Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Differentiate between concrete and tendons, Differentiate between concrete ...

Differentiate between concrete and tendons In the case of pre-tensioned concrete members, the transfer of prestress takes place due to the bond between concrete and tendons. In

Calculate the invert elevation of the sewer pipe, 1. The center line elevat...

1. The center line elevation of the proposed roadway at station is 345+25.50 is 327.36-ft.   The existing ground top of cut elevation (ft) is most nearly: 2. A design engineer c

Concrete structure, which section is most effective for a design of beam an...

which section is most effective for a design of beam and why

Equllibrium, how to know about he sign convention for equllibrium forces

how to know about he sign convention for equllibrium forces

Concrete, what is the heat of hydration and gel space ratio?

what is the heat of hydration and gel space ratio?

Survey, 3-d figure of line ranger

3-d figure of line ranger

Incremental launching mode of bridge construction, In i ncremental launchin...

In i ncremental launching mode of bridge construction, what are ways adopted to increase sufficient resistance of superstructure during launching practice?

Levelling, Permanent adjustment and temporary adjustment

Permanent adjustment and temporary adjustment

What do you mean by ggbs – cement replacement, Q. What do you mean by GGBS ...

Q. What do you mean by GGBS – cement replacement? From structural point of view GGBS replacement enhances higher durability, lower heat of hydration and higher resistance to su

Explain the equalization basins - hydraulic system, Equalization Basins - H...

Equalization Basins - Hydraulic System For influent flow to publicly owned treatment works (POTWs), flow rates may be excessive for short or long durations, especially in combi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd