Define the finish-to-start dependency, Civil Engineering

Assignment Help:

Sheet rock cannot be installed in the new house you are building until a building inspector approves the plumbing, electrical, HVAC, and insulation.  This is an example of:

  1. A constraint
  2. An assumption
  3. A start-to-finish dependency
  4. A finish-to-start dependency  

Solution: 4. the inspections must be finished before the sheet-rocking can start.


Related Discussions:- Define the finish-to-start dependency

Explain the erosion and sedimentation, Explain the Erosion and Sedimentatio...

Explain the Erosion and Sedimentation Erosion: Removal of soil or other channel material caused by the rapid movement of water over the channel surface. The removed material

Disparity between working stress and limit state approach, Question Wha...

Question What is key disparity between working stress approach and limit state approach ? Answer Working stress approach, service loads are used in whole plan and st

Calculate the effective annual interest rate, A credit card advertises a no...

A credit card advertises a nominal rate of 18% compounded monthly. If no monthly payments are made, the effective annual interest rate is most nearly: The actual rate is, (18%

What is stilling basins, Q. What is Stilling basins? Stilling basins ar...

Q. What is Stilling basins? Stilling basins are usually introduced to convert supercritical flow to subcritical flow before it reaches downstream. A typical stilling basin comp

Estimate total dissolved solids, Estimate total dissolved solids, Alkalinit...

Estimate total dissolved solids, Alkalinity and Hardness A sample of water from Brazos River at Brenham was collected and analyzed for water quality characteristics and the dat

What is raft foundation, Q. What is Raft Foundation? A raft or mat is c...

Q. What is Raft Foundation? A raft or mat is combined footing that covers the entire area beneath a structure and supports all the walls and coloumn when the allowable soil pre

Determine the dimension of the vertical side walls, Determine the dimension...

Determine the dimension of the vertical side walls for a rectangular open channel designed to convey 150 cfs of storm water runoff. The runoff is collected in the parking lots and

Determine the in-situ dry unit weight, Q. The following observations were r...

Q. The following observations were recorded in a Field density determination by sand-replacement method: Volume of Calibrating can = 1000 cm3 Weight of empty can = 10 N We

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd