Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

STRUCTURAL MECHANICS, Define and explain Mohr’s theorem for finding slope a...

Define and explain Mohr’s theorem for finding slope and deflection.

Stabilization of Black Cotton soil, How the stabilization of black cotton ...

How the stabilization of black cotton soil was done in field? what are the methods to do that?

Types of pavements, Types of Pavements: On the basis of structural pe...

Types of Pavements: On the basis of structural performance of pavements, there are basically two types of pavements: (a) Flexible, and (b) Rigid. A flexible pavement

Effect of concrete placing temperature, Effect of concrete placing temperat...

Effect of concrete placing temperature on early thermal movement Rate of hydration of cement paste is related to placing temperature of concrete. Rate of heat production is giv

Grillage foundation, what are the advantages of grillage foundation and why...

what are the advantages of grillage foundation and why people prefers that?

Design the drainage pipes system in reclamation areas, Q. Design the Draina...

Q. Design the Drainage pipes system in reclamation areas? In reclamation areas drainage pipes are generally laid at flatter gradients when compared with upstream stormwater pip

Soil plug in marine piling system of steel tubular pile, Soil plug in marin...

Soil plug in marine piling system of steel tubular pile with reinforced concrete infill At the time of initial driving process, open-ended steel piles are driven through the s

Impact test - tests on stones, Impact Test: Resistance of stones to ...

Impact Test: Resistance of stones to impact is found by conducting tests in impacting testing machine .It contain of a frame with guides in which a metal hammer weighing 13.

Inspection and testing, Q. Inspection and testing ? The inspection and ...

Q. Inspection and testing ? The inspection and tests on elastomer and the finished bearings are very important aspects of ensuring a satisfactory performance of the bearing. IR

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd