Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Earth work in high embankments, Q. Earth work in high embankments? (a) ...

Q. Earth work in high embankments? (a) Borrow pits must not be dug close to telegraph poles, electric poles, level crossings, bridges a culverts, or within 800 meters of the bo

Determine the required area of steel, A rectangular concrete beam is subjec...

A rectangular concrete beam is subjected to a factored moment (Mu) of 345 kip*ft.  The beam has the following properties: f'c = 5500 psi fy = 60,000 psi h = 39 in

Bridge engineering, How to calculate economic span of ss bridge

How to calculate economic span of ss bridge

Shape factor, For a solid circular shaft transmitting torque, the shape fac...

For a solid circular shaft transmitting torque, the shape factor is

Determine the in-situ dry unit weight, Q. The following observations were r...

Q. The following observations were recorded in a Field density determination by sand-replacement method: Volume of Calibrating can = 1000 cm3 Weight of empty can = 10 N We

Specification of flooring for heavy repair shed, Q. Specification of Floori...

Q. Specification of Flooring for heavy repair shed? Scope for use - For flooring for heavy repair shed, Surface hardened concrete flooring can used. In this type of flooring,

Obstacle measurement.., ..describe how u can obtain the length of an inacce...

..describe how u can obtain the length of an inacceble length of a land when a river cross it

Determine the amount of excavated material, The footprint of a proposed off...

The footprint of a proposed office building is overlaid on the existing contours topographic map of a sloping site as shown in the figure. The structural bays which are 65-ft by 65

Designing of pipe jacking, Question While designing of pipe jacking , ...

Question While designing of pipe jacking , what particular areas on pipe joints have to engineers make sure of? Answer While in pipe jacking, jacked pipes may well ha

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd