Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Paints, painting wood work and steel

painting wood work and steel

Design nominal reinforcement for staircase, Question Given a 1meter hig...

Question Given a 1meter high staircase resting on solid concrete, could it be adequate to design nominal reinforcement for staircase? Answer For design of staircase,

Calculate the total cost for the project, The total equipment cost for an a...

The total equipment cost for an addition to a pharmaceutical plant is estimated to be $5,000,000. The percentages provided in the Table represent the average expenditures in other

State the importance of structural element, State the importance of structu...

State the importance of structural element If this structural element is used as a beam element, subjected to self load and other imposed transverse loads, then the bottom fibr

Coagulation, Incoming water contains 2.5 mg/L as a substance of natural alk...

Incoming water contains 2.5 mg/L as a substance of natural alkalinity (HCO3-). The flow rate is 9.5 ML/day). (a) What feed rate is required if the alum dose is 7 mg/L and is avail

Pavement Drainage, What would be the best way to evaluate the field perform...

What would be the best way to evaluate the field performance benefits of subsurface drainage in a flexible pavement? Short term and long term, thick or thin HMA..

Traditional granular sub-base, Question For rigid pavement, what is rec...

Question For rigid pavement, what is recompense of using lean concrete sub-base instead of traditional granular sub-base? Answer There are some shortcomings of using

Dam details, how to prepare a project of final year

how to prepare a project of final year

Mechanical, Define varigions principle of moments and write about system of...

Define varigions principle of moments and write about system of forces?

Show the filter below the revetment, Q. Show the filter below the revetment...

Q. Show the filter below the revetment? A filter placed between the revetment / protection works at the surface and the soil bed below the revetment / protection works. Main fu

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd