Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Physics, A point charge q2 = -2.3 µC is fixed at the origin of a co-ordinat...

A point charge q2 = -2.3 µC is fixed at the origin of a co-ordinate system as shown. Another point charge q1 = 4.0 µC is is initially located at point P, a distance d1 = 6.0 cm fro

Concrete cracking, Attached information shows construction details of a wat...

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped

Surveying, what is meant by geodetic survey

what is meant by geodetic survey

Test for determination of shear modulus, Test for determination of Shear Mo...

Test for determination of Shear Modulus Conditioning load : Bearings shall be preloaded with maximum horizontal load Htest (with Ntest or vertical load held constant) and un

Rubber dams – air-filled vs water-filled, Most of the existing rubber dams ...

Most of the existing rubber dams are of air-filled types. Water-filled rubber dams aren't preferred for the below reasons: (i)  By giving same sheet length and dam height, tensi

Find a suitable slab thickness, The continuous one-way slab shown below is ...

The continuous one-way slab shown below is loaded with a uniform service live load of 80 psf, and a superimposed dead load of 40 psf. Assume the beam width is 16" and use f'c = 5 k

How we can check caisson is stable or not, A box caisson, 10 m high, is 18 ...

A box caisson, 10 m high, is 18 m × 9 m at the base. The weight of the caisson is 9 MN and its centre of gravity is 4.2 m above the base. Check whether the Caisson is stable. If

BESHOOOOO, what are the dimensions of a sheet of paper required for plottin...

what are the dimensions of a sheet of paper required for plotting a traverse ABCDE with 1 : 250 scale if a margin of 4 cm to the right and left sides and a6 cm margin to the other

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd