Define Lead Lag Relationships

1. A lead is when the successor task begins before the predecessor task is complete

2492_Define Lead Lag Relationships 1.png

2. A lag is when a successor task does not start immediately upon the completion of the predecessor task

1342_Define Lead Lag Relationships 2.png


Related Discussions:- Define lead lag relationships - construction management

Centroid, use of centroid in civil engineering

use of centroid in civil engineering

Hexagon, how to draw a regular hexagon using semicircle method

how to draw a regular hexagon using semicircle method

Mechanics of solid, determine the end slope and deflection in the beam

determine the end slope and deflection in the beam

Light-weight aggregate prestressed concrete, Light-weight Aggregate Prestre...

Light-weight Aggregate Prestressed Concrete The use of  light-weight aggregate concrete for prestressed concrete construction is well established. The main advantage of  light-

Explain the clearance interval - signalized intersections, Explain the Clea...

Explain the Clearance Interval - Signalized Intersections  Also known as "Red Clearance Interval" and "All Red"        r = (w+L) / V - If there is no pedestrian traffic r

Chain surveying, Chain Surveying: In the chain surveying, you have stu...

Chain Surveying: In the chain surveying, you have studied the basics of chain surveying. In chain surveying, various equipment and instruments are used for measuring distances

Potential advantages of segmental tunnelling, Q. Potential advantages of se...

Q. Potential advantages of segmental tunnelling when compared with hand-shield pipe-jacking? In segmental tunnelling, jacks are installed at the shield so that itisn't necessar

BRIDGES, WHAT ARE THE DIFFERENT TYPES OF BRIDGES

WHAT ARE THE DIFFERENT TYPES OF BRIDGES

What should be the hydrometer reading, A litre of suspension containing 0.5...

A litre of suspension containing 0.5 N of soil with a specific gravity of 2.70 is prepared for a hydrometer test. When no temperature correction is considered necessary, what shoul

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd