Define the finish-to-start dependency, Civil Engineering

Assignment Help:

Sheet rock cannot be installed in the new house you are building until a building inspector approves the plumbing, electrical, HVAC, and insulation.  This is an example of:

  1. A constraint
  2. An assumption
  3. A start-to-finish dependency
  4. A finish-to-start dependency  

Solution: 4. the inspections must be finished before the sheet-rocking can start.


Related Discussions:- Define the finish-to-start dependency

Compaction, describe how quality control is maintained in a rolled fill dam...

describe how quality control is maintained in a rolled fill dam

Explain interim inspection - underwater inspection of bridge, Explain the I...

Explain the Interim inspection - underwater inspection of bridge An interim inspection is an inspection scheduled at the discretion of the engineer. An interim inspection is us

Determine the types of untensioned reinforcement, Determine the types of un...

Determine the types of untensioned Reinforcement  Reinforcement used as untensioned steel should be one of the following types : (a)  Mild steel and medium tensile steel bar

Matlab program, for calculating the bending moment in which the loading and...

for calculating the bending moment in which the loading and the length of continuous beam is taken from the user

Proctor test for GSB material, what is the procedure for gsb proctor test f...

what is the procedure for gsb proctor test for matrial sampling for lab density

Building construction drawings, I need a drawing detail of expansion joints...

I need a drawing detail of expansion joints in building and different sizes

Construct the shear force and bending moment diagrams, A Beam A B 12 meter ...

A Beam A B 12 meter long rests on supports 9 meter apart the right hand end over hanging the supports by 1 m and the left hand end by 2 m . The beam carries a uniformity distribute

Embankment, Describe the various steps in embankment construction.

Describe the various steps in embankment construction.

Duration activity for cast-in-place foundation formwork, A concrete contrac...

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd