Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Digit of cells for concrete box girder bridges, Question How does an engine...

Question How does an engineer determine digit of cells for concrete box girder bridges ? Answer If depth of a box girder bridge exceeds 1/6 or 1/5 of bridge width, then it is o

Explain the components of a rebound hammer, Explain the Components of a reb...

Explain the Components of a rebound Hammer? Several components of a rebound hammer are displayed in below Figure. 1. Concrete surface; 2. Impact spring; 3. Rider on gui

Factors affecting location decision, Factors Affecting Location Decision: ...

Factors Affecting Location Decision:   Mining, quarrying and heavy manufacturing have capital intensive facilities that are costly to build and cover large area and use large q

Advantages of casings for mini-piles, Question Advantages of casings ...

Question Advantages of casings for mini-piles ? Answer Left-in casings for mini-piles have next advantages as follows- (i) recover resistance to corrosion of ma

Explain the ion exchange water softening, Explain the Ion Exchange water So...

Explain the Ion Exchange water Softening Softening is usually done using a resin (natural or synthetic long chain chemical with a sodium ion attached). When water containing ha

Moment of force on shoulders, During weight training,an athlete pulls a wei...

During weight training,an athlete pulls a weight of 500 N with his arms pulling on a handlebar connected to a universal machine by a cable.Find the moment of the force about the sh

Structural connection loosening - deterioration in steel, Define Structural...

Define Structural connection loosening - Deterioration in Steel? Structural connections joined together by rivets or bolts have a tendency to work loose over an extended period

Failure analysis in designing of a structure, Modes of failure • For sa...

Modes of failure • For safe design, a knowledge of the possible modes of failure is also necessary, e.g. failure of the structure could occur due to - Tensile fracture due t

Deflection of beams, 1) A propped cantilever beam ABC is 7m long.It has th...

1) A propped cantilever beam ABC is 7m long.It has the point C fixed and Point A on a roller support.It carries a 200Kn point load at a distance 3m from A.There is a moment of 80KN

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd