Define superposition method, Civil Engineering

Assignment Help:

Define Superposition Method

 1. Remove enough redundant supports to reduce the structure to a statically determinate condition

2. Calculate the deflections at the previous locations.  Use consistent sign conventions

3. Apply each redundant support as a load and find the deflections at the redundant support as a function of these forces

4. Use superposition to combine the deflections due to the actual and redundant loads.  The total deflection must be known (at a support is typically zero).


Related Discussions:- Define superposition method

Discuss about the post-tensioning systems, Discuss about the post-tensionin...

Discuss about the post-tensioning systems In most of post-tensioning systems, when the cable is tensioned and the jack is released to transfer prestress to concrete, the fricti

Define well steoning, Q. Define Well Steoning? It is the side wall of w...

Q. Define Well Steoning? It is the side wall of well foundation. It is built of masonry or cement concrete not less than M 10 grade, sufficient bond rods should be provided to

Explain the kinematic viscosity, Explain the Kinematic Viscosity Ratio ...

Explain the Kinematic Viscosity Ratio of a fluid's Viscosity to the same fluid's Density.  Greek symbol: ν nu    ν = μ/ρ = Absolute Viscosity/Mass Density    Units: ft

REQUIREMENT OF GOOD BUILDING STONE, HOW TO MAKE A GOOD BUILDING .? TELL ABO...

HOW TO MAKE A GOOD BUILDING .? TELL ABOUT SOME TIPS OF REQUIREMENT OF GOOD BUILDING STONE? AND SAY ABOUT CEMENT?

Closing and opening of expansion joints and contraction join, Question ...

Question In case of for unreinforced concrete carriageway, what will succession of closing and opening of expansion joints and contraction joints? Answer Take a case t

Define the finish to finish activity, A finish-to-finish activity is best d...

A finish-to-finish activity is best described as: The "from" activity must finish before the "to" activity can finish The "from" activity must finish before the "to" acti

Calculate the net annual profit - construction management, A heavy equipmen...

A heavy equipment rental company uses a high interest rate of 30% for the rental of a specialty heavy haul dump truck.  The net annual profit for this investment is most nearly:

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd