Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Ild and rolling load, how to solve ild and rolling load problem for shear f...

how to solve ild and rolling load problem for shear force and bending moment with the diagram.

Whole barings, Ask question #Minexaple of wholeiwhole baring 100 words acce...

Ask question #Minexaple of wholeiwhole baring 100 words accepted#

What is n-value of standard penetration test, Define and discuss the variou...

Define and discuss the various factors that help decide the number and depth of bore holes needed for subsoil exploration. What is 'N-value' of Standard Penetration Test? How do

Application of bitumen to driven piles, Q. Application of bitumen to driven...

Q. Application of bitumen to driven piles? In a certain area of H-piles subjected to ground water table fluctuation, painting is occasionally applied on the surface of H-piles

Design of the aeration basin based on solids retention time, Design of the ...

Design of the Aeration Basin Based on Solids Retention Time - sewer construction: You are provided the following information about a municipal wastewater treatment plant. That

Precast concrete jacking pipes, Question While precast concrete jackin...

Question While precast concrete jacking pipes , from time to time grout holes are calculated inside these precast pipes. Give specific and key reasons? Answer Grout h

Upper bound of indirect tensile strength, Question While designing rese...

Question While designing reservoirs, indirect tensile strength of the concrete mix is particular to be less than a specific value such as 2.8N/mm2 for potable water. Why ought

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd