Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Work, Grouted or Penetration Macadam:

Grouted or Penetration Macadam:

Matlab program, for calculating the bending moment in which the loading and...

for calculating the bending moment in which the loading and the length of continuous beam is taken from the user

Geodesy, what is the difference between geodesy and plane survey

what is the difference between geodesy and plane survey

Indicate quality of rock foundation, Question During piling works, norm...

Question During piling works, normally founding levels of bored piles are definite by using total core recovery or rock quality designation (RQD). Are there any problems by

Explain tension and compression anchorage length, Q. Explain Tension and co...

Q. Explain Tension and compression anchorage length? Tension anchorage length vs. compression anchorage length Tension anchorage length of steel reinforcement in concrete

Pelton wheel, what is the use of the pelton wheel

what is the use of the pelton wheel

Determine the expected extension at the jack, A cylindrical concrete tank,...

A cylindrical concrete tank, 30 m external diameter, is to be prestressed circumferentially by means of  high-strength steel wire (E, = 2 x  10 5   N/mm 2 )  jacked  at 4 points, 9

Grouting in segmental linings in tunnels, Q. Grouting in segmental linings ...

Q. Grouting in segmental linings in tunnels? Grouting is typically carried out under pressure in segmental linings at the time of tunnel construction due to the below reasons:

Prismatic compass, Figure, working,principle of prismatic compass

Figure, working,principle of prismatic compass

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd