An assembly line with 11 tasks is to be balanced. The longest task is 2.7 minutes, the shortest task is 0.4 minutes, and the sum of the task times is 18 minutes. The line will operate for 800 minutes per day.

a. Determine the minimum and maximum cycle times.

b. What range of output is theoretically possible for the line?

c. What is the minimum number of stations needed if the maximum output rate is to be sought?

d. What cycle time will provide an output rate of 200 units per day?


Related Discussions:- Define the minimum and maximum cycle times

Quality management., examples of internal and external failure cost

examples of internal and external failure cost

Explain skills associated with effective project manage, Determine which of...

Determine which of the eight traits or skills associated with being an effective project manager would be the most effective when managing a group of newly hired engineers. Justify

What is the distinction between prediction and forecasting, Question 1: ...

Question 1: Show the nature and importance of the four logistics-related elements of customer service. Question 2: (a) Describe the concept of supply chain management.

What are disadvantages of using multiple sourcing strategies, What are the ...

What are the disadvantages of using multiple sourcing strategies? Disadvantages of using multiple sourcing: a. Not simple to facilitate quality assurance procedures while

Describe all the limitations of matrix organization, Describe all the limit...

Describe all the limitations of matrix organization. Limitations of matrix organization (i) Matrix organization violates the principle of unity of command when a person

Explain principles for determining product mix, The senior management at Ca...

The senior management at Canine Kernels Company CKC is concerned with the existing capacity limitations so they want to accept the mix of orders that maximizes the company's profit

Explain how much repayment of principal, Jan sold her house on December 31 ...

Jan sold her house on December 31 and took a $50,000 mortgage as part of the payment. The 10-year mortgage has a 11% nominal interest rate, but it calls for semiannual payments beg

Line balancing, what do you understand by “line balancing “? What happens i...

what do you understand by “line balancing “? What happens if balance doesn’t exist?

Airline implementing a policy that need to buy second seat, Answer the foll...

Answer the following questions: 1. what are the pros and cons of an airline implementing a policy that heavier customers need to buy a second seat? Research an airline and provide

Concepts of collective bargaining process, The United Auto Workers union en...

The United Auto Workers union enters into contract negotiations with the Ford Motor Company in Michigan. What are the three main subject areas the UAW can negotiate with Ford? Prov

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd