Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Explain rcra and hswa - hazardous waste regulations, Explain RCRA and HSWA ...

Explain RCRA and HSWA - Hazardous Waste Regulations 1. In 1976, Congress passed the Resource Conservation and Recovery Act (RCRA) and directed EPA to establish hazardous waste

Holes in steel plates connecting to H-piles, Q. Holes in steel plates conne...

Q. Holes in steel plates connecting to H-piles There are two types of holes present in the steel plate associated to H-piles in the pile cap. The first type of holes is design

What is preset in bridge bearing, Q. What is Preset in bridge bearing? ...

Q. What is Preset in bridge bearing? 'Preset' is a method to decrease the size of upper plates of sliding bearings in order to save cost. Normal length of an upper bearing plat

Sampling distribution and approximations of distributions, Sampling Distrib...

Sampling Distribution And Approximations Of Distributions: 1) Learnt three approaches for deriving the probability distributions of functions of one or more random variables v

Building classification, Why I is the missing after h and J is written in t...

Why I is the missing after h and J is written in the classification of building

Explain the equation for length of spiral curve, Explain the Equation for L...

Explain the Equation for Length of Spiral Curve Length of Spiral Curve can be calculated using the following equation L s = 3.15V 3 /RC Where: V - Design Speed in MPH

Manufacturing technique of ferro cement, what are the manufacturing techniq...

what are the manufacturing techniques of ferro cement?

Aggregaters, What Aggregate''s class III

What Aggregate''s class III

Explain the corrosion by the action of bacteria, Explain the Corrosion by t...

Explain the Corrosion by the Action of Bacteria? Corrosion can also be accelerated by the action of bacteria.  In the absence of oxygen, sulphate-reducing bacteria can grow, an

Retaioning walls, what are the uses of retaining wall?!

what are the uses of retaining wall?!

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd