Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Bending moments& shear force, calculate bending &shear force of 16kn/m and ...

calculate bending &shear force of 16kn/m and draw the shear force and bending moment diagrams

Harbour, typical layout showing dock,quay.jetties,turning circle,pier

typical layout showing dock,quay.jetties,turning circle,pier

Concreting, #question why cracks develops on the surface of concrete on the...

#question why cracks develops on the surface of concrete on the next day of casting?

Rolling - binder, Rolling - Binder: The layer thickness is 40-50 mm. R...

Rolling - Binder: The layer thickness is 40-50 mm. Rolling is done in three stages : Initial Rolling By 80-100 kN smooth wheeled roller. Intermediate Rolling B

Slope, how to calculate a slope

how to calculate a slope

Potential advantages of segmental tunnelling, Q. Potential advantages of se...

Q. Potential advantages of segmental tunnelling when compared with hand-shield pipe-jacking? In segmental tunnelling, jacks are installed at the shield so that itisn't necessar

Determine about the lee-mccall system, Determine about the Lee-McCall syste...

Determine about the Lee-McCall system In the Lee-McCall system, high-tensile strength bars of diameter varying from 12 to 40 rnrn are used as tendons. These bars are threaded a

How can you design side slope of bank, Q. How can you design Side Slope of ...

Q. How can you design Side Slope of bank? Angle of bank should be flatter than angle of repose of pitching material. Angle of repose of sand is 2:1 while that of stone is about

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd