Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Calculate the annual cost of alum - coagulation, Incoming water contains 2....

Incoming water contains 2.5 mg/L as a substance of natural alkalinity (HCO 3 - ). The flow rate is 9.5 ML/day). (a) What feed rate is required if the alum dose is 7 mg/L and

Rectilinear motion, A train starts from rest as A and accelerates at 1,7m/...

A train starts from rest as A and accelerates at 1,7m/s2 to full speed at which it maintains until the brakes gives it a deceleration of 1,7m/s2 to stop at B. AB=1,6km. determine

Disparities b/w epoxy grout cement grout and cement mortar, Question What a...

Question What are the key disparities between epoxy grout cement grout and cement mortar ? Answer Epoxy grout contains of epoxy resin, epoxy hardener and sand or aggregates.

Find out load carrying capacity, Q.for ISMB200 having 6.70 m span simply su...

Q.for ISMB200 having 6.70 m span simply supported so find out load carrying capacity.

Demonstrate the design of prestressed concrete poles, Demonstrate the Desi...

Demonstrate the Design  of Prestressed concrete poles Prestressed concrete poles are generally designed as members with uniform prestress since they are subjected to bending mo

Marine piles circular in cross section, Question Give reason that why a...

Question Give reason that why are most marine piles circular in cross section? Answer As marine piles, there are a number of options existing for selection, name as H-

Irrigation, what is a balancing depth

what is a balancing depth

Can you explain curved heads, Q. Can you explain Curved heads ? In case...

Q. Can you explain Curved heads ? In case of rivers carrying high discharges of the order of 28300 m 3 Is and above, Gale's recommendations are more conservative than Spring's

Define alum (aluminum sulfate) caogulation, Define Alum (aluminum sulfate) ...

Define Alum (aluminum sulfate) Caogulation Purchased as dry or liquid alum { Al 2 (SO 4 ) 3 ,14 H 2 O}, MW 594 (other formulas with varying number of water molecules also u

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd