Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

What is portal cranes, Q. What is Portal Cranes? The Portal crane is a ...

Q. What is Portal Cranes? The Portal crane is a hydraulically driven four wheeled machine and is meant for carrying sleepers or track panels. The power for running and working

Fixed end moments, For fixed beam(say for example fixed with a point load a...

For fixed beam(say for example fixed with a point load at midspan) how did we end up getting P*L/8...??

Method of observation by satellite, Q. Method of observation by satellite? ...

Q. Method of observation by satellite? The difference between a photographs and imageries needs to be understood first. A photograph covers a specific area within its view and

Explain the term - untensioned reinforcement, Explain the term - Untensione...

Explain the term - Untensioned Reinforcement In prestressed concrete construction, use of untensioned reinforcement also has to be made alongwith tendons. This is essential as

Manhole covers finished of cast iron same as ductile iron, Question Why are...

Question Why are manhole covers finished of cast iron as same are through of ductile iron ? Answer Usually, manholes covers are made of cast iron. Though, in viewpoint of pipe

Underwater problems in bridge construction, Q. Underwater problems in bridg...

Q. Underwater problems in bridge construction? The major bridge construction materials are steel and concrete. In the past, stone and brick masonry, with lime mortar as binding

Define Statically indeterminate structures, Statically indeterminate struct...

Statically indeterminate structures a. Fall into two categories: 1.  Beam problems with additional supports/restraints 2.  Axial bar members subjected to temperature/forc

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd