Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Angle&direction, whate does mean bearing?with example

whate does mean bearing?with example

Road survay, how many programmes in road survey by level matichine and ts?

how many programmes in road survey by level matichine and ts?

Obstacles, Obstacles which can be ranged

Obstacles which can be ranged

Determine about the prestressed concrete, Determine about the Prestressed c...

Determine about the Prestressed concrete Prestressed concrete is a special type of concrete in which internal stresses of a suitable nature, magnitude and distribution are int

What is the correct value of the specific gravity, In a specific gravity te...

In a specific gravity test, 1.17 N of oven-dired soil was taken. The weight of pyknometer, soil and water was obtained as 6.51 N. The weight of pyknometer full of water alone was 5

Calculate the total duration for the four activity project, Calculate the T...

Calculate the Total Duration for the Four Activity Project Solution:      Scheduling work activity has associated time duration. The durations shown in the Table were e

What is the meaning of concordant prestressing, Concordant Prestressing ...

Concordant Prestressing In this type of prestressing, tendons follow a concordant profile. The concordant profile of  tendons does not change the support reactions in a statica

Compute the skin friction resistance, A 30 cm diameter pile penetrates a de...

A 30 cm diameter pile penetrates a deposit of soft clay 9 m deep and rests on sand. Compute the skin friction resistance. The clay has unit cohesion of 0.6 kg/cm 2 . Suppose

Total station - uses and mining, Total station - uses and mining: Use...

Total station - uses and mining: Uses:- Total stations are mainly used by land surveyors and Civil Engineers, either to record features as in Topographic Surveying or to

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd