Define the Cost per Square Foot of Contact Area

The cost of concrete formwork is influenced by three factors:

1. Initial cost or fabrication cost that contains the cost of transportation, materials, assembly, and erection.

2. Potential reuse which decreases the final total cost per square foot of contact area. The data in Table indicates that the maximum economy can be achieved by maximizing the number of reuses.

588_Define the Cost per Square Foot of Contact Area.png

3. Stripping costs, this also includes the cost of cleaning and repair. This item tends to stay constant for each reuse up to a fixed point at which the total cost of repairing and cleaning start rising rapidly.

In deciding to use a specific formwork system, the initial cost should be evaluated versus the available budget for formwork cost. Some formwork systems tend to have a high initial cost, but through repetitive reuse, they become economical.

For example, slip forms have a high initial cost, but the average potential reuse (usually over 100 times) reduces the final cost per square foot of contact area for the type of formwork. In the case of rented formwork systems, the period of time the formwork is in use has a great effect on the cost of the formwork.


Related Discussions:- Define the cost per square foot of contact area

Explain the system curves - pumping system, Explain the System Curves - Pum...

Explain the System Curves - Pumping System Non-linear plot beginning on the y-axis at the Total Static Head (TSH) and plotted primarily based on the h f .

Point of virtual fixity of lateral loading for piles, Point of virtual fixi...

Point of virtual fixity and critical length of lateral loading for piles Some engineers can get confused about the difference between the two terms which are point of virtual

How can a temporary diversion to laid, Q. How can a temporary diversion to ...

Q. How can a temporary diversion to laid a cross flowing river in case of disruption to rail traffic over a major bridge lasting over 6 months. Ans.- Temporary diversion

Acidity and alkalinity - chemical characteristics of water, Acidity and Alk...

Acidity and Alkalinity - Chemical Characteristics of Water Acidity: Capacity to neutralize bases and is a measure of acids in water. Acidity is measured by titrating the s

Estimate prestress losses, Given: beam deminsions: flange width=22" FL...

Given: beam deminsions: flange width=22" FLANGE THICKNESS=7" WEB WIDTH=7" SECTION HEIGHT=40" f'c=5000psi f'ci=3500psi fpu=270ksi Ap=eighteen 1/2" diam strands superim

Digit of cells for concrete box girder bridges, Question How does an engine...

Question How does an engineer determine digit of cells for concrete box girder bridges ? Answer If depth of a box girder bridge exceeds 1/6 or 1/5 of bridge width, then it is o

What is the role of sunfilter in building, QUESTION (a) Using an illu...

QUESTION (a) Using an illustration, describe what happens to sunrays when it passes through the atmosphere to reach the ground. (b) What is the role of a sunscreen/sunfil

Matrix method of analysis, Ask question #Explalin a joint frame by stiffne...

Ask question #Explalin a joint frame by stiffness method

Levelling, what is the types of levelling

what is the types of levelling

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd