Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Define the types of shock transmission unit, Define the Types of shock tran...

Define the Types of shock transmission unit? Presently two types of STUs are available in the overseas market: (a) Silicon putty based from UK and USA. (b) Oil based from

REport, CASTE DISCRIMANIMATION

CASTE DISCRIMANIMATION

Thodolite, Ask queexplain about the essential parts of transisit ordinate o...

Ask queexplain about the essential parts of transisit ordinate or vernier theodolitestion #Minimum 100 words accepted#

Methods of constructing roads in marshy areas, Methods of Constructing Road...

Methods of Constructing Roads in Marshy Areas: The following methods are adopted for constructing roads in marshy areas: (a) Removal of soft soil and replacement with good

Scheme of some smaller piles with same load capacity, Question Which wi...

Question Which will be a better choice, a large diameter piles or a scheme of some smaller piles with same load capacity ? Answer Choice of a large diameter pile suff

Water treatment, The transmission main from the well field to the community...

The transmission main from the well field to the community is 2500 ft, the velocity of flow at peak pumping capacity is 3.5 fps, water temperature is 10oC, and pH is 7.5. If free c

Flow, what is maximum flood level

what is maximum flood level

Mechanism of taking up loads for concrete paving blocks, Mechanism of takin...

Mechanism of taking up loads for concrete paving blocks  Paving for concrete blocks comprises closely packed paving blocks in pre-determined patterns and tiny joint spaces bet

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd