Q. Define FLARE AND VRU SYSTEM?

VRU, HP and LP Flare systems are used to collect normal and emergency releases from the process and recycle or dispose of them in a safe manner.

The HP Flare system is responsible for collecting and disposing of process streams resulting from manual vents, emergency reliefs or upset conditions from diverse equipment throughout the facility.

Fluid from the flare header enters into the HP Flare Knockout Drum, where liquid and vapour are separated. The vapour flows to the HP Flare Stack where the HC gas is combusted into CO2 and H2O. The liquid from HP Flare KO Drum is sent to the Slop Tanks. Both the HP flare header into the drum and the line from the drum to the stack are sloped downwards towards the drum to prevent condensed liquid from accumulating in the flare header or entering the flare stack.

The VRU system is provided for all recoverable tank vapours and low pressure process vapours. Usually this includes vapours from the closed HC Drain Vessels, Evaporator Package, Surge Tank, Skim Tank, De-Oiled Water Tank, IGF Package, Desand Tank, Slop Tank, Dilbit Tank, Off-Spec Tank, Diluent Tank and Slop Treater Package (if any). The VRU Package increases the pressure of recovered vapours in order to mix them with the other vapours feeding the Mixed Fuel Gas Separator. (The description may be different in various SAGD plants). The VRU package may contain a VRU Suction Cooler, Scrubber, Scrubber Pumps, VRU Compressors, Compressor Cooler and Discharge Separator.

The vapour from VRU header flows to the cooler to cool down the vapour and collecting condensed liquids prior to compression. The liquid is pumped out to Slop Tank and vapour is sent to the compressor. The discharge gas flows to the Discharge Cooler and Separator (three phase) and the overhead gas is routed to the FG system and HC liquids are sent to Slop Tank.

The LP Flare Header collects gas from process sources that cannot withstand backpressure in excess of 3.45 kPag. Normally these vapours are recovered by the VRU but should the VRU System shut down or lack sufficient capacity for any reason, excess vapours are collected in the LP Flare header and sent to the LP KO Drum, where liquid and vapour are separated. Vapours flows to LP Flare Stack and liquids are removed from the LP KO Drum and sent to the Surge Tank or Slop Tank.


Related Discussions:- Define flare and vru system

Tensile strength, Tensile strength: What will be its ultimate tensile ...

Tensile strength: What will be its ultimate tensile strength? Solution The condition for necking is = n = 0.3077 Hence using this value of , the true stress at ne

Shielding gas-argon-advantages of argon, Argon Argon is approximatel...

Argon Argon is approximately one and one third times as heavy as air and ten times heavier than helium. Argon, after leaving the torch nozzle, forms a blanket over the weld

Determine the chemical formulate for refrigerant, (a) Draw P-H and T-S diag...

(a) Draw P-H and T-S diagrams for following cases : (3) (i) Cycle with superheated vapour before compression. (ii) Cycle with sub-cooling or under-cooling of refrigerant.

Thermodynamic 1st law, What is the diff between system underfoing cycle and...

What is the diff between system underfoing cycle and system undergoing process

What are the advantages and disadvantages of induction motor, What are the ...

What are the advantages and disadvantages of induction motors? A coil of 500 turns is linked by a ?ux of 0.4 mWb. If the ?ux is reversed in 0.01 second, ?nd the e.m.f induced i

Mechanisms of machines, slidder crank chain / reciprocating engine mechanis...

slidder crank chain / reciprocating engine mechanism pics

Gear complaints of engine starting, Gear Complaints Nature of Complaints (...

Gear Complaints Nature of Complaints (a) Gear shifting hard (b) Gear slipping (c) Gear noise

Material Handling, Identify the basic activities involved in the use of int...

Identify the basic activities involved in the use of intermittent operation in handling machines in material handling?

Schedule evaluation, Schedule Evaluation Each continuations of a partia...

Schedule Evaluation Each continuations of a partial schedule that are produced in step 1 are ranked as per to their respective cost function. This cost function might be dissim

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd