Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Determine the common ways to present the project schedule, Common ways to p...

Common ways to present the project schedule include all except: a. Gantt charts b. Milestone charts c. PERT charts D. Project Network Diagrams with dates added   So

Tests on cement, Tests on Cement: The following tests are conducted o...

Tests on Cement: The following tests are conducted on cement in a project site: Setting Time Initial setting time Final setting time Compressive Streng

Explain the kinematic viscosity, Explain the Kinematic Viscosity Ratio ...

Explain the Kinematic Viscosity Ratio of a fluid's Viscosity to the same fluid's Density.  Greek symbol: ν nu    ν = μ/ρ = Absolute Viscosity/Mass Density    Units: ft

Dissimilarity in methods of compaction, Question Are there any dissimil...

Question Are there any dissimilarity in methods of compaction between clayey soil material and sandy material ? Answer The three key actions of compaction are static

Cement, manufacture of cement by dry process

manufacture of cement by dry process

Which type of pile cap transfers loads equally to piles, Q. Which type of p...

Q. Which type of pile cap transfers loads equally to piles, flexible pile cap orrigid pile cap? Loads from columns transferring to pile cap persuade tensile forces at the bott

Streams not wholly alluvial - alluvial streams, Streams Not Wholly Alluvial...

Streams Not Wholly Alluvial In streams which are not wholly alluvial, consisting of bed of pebbles, rock, etc. the liner waterway is kept equal to the actual surface width of

Verify the grain specific gravity, Verify the grain specific gravity In...

Verify the grain specific gravity In a specific gravity test, the weight of the dry soil taken is 0.66 N. The weight of the pyknometer filled with this soil and water is 6.756

Movement accommodation factor for joint sealant, Movement accommodation fac...

Movement accommodation factor is normally specified by manufacturers of joint sealants for designers to design dimension of joints. It is stated as the total movement that a joint

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd