Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Necessity for road drainage - road drainage, Necessity for Road Drainage: ...

Necessity for Road Drainage: Poor drainage can cause damage to the various components of a road in the following manner: (a) Water can enter the various pavement layers th

Determine the final stresses in the bolt, Determine the final stresses in t...

Determine the final stresses in the bolt: A steel bolt of diameter 12 mm and length 175 mm is used to clamp a brass sleeve of length 150 mm to a rigid base plate as in Figure.

Frames, how to analyse a frame

how to analyse a frame

Determine the loss in post-tensioned members, Determine the Loss in post-te...

Determine the Loss in post-tensioned members This loss occurs only in post-tensioned members. There always exists a certain amount of friction in the jacking and anchoring syst

Chain surveying, describe setting out right angle at given point on a chain...

describe setting out right angle at given point on a chain line and when the point lies outside the chain line

#title Design a gravity-flow sanitary sewer , i have to Design a gravity-f...

i have to Design a gravity-flow sanitary sewer to serve and i need it to be done asap

Storm water drainage - Road drainage and maintenance, Storm Water Drainage:...

Storm Water Drainage: In city streets, the disposal of rain water has to be done through a system of underground storm water drains. The water is collected at the roadside ke

Illustrate concept of filter design, Q. Illustrate Concept of filter design...

Q. Illustrate Concept of filter design? The material used for filter should satisfy the following normal criteria a. Filter material is more pervious than the base material

Foundation, The strap serves the same purpose as the interior portion of a ...

The strap serves the same purpose as the interior portion of a combined footing but is much narrower to save materials. ? The resultant soil pressure is assumed at the centers of b

Orientation of wing walls in designing of bridge abutments, Question Wha...

Question What is consideration in selecting an orientation of wing walls in designing of bridge abutments ? Answer There are three familiar arrangements of wing walls in

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd