Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Show the silt curtain touching seabed, Q. Show the Silt curtain touching se...

Q. Show the Silt curtain touching seabed? Silt curtains are impermeable vertical barriers extending from seawater surface to their designed depths. Curtains are held in a verti

What are rules for working of dip lorries, Q. What are rules for working of...

Q. What are rules for working of Dip lorries and their protection arrangements on a single line section explain with sketches? Ans.-Rules for working of Dip lorries - i. Sub

Explain resultant force on a given area of an inclined plane, Resultant For...

Resultant Force on a Given Area of an Inclined Plane The resultant force is calculated from the average pressure:    R = (AVERAGE P)(A)

Which direction of reinforcement must be provided, Question In the desi...

Question In the designing of a simply supported skew bridge , which direction of reinforcement must be provided? Answer In conventional design of steel reinforcement f

What do you know about shallow piers, Q. What do you know about Shallow Pie...

Q. What do you know about Shallow Piers? In case of some of the existing bridges, piers may be shallow and grip may be found to be inadequate. Protection round piers is then re

The regulations and specification that followed for compacti, what are The ...

what are The regulations and specification that followed for compaction works for earth dam in Oman.

N-type semiconductor is an example of what semiconductor, N-type semiconduc...

N-type semiconductor is an example of what semiconductor? Answer : N-type semiconductor is an example of extrinsic semiconductor.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd