Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

State the location and spacing of borings, Location and spacing of borings ...

Location and spacing of borings The location, spacing of geophysical profiles, soundings and borings should be such that,  you will be in a position to accurately predict the

Assignment, I need to find support reactions at O for the beam with a distr...

I need to find support reactions at O for the beam with a distributed load, a 6 kN moment couple at A and a 3 kN axial load as shown in picture.

Show the grout curtain around excavation, Q. Show the Grout curtain around ...

Q. Show the Grout curtain around excavation? When excavation work is performed in grounds with highly permeable soils, other than installation of well points to lower down grou

Example for productivity analysis and improvement, Example for Productivity...

Example for Productivity Analysis and Improvement An excavator with a bucket capacity of 3-yd 3 has a standard production rate of 2,160-yd 3 for an 8-hour day.  The job site

Stairs, what are the basic reqiureents for stairs. explain the basic proced...

what are the basic reqiureents for stairs. explain the basic procedures for stair construction

Wearing course or additional thickness be designed on piers, Question S...

Question Shall layer of wearing course or additional thickness be designed on surface of piers ? Answer In designing of piers , considerations have to be given to

Overhanging beams, Do we take the whole length (including the over hanging ...

Do we take the whole length (including the over hanging portion when we say the "whole span" of th beam ?

Consultant , how to convert a varying distributed load to a uniformly distr...

how to convert a varying distributed load to a uniformly distributed load

Construct the correct network for project, A project requires that activiti...

A project requires that activities A and B can be started independently and activities C and D are independent but can be started after A and B have been completed. Activity E can

Rehabilitation of Concrete Roads, Step by step rehabilitation strategies wi...

Step by step rehabilitation strategies with drawing, figures, and illustrations

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd