Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Regression, I would like to ask what is regression and its function?

I would like to ask what is regression and its function?

Find the size of the foundation required, A steam turbine with base 6 m × 3...

A steam turbine with base 6 m × 3.6 m weighs 10,000 kN. It is to be placed on a clay soil with c = 135 kN/m 2 . Find the size of the foundation needed if the factor of safety is to

Determine stability of the upstream slope of an earth dam, Stability of the...

Stability of the upstream slope of an earth dam Give the step by step procedure for examining the stability of the upstream slope of an earth dam by the Swedish method of slice

Flemish bond, what is the advantages of Flemish bond

what is the advantages of Flemish bond

CONCRETE BATCHING, DOES A GAUGE BOX OF THE SIZE LIKE 50,40,30 MM EXISTS?

DOES A GAUGE BOX OF THE SIZE LIKE 50,40,30 MM EXISTS?

Calculate the flood discharg, Q. A bridge is to be constructed over a strea...

Q. A bridge is to be constructed over a stream having a catchment area = 20 miles 2 partly in plains and partly in hills. Portion in hills has a length of 1.7 miles and fall of 88

Drawing, how to draw an elipse

how to draw an elipse

Example for productivity analysis and improvement, Example for Productivity...

Example for Productivity Analysis and Improvement An excavator with a bucket capacity of 3-yd 3 has a standard production rate of 2,160-yd 3 for an 8-hour day.  The job site

Finding the Point of Contraflexure, Hi, I am struggling with some beam desi...

Hi, I am struggling with some beam design, I need to find the bending moment of a continuous beam. It has 3 supports, each end is pinned and the middle support is off centre and fi

Rb slab, #questionshow me picture..

#questionshow me picture..

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd