Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Temperature requirements for bituminous material, Question In all-purpo...

Question In all-purpose Specification for Civil Engineering Works, it details temperature requirements for bituminous material all through and after mixing. What is cause beh

Difference between normal bolts and high friction grip bolts, Question ...

Question What is key difference between normal bolts and high friction grip bolts ? Answer High friction grip bolts are usually used in structural steelwork. They i

Define categories of spalls -underwater inspection of bridge, Define catego...

Define categories of Spalls -underwater inspection of bridge? Spalls are classified as follows:  i. Small spalls - up to 25 mm deep or approximately 150 mm in diameter. i

Break even point, Break even point: EM Electricals, Inc., contains fix...

Break even point: EM Electricals, Inc., contains fixed costs of Rs. 600,000 this period. Variable costs involved labour charges of Rs.100 per unit and material cost of Rs. 200

Find the settlement at the centre and at edge of the footing, A load of 300...

A load of 3000 kN is being taken by a square column footing. Side of the column is 3 m, footing rests on a silty soil with a Poisson's ratio = 0.3. Modulus of elasticity of the soi

Define the frame column analysis, Define the Frame Column Analysis 1. B...

Define the Frame Column Analysis 1. Based on if a column section is a braced frame or unbraced frame. 2. Braced frame-indicates buckling mode shape does not involve tr

Define the abrasion - underwater inspection of bridge, Define the Abrasion ...

Define the Abrasion - underwater inspection of bridge? Abrasion damage is caused by continuous action of external forces on the surface of the concrete element. Erosive action

Explain measured shovel packing, Explain Measured shovel Packing Measu...

Explain Measured shovel Packing Measured shovel Packing essentially consists of accurate measurements of track defects particularly the unevenness and voids caused in the cour

Variations of tendon stresses in pre tensioned concrete, Variations of tend...

Variations of tendon stresses in pre or post-tensioned concrete Variations of tendon stresses in pre or post-tensioned concrete members, along the length of tendons, may be of

Major ways to undertake negative skin friction, Question What are major...

Question What are major ways to undertake negative skin friction ? Answer (i) Utilize slender pile sections since smaller pile area when subject to same working load

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd