Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Purpose of tar in bituminous materials, Q. Purpose of tar in bituminous mat...

Q. Purpose of tar in bituminous materials? Tar is usually incorporated in bituminous materials due to the below reasons: (i)  Blending of tar with bitumen possesses better b

How to calculate the combined stresses, Compute the stresses at top and bot...

Compute the stresses at top and bottom fibers in a simply supported pre-stressed concrete beam with a rectangular cross section, 250 mm wide and 450 mm deep, as shown in Figure, at

Estimation of loading carrying capacity, Question While designing mini...

Question While designing mini-piles , should strength of grout be disused during estimation of loading carrying capacity? Answer While designing min-piles, there will

Inspection and testing, Q. Inspection and testing ? The inspection and ...

Q. Inspection and testing ? The inspection and tests on elastomer and the finished bearings are very important aspects of ensuring a satisfactory performance of the bearing. IR

Third law of thermodynamics, Is there any application by using the third la...

Is there any application by using the third law of thermodynamics. A Actual application without explained the calculation

Calculate the invert elevation of the sewer pipe, 1. The center line elevat...

1. The center line elevation of the proposed roadway at station is 345+25.50 is 327.36-ft.   The existing ground top of cut elevation (ft) is most nearly: 2. A design engineer c

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd