Define the crash rate for intersection, Civil Engineering

Assignment Help:

An intersection has a total entering traffic volume of 42,000 vehicles per day.  During the past three years, there have been a total of 35 reported intersection-related crashes.  What is the crash rate for this intersection?

Answer:

Rint = 35*106 / (365 * 3 * 42,000) = 0.76 crashes per MEV


Related Discussions:- Define the crash rate for intersection

Stairs, describe details about stairs and its type also draw sketch?

describe details about stairs and its type also draw sketch?

Inspection and testing, Q. Inspection and testing ? The inspection and ...

Q. Inspection and testing ? The inspection and tests on elastomer and the finished bearings are very important aspects of ensuring a satisfactory performance of the bearing. IR

Calculate the number of trucks for fleet working, A contractor was awarded ...

A contractor was awarded a Contract to excavate and haul 200,000-yds 3 of silty clay (USCS classification ML) with a bulking factor of 30%.  The contractor's fleet of dump trucks

Pumps, largest centrifugal pumps

largest centrifugal pumps

Conducting triaxial test, Question In conducting triaxial test to deter...

Question In conducting triaxial test to determine shear strengths for soil samples, what consolidation pressures should be specified? Answer It appears that the sele

Arrangement of piles in a pile cap to reduce bending moment, Arrangement of...

Arrangement of piles in a pile cap to reduce bending moment induced in piles Let's consider that piles are designed to intersect at a single common point in a pile cap. The re

Physical evaluation of food grains, Q. Physical evaluation of food grains? ...

Q. Physical evaluation of food grains? Food grains are judged for quality by their physical, chemical and microbiological examination. The physical examination includes chec

Calculate the daily standard production rate of equipment, Calculate the Da...

Calculate the Daily Standard Production Rate of Equipment An excavator with a bucket capacity of 3-yd 3 has a standard operating cycle time of 40 seconds. The daily standard p

Explain the term - non-bonded prestressed concrete, Explain the term - Non-...

Explain the term - Non-bonded Prestressed Concrete It is a method of construction in which the tendons are not bonded to the concrete. Ducts, housing the tendons, are not grout

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd