engineers have started designing multi span simply supported bridges, they have been dreaming of connecting all the spans together to distribute seismic loads to more than one pier during an earthquake or other sudden loadings. Thus, the peaks due to sudden force is considerably reduced. One possible solution to this requirement could be continuous construction of bridges so that a large number of piers can participate in load sharing during earthquake. But the requirement of size of expansion joint in such an arrangement would be extraordinarily large and thus not feasible. The other solution has been provided by Shock Transmission Unit (STU) or Lock Up Device (LUD).

It is a simple device which is designed to be connected between superstructure and substructure of a bridge to form a temporary rigid link. The peculiar feature of this device is that it forms a rigid link only under rapidly applied loads such as braking and seismic forces whereas under slowly applied loads such as temperature, creep, shrinkage etc, it allows the free movement. STU, thus, allows load sharing in case of suddenly applied short duration horizontal loads. The unit is connected near the bearing between the superstructure and substructure. It works on principle that rapid passage of viscous fluid through a narrow gap generates considerable resistance while slow passage through the same gap only minor resistance.

In this figure e1 and e2 are the movements accommodated in STU due to superstructure and substructure respectively.


Related Discussions:- Define the shock transmission unit

Determine the project duration and critical path, Critical Path - Activity ...

Critical Path - Activity on Node The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for start

Vibrocoring in marine ground investigation, Vibrocoring in marine ground in...

Vibrocoring in marine ground investigation If only shallow marine ground geotechnical information is essential for design purpose, vibrocoring is certainly a good choice for s

Bitumen, limitation in using with bitumen as watertight material

limitation in using with bitumen as watertight material

What is the correct value of the specific gravity, In a specific gravity te...

In a specific gravity test, 1.17 N of oven-dired soil was taken. The weight of pyknometer, soil and water was obtained as 6.51 N. The weight of pyknometer full of water alone was 5

Break even point, Break even point: EM Electricals, Inc., contains fix...

Break even point: EM Electricals, Inc., contains fixed costs of Rs. 600,000 this period. Variable costs involved labour charges of Rs.100 per unit and material cost of Rs. 200

Upper bound of indirect tensile strength, Question While designing rese...

Question While designing reservoirs, indirect tensile strength of the concrete mix is particular to be less than a specific value such as 2.8N/mm2 for potable water. Why ought

Transit sheds and warehouses, Transit Sheds and Warehouses: These are ...

Transit Sheds and Warehouses: These are sheds constructed as steel frames or RCC frames with a steel truss, with galvanised iron or asbestos cement sheets. Transit sheds may b

Fixed and pinned connection between piles and pile caps, Q. Fixed vs pinned...

Q. Fixed vs pinned connection between piles and pile caps? The type of connection amid piles and pile caps affects the load carrying capacity of pile groups. Fixity of pile hea

Brick mansory, Aim,materials or tools required,procedure for constructing e...

Aim,materials or tools required,procedure for constructing english bond bricks

Application of bitumen to driven piles, Q. Application of bitumen to driven...

Q. Application of bitumen to driven piles? In a certain area of H-piles subjected to ground water table fluctuation, painting is occasionally applied on the surface of H-piles

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd