Define the arrow diagramming method, Civil Engineering

Assignment Help:

Define the Arrow Diagramming Method

  • Activity-on-Arrow (Branch) with nodes as dependencies
  • Uses finish-to-start precedence only. The solution method for an activity on arrow problem is essentially the same as for the activity-on-node problems requiring forward and backward passes to determine the earliest and latest dates.
  • May require use of dummy activities to maintain proper logic of various construction activities. If two activities have the same starting and ending events, a dummy node is required to give one activity a uniquely identifiable completion event.
  • A dummy is treated as an activity (represented by a dotted line on the arrow network diagram), that indicates that any activity following the dummy cannot be started until the activity or activities preceding the dummy are completed. The dummy activity does not consume time or any resource.
  • Review Figure Activity-on-Arrow diagram below. Note the dummy activity showing the relationship between the material procurement and installation of the components.

 

1152_Define the Arrow Diagramming Method.png

Diagram- Activity on Arrow Diagram

 


Related Discussions:- Define the arrow diagramming method

Explain the secondary treatment for wastewater, Explain the Secondary treat...

Explain the Secondary treatment for wastewater Secondary Treatment: to remove soluble BOD that escapes the primary treatment and to provide added removal of suspended solids.

Statics, Applications of statics

Applications of statics

Poly tetra fluoro ethylene (PTFE) is used in sliding bearing, Question W...

Question Why Poly tetra fluoro ethylene (PTFE) is usually used in sliding bearings? Answer The choice of sliding surface of bearings is of very important importance sinc

Factors affecting location decision, Factors Affecting Location Decision: ...

Factors Affecting Location Decision:   Mining, quarrying and heavy manufacturing have capital intensive facilities that are costly to build and cover large area and use large q

Show the specification of bricks, Q. Show the Specification of Bricks? ...

Q. Show the Specification of Bricks? Specification of Ist class Bricks- 1. Table moulded and wire cut. 2. It should have edges and parallel faces. 3. If struck with ha

Design of the aeration basin based on solids retention time, Design of the ...

Design of the Aeration Basin Based on Solids Retention Time - sewer construction: You are provided the following information about a municipal wastewater treatment plant. That

Show the functions of diaphragm walls, Q. Show the Functions of diaphragm w...

Q. Show the Functions of diaphragm walls? The functions of diaphragm walls are as follows: (i)  It is designed to maintain soils during the construction of underground

Best efficiency point and operating point for pumps, Q. Best efficiency poi...

Q. Best efficiency point and operating point for pumps? In a pumping system, a system curve can be derived based on static head needed to lift up the fluid and variable head be

Tension member, Explain various forms of tension members.

Explain various forms of tension members.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd