Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Plinth wall, is it necessary for to put plinth wall in buildings

is it necessary for to put plinth wall in buildings

Determine the term - final tension, Determine the term - Final Tension ...

Determine the term - Final Tension The tension in tendons after losses of prestress have taken place is called as final tension. Final tension is taken to be corresponding  to

Tests on bricks, Tests on Bricks The following laboratory tests can be...

Tests on Bricks The following laboratory tests can be conducted on the bricks to find their suitability: 1.    Crushing strength 2.    Absorption 3.    Shape and size

Calculate dead, A building cross section is shown below. The building consi...

A building cross section is shown below. The building consists of eight (8) of the shown frames placed at distance of 20 feet oc for a total length of 140 feet. The glulam beams ar

Inspection and testing, Q. Inspection and testing ? The inspection and ...

Q. Inspection and testing ? The inspection and tests on elastomer and the finished bearings are very important aspects of ensuring a satisfactory performance of the bearing. IR

Foundation, why is the foundation failure?

why is the foundation failure?

Surveying, What is the shrinkage factor

What is the shrinkage factor

Building plan, the conventional symbol used in building plan

the conventional symbol used in building plan

Can all utility detectors detect depth of utilities, Question Can all u...

Question Can all utility detectors detect depth of utilities ? Answer In Hong Kong, underground utility detectors are as a rule separated into two categories- electro

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd