Define the finish-to-start dependency, Civil Engineering

Assignment Help:

Sheet rock cannot be installed in the new house you are building until a building inspector approves the plumbing, electrical, HVAC, and insulation.  This is an example of:

  1. A constraint
  2. An assumption
  3. A start-to-finish dependency
  4. A finish-to-start dependency  

Solution: 4. the inspections must be finished before the sheet-rocking can start.


Related Discussions:- Define the finish-to-start dependency

Calculate the total passive earth resistance on the wall, A  retaining wall...

A  retaining wall, 4.5 m high, retains a soil with  c = 2 N/cm 2 ,  φ = 30° and g = 20 kN/m 3 , with horizontal surface level with the top of the wall. The backfill carries a surch

Diffrence between concrete road and bituminous road, Q. Diffrence between C...

Q. Diffrence between Concrete road and bituminous road? Concrete road belongs to rigid pavement and they don't deflect under traffic loads. Quite the reverse, bituminous pavem

Fixed end moments, For fixed beam(say for example fixed with a point load a...

For fixed beam(say for example fixed with a point load at midspan) how did we end up getting P*L/8...??

Designing of roadbase material, Question In General Specification for C...

Question In General Specification for Civil Engineering Works, designing of roadbase material is based on recipe approach. Give reason. Answer Designing of roadbase

Define the term- erection stresses, Define the term- erection stresses ...

Define the term- erection stresses The creep loss due to live load stress, erection stresses and other stresses of short duration may be ignored. The loss of prestress due to

Traditional marine piling system of steel tubular pile, Question What i...

Question What is problem in traditional marine piling system of steel tubular pile with concrete infill and what are key possible remedial measures? Answer In design

What is the absolute maximum shear stress, A strip load of considerable len...

A strip load of considerable length and 1.5 m width transmits a pressure of 150 kN/m 2 to the underlying soil. Verify the maximum principal stress at 0.75 m depth below the footin

Load transfer mechanism, Question What is load transfer mechanism for p...

Question What is load transfer mechanism for paving blocks in pedestrian footway? Answer In Hong Kong, footway is as a rule designed with paving slabs or interlocking b

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd