Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

WMM, what is wmm what are all the uses of that wmm

what is wmm what are all the uses of that wmm

Meaning of driving succession of driven piles, Question What is meaning...

Question What is meaning of driving succession of driven piles? Answer In Basement construction, if piles are driven from centre to perimeter, there is a propensity o

Two way slab, how can i design reinforcement for a two way slab

how can i design reinforcement for a two way slab

Influenza virus, humans who - are the most likely to contact swine flu

humans who - are the most likely to contact swine flu

Numericals on settlement of foundation, A footing foundation for a water to...

A footing foundation for a water tower carries a load of 9000 kN and is 3.6 metres square. It rests on dense sand of 9 m thickness overlying a clay layer of 3 metres depth. The cla

Vitrification, what is this process?whats its procedure?need some case stud...

what is this process?whats its procedure?need some case studies

Landslides induced by rainfall, Landslides induced by rainfall After r...

Landslides induced by rainfall After rainfall, groundwater pressure is built up and this elevates ground water table. Water inside the pores of soil reducesthe effective stres

Stress analysis, • The previous load analysis represents a first and necess...

• The previous load analysis represents a first and necessary step in the analysis of the given structure but it does not tell us whether the given load can be safely supported (i.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd