Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Explain the statements about the critical path method, 1. Determine a netwo...

1. Determine a network diagram method that uses only finish-to-start relationships and may use dummy activities to define logical relationships.  2.  Precedence diagr

What is the safe bearing capacity of wide strip footing, A loading test was...

A loading test was conducted with a 300 mm square plate at depth of 1 m under the ground surface in pure clay deposit. The water table is situated at a depth of 4 m below the groun

Fly levelling, what is meant by fly levelling and when it is carried out ?

what is meant by fly levelling and when it is carried out ?

Construction water, what should we do if alkalinity in water is greater tha...

what should we do if alkalinity in water is greater than 25

Engineering Graphics, Draw a parabola , height 40mm and bass 120mm using of...

Draw a parabola , height 40mm and bass 120mm using offset method

WBM Road, if the WBM Road is constructed with 80mm , 40mm metal what will b...

if the WBM Road is constructed with 80mm , 40mm metal what will be the depreciation factor per year, how much thickness of the layer will be reduced per year due to trafic and rai

Mechanism of taking up loads for concrete paving blocks, Mechanism of takin...

Mechanism of taking up loads for concrete paving blocks  Paving for concrete blocks comprises closely packed paving blocks in pre-determined patterns and tiny joint spaces bet

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd