Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Determine about the statement - failure at cracking load, Determine about t...

Determine about the statement - Failure at Cracking Load This brittle mode of failure is likely to occur in those pre-stressed elements that are concentrically pre-stressed wit

Axial flow pumps for large flows and low heads, Q. Axial flow pumps for lar...

Q. Axial flow pumps for large flows and low heads? It is well known that axial flow pumps are the most suitable for providing large flows and low heads. Reason behind this is c

Epoxy-coated bars vs galvanized bars, Bonding performance to concrete: Epox...

Bonding performance to concrete: Epoxy-coated bars vs. galvanized bars  Based on the findings of CEB Bulletin 211 the bonding of galvanized bars to concrete is lower in early

Determine a cylindrical specimen of saturated clay, A cylindrical specimen ...

A cylindrical specimen of saturated clay, 4.5 cm in diameter, and 9 cm long, is tested in an unconfined compression apparatus. Search the cohesion if the specimen fails at an ax

Systems approach to diagnose and solve the chronic w, systems approach to d...

systems approach to diagnose and solve the chronic water crisis in the city.

Calculate the fuel consumed, A 160-HP Diesel engine (peak fuel consumption ...

A 160-HP Diesel engine (peak fuel consumption = 0.04-gal/HP-hr) hydraulic excavator operates on a cycle time of 20 seconds during a 50-min/hr.  During the filling of the bucket cyc

Process of lubrication of girder bearing, Q. Process of Lubrication of Gird...

Q. Process of Lubrication of Girder Bearing? Oiling and greasing of bearings is done to ensure that the bearings are well lubricated and working freely to permit expansion and

Stone, Explain briefly physical classifications of stone

Explain briefly physical classifications of stone

Engineering economics, Ask quA contractor has both a 3-cy and a 5-cy shovel...

Ask quA contractor has both a 3-cy and a 5-cy shovel in the equipment fleet. Select the minimum size shovel that will excavate 450,000 bcy of common earth in a minimum of 120 worki

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd