Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

surveying, calculation of corrected fore bearings and back bearings i

calculation of corrected fore bearings and back bearings in

Concrete surface finish - limitations of ultrasonic system, Define Concrete...

Define Concrete Surface Finish - Limitations of Ultrasonic System? The smoothness of the surface under test is important to ensure proper acoustical contact between the transdu

Plumbing technology, This assessment will test Learning Outcomes 3 and 4 as...

This assessment will test Learning Outcomes 3 and 4 as well as the component of Learning Outcome 1 as it refers to waste disposal for the Plumbing Technology. The student is expect

Coating on concrete – complete im-permeability to moisture, Q. Coating on c...

Q. Coating on concrete – complete im-permeability to moisture? In designing protective coating on concrete structures, stoppage of water ingress by the coating is generally req

Define the approach velocity, Define the Approach Velocity Typical prob...

Define the Approach Velocity Typical problems have negligible approach velocity.  v 1 = Q/A, where A = the cross-sectional area of flow in the channel. The value is not the ve

How can designer cater for stability of minor slips, Question Soil nail...

Question Soil nails are mostly designed for stabilization of key slips . How can designer cater for stability of minor slips? Answer There are many methods to treat mi

Foundation, difference between raft and pile foundation question..

difference between raft and pile foundation question..

Plumbing, what is the different kinds of pipes and fittings

what is the different kinds of pipes and fittings

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd