Define the cost per square foot of contact area, Civil Engineering

Assignment Help:

Define the Cost per Square Foot of Contact Area

The cost of concrete formwork is influenced by three factors:

1. Initial cost or fabrication cost that contains the cost of transportation, materials, assembly, and erection.

2. Potential reuse which decreases the final total cost per square foot of contact area. The data in Table indicates that the maximum economy can be achieved by maximizing the number of reuses.

588_Define the Cost per Square Foot of Contact Area.png

3. Stripping costs, this also includes the cost of cleaning and repair. This item tends to stay constant for each reuse up to a fixed point at which the total cost of repairing and cleaning start rising rapidly.

In deciding to use a specific formwork system, the initial cost should be evaluated versus the available budget for formwork cost. Some formwork systems tend to have a high initial cost, but through repetitive reuse, they become economical.

For example, slip forms have a high initial cost, but the average potential reuse (usually over 100 times) reduces the final cost per square foot of contact area for the type of formwork. In the case of rented formwork systems, the period of time the formwork is in use has a great effect on the cost of the formwork.


Related Discussions:- Define the cost per square foot of contact area

State the needs for high strength steel and concrete, State the Needs for h...

State the Needs for high strength steel and concrete In  prestressed  concrete construction, tendons have 3  small area of cross-section compared  to the cross-sectional  area

Lock entrance - docks, Lock Entrance: Wet docks have lock entrances to...

Lock Entrance: Wet docks have lock entrances to overcome the high fluctuations in water level in the sea. Figure 7 gives a layout of a lock entrance. It consists of a lock cha

Methods of constructing roads in marshy areas, Methods of Constructing Road...

Methods of Constructing Roads in Marshy Areas: The following methods are adopted for constructing roads in marshy areas: (a) Removal of soft soil and replacement with good

Overhanging beams, Do we take the whole length (including the over hanging ...

Do we take the whole length (including the over hanging portion when we say the "whole span" of th beam ?

Particle size distribution - soil compaction, Particle Size Distribution (G...

Particle Size Distribution (Gradation): The particle size distribution is determined by passing the aggregates through a set of standard IS sieves (Figure) and determining th

Distomat, write the brief description about distomat

write the brief description about distomat

Timer, grading classification

grading classification

Engineering mechanics, Characteristics of couple #Minimum 150 words accepte...

Characteristics of couple #Minimum 150 words accepted#

Engineering economics, Ask quA contractor has both a 3-cy and a 5-cy shovel...

Ask quA contractor has both a 3-cy and a 5-cy shovel in the equipment fleet. Select the minimum size shovel that will excavate 450,000 bcy of common earth in a minimum of 120 worki

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd