Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

What are the causes of settlement, Q. What are the causes of settlement? ...

Q. What are the causes of settlement? The various causes of settlement are: 1) increasing load on the surrounding soil deposit, 2) excavation, 3) lowering of water tab

Bridge design, criteria for economical span length in bridge

criteria for economical span length in bridge

Design nominal reinforcement to piles, Question Is it true that there i...

Question Is it true that there is no essential to design nominal reinforcement to piles. Answer In BS8110 and BS5400 Pt.4, they need provision of nominal reinforce

Embankment, Describe the various steps in embankment construction.

Describe the various steps in embankment construction.

Calculate the principal stresses for the state of stress, Calculate the pri...

Calculate the principal stresses for the state of stress: Calculate the principal stresses and principal planes for the state of stress shown in Figure. Figure

Sub-base layer be served as a drainage layer , Question Would a sub-bas...

Question Would a sub-base layer be served as a drainage layer to take away water from pavement? Answer As well providing load distribution in post-construction stage a

How do you measure concrete, We can measure concrete by Cubic feet, Cubic y...

We can measure concrete by Cubic feet, Cubic yards, Cubic Meter

Stop dead restriction, With a clear sketch indicate the system of protectio...

With a clear sketch indicate the system of protection of line for works of short duration where ‘ Stop dead restriction' need to be observed on a single line section on a BG track.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd