Investigation scour for underwater inspection of bridge, Civil Engineering

Assignment Help:

Define Investigation Scour for Underwater Inspection of Bridge?

Investigation Scour is probably the most critical item to be aware of when performing an underwater inspection of pier/abutment or protection work of a bridge. The most important assessment of scour is how much of the pier or abutment or protection work is exposed when compared to plans and typical designs. Therefore, inspection for scour should be carried out near pier / abutment's base at bed level on the upstream side and adjacent to it.

Local scour is detectable by divers since this type of scour is characterised by holes near piers/protection works. Divers should routinely check for such scour holes. A typical approach is to take depth measurements around the substructure, both directly adjacent and at concentric intervals. Measurement should be taken at 10 cm increments from upstream to downstream end. Water depth and height of scoured level to normal mud line should be measured and recorded. It should be noted that divers operate in low current situations. Sediments often refill the scour holes during these periods. However, since this refilled sediment is usually soft, a diver using a probing rod can often detect soft areas indicating scour refilling.

 


Related Discussions:- Investigation scour for underwater inspection of bridge

AAA, Ask question #MiAAAAnimum 100 wordAs accepted#

Ask question #MiAAAAnimum 100 wordAs accepted#

Determine the flow rate from the dewatering well, A construction project in...

A construction project involves excavation below grade. A 24 inch diameter dewatering well is installed from grade (EL 586) to 80 ft below grade to lower the water table. Soil bori

Show the process of waterproofing for bridge decks, Q. Show the process of ...

Q. Show the process of Waterproofing for bridge decks? Waterproofing materials such as membranes are applied on top of bridge deck surface since:  (i)  Vehicular traffic (f

General requirement for civil engineering, Question General requirement for...

Question General requirement for Civil Engineering Works in 1992 Edition, Clause 15.09 details that tying wires for strengthening adjacent to and above Class F4 and F5 closes must

Fore bearing and back bearing, write a c program to calculate the included ...

write a c program to calculate the included angles for given fore bearing and back bearing.

Dams, types of dams

types of dams

Advantageous to use concrete of very high power, Question Will it advantag...

Question Will it advantageous to use concrete of very high power for example exceeding 60MPa? What are potential problems connected with high strength concrete ? Answer To in

Compute the negative skin friction of the pile group, A square pile group o...

A square pile group of 9 piles passes by a recently filled up material of 4.5 m depth. The diameter of the pile is 30 cm and pile spacing is 90 cm centre to centre. If the unconfin

Laplace transform, Using Laplace transfom, the following differential equat...

Using Laplace transfom, the following differential equation d y dy dt reduces to the algebraic equation of the form Resolve y(s) into partial fractions

Design an equalization basin with a safety factor, A storm occurs with rain...

A storm occurs with rain of varying intensity falling over a commercial area. The area has a combined sewer system. Two interceptor sewers direct flow to the wastewater treatment p

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd