Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Premix carpet open graded, what is premix carpet open graded and where is i...

what is premix carpet open graded and where is it used and what are its limitations ?

Show suspended impurities in water, Q. Show Suspended Impurities in water? ...

Q. Show Suspended Impurities in water? The solid particles which are dispersed in water are referred as suspended Impurities. These are microscopic as under-

Slope IN Civil, How to calculate the slope in civil engineering?????

How to calculate the slope in civil engineering?????

#title., desirable properties in green concrete

desirable properties in green concrete

Example, slope deflection with settlement

slope deflection with settlement

Timber, uses of timber in civil engineering field and its physical state an...

uses of timber in civil engineering field and its physical state and chemical formula or symbol?

Contractor to continue concreting works, Question If on-site slump test fai...

Question If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works ? Answer This is an extremely traditional question raised by

Pre-stressing work, Under which situation shall engineers use jacking in ag...

Under which situation shall engineers use jacking in agreement end only and from both ends in pre-stressing work?

Hoyers long line system pre-tensioning, Hoyers long line system pre-tension...

Hoyers long line system pre-tensioning When concrete attains the required strength,  jacks  are released and tendon wires in-between various units are cut.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd