Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Raking piles of bridge abutment placed under an embankment, Question It sho...

Question It should be necessary that raking piles of a bridge abutment be placed under an embankment ? Answer For a bridge abutment to be supported on raking piles with div

Simple bending, In case of simple bending after simply supported beam, deri...

In case of simple bending after simply supported beam, derive that M/I = s /y = E/R.

. determine the permeability of the aquifer, An unconfined aquifer is calle...

An unconfined aquifer is called to be 32 m thick below the water table. A constant discharge of 2 cubic metres per minute is pumped out of the aquifer by a tubewell till the water

Basic, what you mean by civil engineering

what you mean by civil engineering

Contractor to continue concreting works, Question If on-site slump test fai...

Question If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works ? Answer This is an extremely traditional question raised by

Dense Bituminous Macadam, What is DBM?Why use DBM where other binder course...

What is DBM?Why use DBM where other binder courses are available?What is composition and advantages of using DBM?

Differentiate, differentiate between components and resolved parts

differentiate between components and resolved parts

Chemistry, Construction and working of calomel electrode

Construction and working of calomel electrode

Light-weight aggregate prestressed concrete, Light-weight Aggregate Prestre...

Light-weight Aggregate Prestressed Concrete The use of  light-weight aggregate concrete for prestressed concrete construction is well established. The main advantage of  light-

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd