Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Determine the equivalent of free float, The free float is equal to: a. L...

The free float is equal to: a. Latest allowable event occurrence time + Early finish time b. Earliest event occurrence time + early finish time c. Latest allowable event o

Soil compaction test, Question In soil compaction test , if test resul...

Question In soil compaction test , if test result exceeds 100%, should engineers accept result? Answer Soil compaction is method of increasing soil density by re

What do you mean by base fixity, Q. What do you mean by Base fixity? B...

Q. What do you mean by Base fixity? Base fixity When structures such as portal frames are associated to the base foundation, engineers have to determine the degree of fix

Survey, who to we calculate the RL at first point.

who to we calculate the RL at first point.

Determine the required stirrup size and spacing requirement, A rectangular ...

A rectangular concrete beam is subjected to a factored design shear force of 200 kips.  For the beam shown below, determine the required stirrup size and spacing requirement. H = 3

Conducting triaxial test, Question In conducting triaxial test to deter...

Question In conducting triaxial test to determine shear strengths for soil samples, what consolidation pressures should be specified? Answer It appears that the sele

State the method of pre- tensioning, State the method of Pre- Tensioning ...

State the method of Pre- Tensioning It is a method of prestressing concrete in which tendons are stretched or tensioned before concreting. In this form of construction, concr

Energy equation, find the pressure head at 2-2 if the rate of flow in pipe ...

find the pressure head at 2-2 if the rate of flow in pipe is 0.36m^3/s

Explain the term - circular prestressing, Explain the term - Circular Prest...

Explain the term - Circular Prestressing This term refers to the case when tendon profile is provided in a round shape, such as in water tanks and pipes, etc.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd