Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Define the finish-to-start dependency, Sheet rock cannot be installed in th...

Sheet rock cannot be installed in the new house you are building until a building inspector approves the plumbing, electrical, HVAC, and insulation.  This is an example of:

Functions and desirable characteristics of pavements, Functions and Desirab...

Functions and Desirable Characteristics of Pavements Function of Pavement A pavement is that part of a road on which vehicles travel. The pavement has the following f

Constructed wetland design guidelines, Develop a simple urban constructed w...

Develop a simple urban constructed wetland design guidelines and drawings. Your report should include the following: I. Data required for the design II. Types of constructed

Glazed tiles for construction material, Q. Glazed tiles for Construction Ma...

Q. Glazed tiles for Construction Material? Glazed tiles are only meant for dadoes of bath room, Toilet and kitchens etc as they have no strength . Normally 8'' x 4'' g

Steel structure, what do mean by outstand element of compression flange, in...

what do mean by outstand element of compression flange, internal element of compression flange and web general

Construction mesurment, Measurement quantity of excavation, concrete, formw...

Measurement quantity of excavation, concrete, formwork as my assignment brief.

Define pneumatic tools for underwater inspection of bridge, Define Pneumati...

Define Pneumatic Tools for Underwater Inspection of Bridge? These are more efficient than hand tools and cause less diver fatigue. The disadvantages are that below about 20 m,

Continuous prestressed concrete beam design , Assignment:-Continuous Prestr...

Assignment:-Continuous Prestressed Concrete Beam Design A cast in-place 3-span prestressed concrete T-beam is to be designed. The T-beam concsists of an 8-in thick reinforced

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd