Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Bearing pressure on soil nail, Question What is relation of bearing pr...

Question What is relation of bearing pressure on soil nail head to ratio La/Lb, where La is length of soil nail before potential slip circle as Lb is length of soil nail beyo

Castigliano theoremn, what is vertical deflection of a beam, a conservative...

what is vertical deflection of a beam, a conservative structure and of what use is castigliano theoremn

Higway engineering, Ask question Design the pavement by group index method ...

Ask question Design the pavement by group index method for heavy traffic using following subgrade data Soil passing 75micron sieve =65%,liquid limit =40%plastic limit =20% #Min

door shutters, what is the difference between paneled and glazed shutte

what is the difference between paneled and glazed shutter

Moisture content, What is moisture content for road work

What is moisture content for road work

State the importance of structural element, State the importance of structu...

State the importance of structural element If this structural element is used as a beam element, subjected to self load and other imposed transverse loads, then the bottom fibr

Boundary ratio of weight of hammer to weight of pile, Question If n a n...

Question If n a number of codes, they boundary ratio of weight of hammer to weight of pile for pile driving. What will be the key reason for this? Answer As a hamm

Construction mesurment, Measurement quantity of excavation, concrete, formw...

Measurement quantity of excavation, concrete, formwork as my assignment brief.

., WHAT IS PILE CORROSION

WHAT IS PILE CORROSION

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd