Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

What is dead weight, Dead weight Dead loads are the weight of perma...

Dead weight Dead loads are the weight of permanent components of the structures such as the weight of the elements and spheres, casing weight, weight of the false ceiling a

Human resource, Ask question #Minimum 100 words acceFor this discussion, lo...

Ask question #Minimum 100 words acceFor this discussion, look at a specific country of your choice. Develop two brief introductions, one for a U.S. peer, and one for a peer in anot

Calculate the equivalent uniform annual cost, A contractor purchased an exc...

A contractor purchased an excavator for $100,000. The life expectancy is 10-years. With the annual interest rate at 7%, the annual cost for the excavator is most nearly: Solutio

Retaining walls, Retaining Walls: Needed to retain the fill portion, a...

Retaining Walls: Needed to retain the fill portion, and generally constructed in dry stone masonry with pucca bunds (Figure). Figure: Typical Design for a Retaining

Quality of constraction material ., haw to control quality of constraction...

haw to control quality of constraction material and it''s stage of control, control management, quality of performance ,organization for control

School building, from surveying to school building finish

from surveying to school building finish

Air infiltration, Using Matlab/ Simulink software, verify the heating requi...

Using Matlab/ Simulink software, verify the heating requirement (kW) for the building because of  air infiltration and natural ventilation. Note that this needs you to estimate air

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd