The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Show the side clearance of pipes in trenches, Side clearance of pipes in tr...

Side clearance of pipes in trenches From the design point of view, it's predominant to minimize the width of pipe trenches due to thebelow reasons: (i)  Higher cost of exca

Explain resultant force on a given area of an inclined plane, Resultant For...

Resultant Force on a Given Area of an Inclined Plane The resultant force is calculated from the average pressure:    R = (AVERAGE P)(A)

Surveying, what do you understand by the term local attraction

what do you understand by the term local attraction

Which is stronger solid steel rod or hollow steel pipe, On a per pound basi...

On a per pound basis, steel pipe is stronger in bending and is less likely to buckle in axial compression.

Calculate the diameter of the stockpile, 1. On a 5-acre level terrain build...

1. On a 5-acre level terrain building site, an earthwork contractor has instructed her crew to strip and grub the topsoil of a 60,000-ft 2 proposed building pad to a minus 2-ft su

Force systems and equlibrium, write short notes about force systems and equ...

write short notes about force systems and equilibrium

Ecology, subdivisions of ecology

subdivisions of ecology

Recognize the losses of prestress, Recognize the losses of prestress Re...

Recognize the losses of prestress Recognising the losses of prestress which take place after the prestressing OF concrete structural elements, it is to be appreciated that pres

Fluid mechanics , i have three civil engineering fluid mechanics. 1 manomet...

i have three civil engineering fluid mechanics. 1 manometer problem 2 estimate the discharge for a channel 3 pipe system - direction of flow in line and what the value of flow in l

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd