Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

#titlecivil war.., how can you know that the civil war real.

how can you know that the civil war real.

Mechanics problem, i am facing some problem in solving the problem of elong...

i am facing some problem in solving the problem of elongation due to self weight suspended from fixed support in the conical bar

Determine the specific gravity of solids, The Atterberg limits of a clay so...

The Atterberg limits of a clay soil are: Liquid limit = 63%, Plastic limit = 40%, and shrinkage limit = 27%. If a sample of this soil has a volume of 10 cm 3 at the liquid limit a

What is a footing foundation for a water tower, A footing foundation for a ...

A footing foundation for a water tower carries a load of 9000 kN and is 3.6 metres square. It rests on dense sand of 9 m thickness overlying a clay layer of 3 metres depth. The cla

Show the settlement due to excavation, Q. Show the Settlement due to Excava...

Q. Show the Settlement due to Excavation? If  an excavation is made in a sandy soil,  the structure founded near the excavation will be affected and it will cause extra settlem

Sand layer underlying paving slab or interlocking blocks, Question What...

Question What is function of a sand layer underlying paving slab or interlocking blocks? Answer Normally after laying of sub-base layer of paving slab or interlocking

Calculate the number of trucks for fleet working, A contractor was awarded ...

A contractor was awarded a Contract to excavate and haul 200,000-yds 3 of silty clay (USCS classification ML) with a bulking factor of 30%.  The contractor's fleet of dump trucks

Plane tabling, difference between compass suveying and chain surveying

difference between compass suveying and chain surveying

Method to calculate the loss of prestress, Method to calculate the loss of ...

Method to calculate the loss of prestress When the consider creep in regard to loss of prestress, we have to see that the prestressed member is under compressive stresses due

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd