Define the critical path, Operation Management

Assignment Help:

The following is a table of activities associated with a project at Bill Figg Enterprises, their durations and what activities each must precede:

Activity Duration (weeks) Precedes

A (start) 1 B, C

B 1 E

C 4 F

E 2 F

F(end) 2 %u2014

a) Draw an AON diagram of the project, including activity durations.

b) Define the critical path, listing all critical activities in chronological order.

c) What is the project duration (in weeks)?

d) What is the slack (in weeks) associated with any and all noncritical paths through the project?

 


Related Discussions:- Define the critical path

A budget is using which manager who is using spreadsheet, a budget is using...

a budget is using which manager who is using spreadsheet software to prepare department budget is using which managerial skills according to Katz/1.human/ 2.technical/3.conceptual/

Explain the current maximum output of the process, I-mart is a discount opt...

I-mart is a discount optical shop that can fill most prescription orders in around 1 hour. The management is analyzing the processes at the store. There currently is one person ass

Benefits long-term employees in the firm''s home country, Under what condit...

Under what conditions is it ethically defensible to outsource production to a developing world where labor costs are lower when such actions also involve laying off long-term emplo

What are the types of the workforce flexibility, What are the types of the ...

What are the types of the workforce flexibility? Types of workforce flexibility: a. Functional flexibility (task flexibility or multi-skilled employees) b. Financial f

How hrm is described as a primary activity, In Porter's value-chain model ...

In Porter's value-chain model a. HRM is described as a primary activity b HRM is described as a support activity c HRM is not mentioned as an activity d HRM is describe

Sample mean chart - control charts for variables, Sample Mean Chart - Contr...

Sample Mean Chart - Control Charts for Variables This figure depicts a typical means chart, on which sample means would be progressively plotted, left to right. Two sets of c

Regression analysis, advantages of simple regression method for cost estima...

advantages of simple regression method for cost estimation.

Explain trade-offs among increased wages for unions, What are the trade-off...

What are the trade-offs among increased wages for unions, productivity effects and profitability effects on organizations?

Explain cost management a strategic emphasis, Do you have the test associat...

Do you have the test associated with the book Cost Management A strategic Emphasis, 5th edition

Explain were the colonists more responsible for winning it, Need reference/...

Need reference/cited for this question. • Were the British more responsible for losing the war or were the colonists more responsible for winning it? Use specific examples fr

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd