Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

How to calculate the vertical stress, A rectangular foundation, 2 m × 4 m, ...

A rectangular foundation, 2 m × 4 m, transmits a uniform pressure of 450 kN/m 2 to the underlying soil. Verify the vertical stress at a depth of 1 metre below the foundation at a

State the term - post-tensioned concrete, State the term - Post-tensioned c...

State the term - Post-tensioned concrete In Post-tensioned concrete construction, as shown in Figure,  tendons are placed inside concrete and stretched after concrete has attai

Discuss about the post-tensioning systems, Discuss about the post-tensionin...

Discuss about the post-tensioning systems In most of post-tensioning systems, when the cable is tensioned and the jack is released to transfer prestress to concrete, the fricti

Common defects - bituminous roads, Common defects - bituminous roads: ...

Common defects - bituminous roads: Cracks can be filled with a bitumen emulsion. Wide cracks can be filled with premix sand asphalt. If an overlay is to be laid on a cracke

Soil plug in marine piling system of steel tubular pile, Soil plug in marin...

Soil plug in marine piling system of steel tubular pile with reinforced concrete infill At the time of initial driving process, open-ended steel piles are driven through the s

Lime, LIME It is significant binding material utilized in building con...

LIME It is significant binding material utilized in building construction. Lime has been utilized as the material of construction from ancient time. While it is mixed with san

Stress analysis, • The previous load analysis represents a first and necess...

• The previous load analysis represents a first and necessary step in the analysis of the given structure but it does not tell us whether the given load can be safely supported (i.

Biological wastewater engineering, a. We put a lot of time and effort into ...

a. We put a lot of time and effort into cultivating our activated sludge microbial community. So why do we waste sludge out of it? b. A wastewater discharges to Puget sound, a mari

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd