Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Analyse the state of stress at the critical section, Analyse the state of s...

Analyse the state of stress at the critical section: A prismatic bar of circular section with 80 mm diameter is subjected to bending moment of 5 kN-m and a torque of 7 kN-m. A

Direction of placing the main weight of reinforcement, Q. Direction of plac...

Q. Direction of placing the main weight of reinforcement in concrete pavement? The reinforcement of concrete pavement is typically in the form of longmesh type. A road generall

Strength of materials, An I-section beam 350*200mm2 has a web thickness of ...

An I-section beam 350*200mm2 has a web thickness of 12.5mm & a flange thickness of 25mm. It carries a shearing force of 200KN at a section. Sketch the shear stress distribution acr

Determine the total active thrust by rebhann''s method, A retaining wall 3....

A retaining wall 3.6 m high supports a dry cohesion less backfill with a plane ground surface sloping upwards at a surcharge angle of 20° from the top of the wall. The back of the

Show the design of howe truss, Q. Show the Design of Howe truss? Design...

Q. Show the Design of Howe truss? Design of Howe truss is the opposite to that of Pratt truss in that the diagonal members are slanted in the direction opposite to that of Prat

Semi dense bituminous concrete, Semi Dense Bituminous Concrete: Semi ...

Semi Dense Bituminous Concrete: Semi Dense Bituminous Concrete (SDBC) is similar to BC, but with a higher void content (5-10 per cent, as against 3-5 per cent in the case of

Bond performance of bar reinforcement, Question Does occurrence of rust hav...

Question Does occurrence of rust have adverse collision to bond performance of bar reinforcement ? Answer In fact, presence of rust in bars cannot have adverse impact to the bo

Calculate the amount of import or export, Calculate the Amount of Import or...

Calculate the Amount of Import or Export For the project site shown in Figure, the amount of import or export to bring the entire site to elevation 90-ft is most nearly:

Chain surveying, Explain me about obstacles in chain surveying and what is ...

Explain me about obstacles in chain surveying and what is meant by cross staff,offsets?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd