Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Resting on several raking piles, Question Should dolphins be designed i...

Question Should dolphins be designed in a rigid manner such as resting on several raking piles? Answer While designing dolphins, they are normally supported on a syste

Water retaining structure, Question Why do BS8007 specify permissible c...

Question Why do BS8007 specify permissible crack width of water retaining structure as 0.2mm for severe, extremely severe exposure? Answer For break width less than

Plumbing, what is the different kinds of pipes and fittings

what is the different kinds of pipes and fittings

Mechanics problem, i am facing some problem in solving the problem of elong...

i am facing some problem in solving the problem of elongation due to self weight suspended from fixed support in the conical bar

Physical tests on cement, Physical Tests on Cement (a) Soundness Test: ...

Physical Tests on Cement (a) Soundness Test: by sieve analysis, it is conducted. 100 gms of cement is taken and sieved throughout IS sieve No. 9 for fifteen minutes. Residue on

State the method of pre- tensioning, State the method of Pre- Tensioning ...

State the method of Pre- Tensioning It is a method of prestressing concrete in which tendons are stretched or tensioned before concreting. In this form of construction, concr

Cross Section Method, Cut and Fill Calculation Using Cross Section Method

Cut and Fill Calculation Using Cross Section Method

Deck that you can park a car under, I wish to build a deck that is 4.7m wid...

I wish to build a deck that is 4.7m wide and 7m long alongside my house. I need to park a car under it so there can be no supports in the middle. Attached to the wall on one side a

Cross-sectional elements - geometric design of roads, Cross-sectional Eleme...

Cross-sectional Elements: The terms used in the cross-section of a road are : Carriageway The portion where traffic moves. Shoulder The portion outside the ca

Pavement layers and their functions, Pavement Layers And Their Functions ...

Pavement Layers And Their Functions Flexible Pavement A typical modern flexible pavement for high traffic is composed of layers as under (Figure). Figure: L

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd