Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Diferential equations, show that Y = 4e2x - 2e-3x is a solution of initia...

show that Y = 4e2x - 2e-3x is a solution of initial-value problem (d2y)/(dx2)+ (dy)/(dx) - 6y=0 ; y(0)=6 ; y’(0)=2 . is Y = 2e2x - 4e-3x also a solution of this proble

Soil Mechanics, Good evening. I have two homework projects from the Soil Me...

Good evening. I have two homework projects from the Soil Mechanics. I am interesting if anybody can solve them.

Design storm water drains to match soffit, Question Why is it best to desig...

Question Why is it best to design storm water drains to match soffit? Answer Storm water drains gather storm water in their corresponding catchment areas throughout rainst

Zeroth law of thermodynamics, Two systems which are equal in temperature to...

Two systems which are equal in temperature to a third system are equal in temperature to each other

Telecommunication, Blocked process list is not maintioned in priority order...

Blocked process list is not maintioned in priority order why

State the volume change from the plastic limit, The plastic limit and liqui...

The plastic limit and liquid limit of a soil are 33% and 45% respectively. The percentage volume change from the liquid limit to the dry state is 36% of the dry volume. Likewise, t

How to calculate the combined stresses, Compute the stresses at top and bot...

Compute the stresses at top and bottom fibers in a simply supported pre-stressed concrete beam with a rectangular cross section, 250 mm wide and 450 mm deep, as shown in Figure, at

Local scour at obstructions in rivers, Q. Local Scour at obstructions in ri...

Q. Local Scour at obstructions in rivers? When the water flow in river is deflected by obstructions such as bridge piers, scouring would occur arising from formation of vortexe

Chemistry, Construction and working of calomel electrode

Construction and working of calomel electrode

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd