Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Manage civil work design, Ask question #Minimum 1Make a detailed list of al...

Ask question #Minimum 1Make a detailed list of all constraints and requirements to the bridge design00 words accepted#

Survey, Operation in chain surveying

Operation in chain surveying

Doors, rolling steel door

rolling steel door

Why nautical mile is different from statute mile, One nautical mile is desc...

One nautical mile is described by one latitude minute of arc (there are 60 like minutes to a degree). This equals 1852 meters, and roughly (but coincidentally) 2000 yards or 6000 f

Define channel jig, Define Channel Jig a) A channel jig is the simplest...

Define Channel Jig a) A channel jig is the simplest form of box jig. b) The work is placed in a channel shaped trough and clamped by mean of screw. c) It is utilized

WMM, what is wmm what are all the uses of that wmm

what is wmm what are all the uses of that wmm

Simulink software, Using Matlab/ Simulink software to model the overall bui...

Using Matlab/ Simulink software to model the overall building fabric heat transmit characteristics, in order to estimate the maximum rate of heat loss (kW) from the building under

Explain the unit hydrograph method, Q.- Explain the Unit hydrograph Method ...

Q.- Explain the Unit hydrograph Method for estimation of peak flood discharge in a river. Ans.- Unit hydrograph Method A hydrograph is a representation of hydraulic cha

Estimation of design flood discharge, Q. Estimation of design flood dischar...

Q. Estimation of design flood discharge? These methods are also in vogue for estimating maximum discharge. Discharge estimated using the above three methods may be compared wit

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd