Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Widening on curves, Widening on Curves: Pavements have to be widened ...

Widening on Curves: Pavements have to be widened on curves because of the fact that : (a) the vehicle has a wheel base and overhang on the front and rear, and the vehicle

Retaioning walls, what are the uses of retaining wall?!

what are the uses of retaining wall?!

State about the pre-tensioned concrete, State about the pre-tensioned concr...

State about the pre-tensioned concrete In pre-tensioned concrete, the tendon stresses are transferred  to concrete by  virtue of bond  of concrete to the  surface of steel tend

Strength of rivet joints, Ask question #Minimum 100 Please help me to...

Ask question #Minimum 100 Please help me to write a c program to determine strength and efficiency of single cover butt joint, lap joint, double cover butt joint . words ac

Define the equations for a contracted rectangular weir, Define the Equation...

Define the Equations for a Contracted Rectangular Weir If the rectangular weir is a contracted weir and the flow is restricted from passing freely through the weir opening, a r

Explain a critical path - construction management, Explain a Critical Path ...

Explain a Critical Path The series of activities which determines the earliest possible date of project completion Usually defined as those activities with minimal or

Geotechnical engineering, what are the 2 principle factors affecting the al...

what are the 2 principle factors affecting the allowable bearing pressure in the design of a specific footing

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd