Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Modulus of elasticity of light-weight concrete, Modulus of elasticity of li...

Modulus of elasticity of light-weight concrete The modulus of elasticity of light-weight concrete is about 50 to 55% of that of normal-weight concrete. The loss of prestresses

What is codal provisions, According to National Building Code (Sp:7 1970), ...

According to National Building Code (Sp:7 1970), the differential settlement shall be kept within the limits to which the superstructure can accommodate itself without harmful dist

Use of primers in joint sealant, Q. Use of primers in joint sealant? Mo...

Q. Use of primers in joint sealant? Most of the joint sealants applied in concrete joints are adhesive and recommended joint width/depth of joint sealant is from 2:1 to 1:1 as

Construction management, i would like to get a project done. I have some pl...

i would like to get a project done. I have some plans and I need a cost estimate on how much it will cost to get it constructed.

Spacing of manholes in straight sections, Question Spacing of manhole...

Question Spacing of manholes in straight sections for diverse pipe sizes is stated in Storm water Drainage Manual. How are figures arrived on? Answer For pipe size

Embankment construction, Embankment Construction: Selection of Soil...

Embankment Construction: Selection of Soil Soil is the material used for embankment construction, though other materials like rock and fly-ash are also used in specia

Structural engg, how static and dynamic frames are works?

how static and dynamic frames are works?

Biological wastewater engineering, a. We put a lot of time and effort into ...

a. We put a lot of time and effort into cultivating our activated sludge microbial community. So why do we waste sludge out of it? b. A wastewater discharges to Puget sound, a mari

Traffic surveys, Traffic Surveys: The following traffic surveys are n...

Traffic Surveys: The following traffic surveys are needed for preparing a good road project: Classified Volume Counts This survey is normally carried out for 7 days,

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd