Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Sand layer underlying paving slab or interlocking blocks, Question What...

Question What is function of a sand layer underlying paving slab or interlocking blocks? Answer Normally after laying of sub-base layer of paving slab or interlocking

Calculate the hydrostatic force, The steel oil container shown in the figur...

The steel oil container shown in the figure has a circular lid centred on its sloping wall. The lid is hinged at A and held closed with a frictionless stopper at B. The lid is made

Ground water, Two pumping wells 1,000 m away fully penetrate the same confi...

Two pumping wells 1,000 m away fully penetrate the same confined aquifer. One of the wells pumps at a rate of 1,240 m3/day. The second well pumps at 850 m3/day. If the aquifer has

Determine the flow rate from the dewatering well, A construction project in...

A construction project involves excavation below grade. A 24 inch diameter dewatering well is installed from grade (EL 586) to 80 ft below grade to lower the water table. Soil bori

Explain the contracted rectangular weir, Explain the Contracted Rectangular...

Explain the Contracted Rectangular Weir Weir plate has sides which extend above the maximum water surface, directing the flow through an opening (b = weir length). Typically th

Revit , how to use the revit program

how to use the revit program

Determine the density index of the sand sample, An undisturbed sample of sa...

An undisturbed sample of sand has a dry weight of 18.9 N and a volume of 1143 cm 3 . The solids have a specific gravity of 2.72. Laboratory tests indicate void ratios of 0.40 and 0

By which materials shank of a spur construct, Q. By which Materials Shank o...

Q. By which Materials Shank of a spur construct? Shank of a spur is constructed of sand core and its exposed faces are protected by stone pitching. The attack at nose is very h

Show the silt curtain touching seabed, Q. Show the Silt curtain touching se...

Q. Show the Silt curtain touching seabed? Silt curtains are impermeable vertical barriers extending from seawater surface to their designed depths. Curtains are held in a verti

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd