Define flare and vru system, Mechanical Engineering

Assignment Help:

Q. Define FLARE AND VRU SYSTEM?

VRU, HP and LP Flare systems are used to collect normal and emergency releases from the process and recycle or dispose of them in a safe manner.

The HP Flare system is responsible for collecting and disposing of process streams resulting from manual vents, emergency reliefs or upset conditions from diverse equipment throughout the facility.

Fluid from the flare header enters into the HP Flare Knockout Drum, where liquid and vapour are separated. The vapour flows to the HP Flare Stack where the HC gas is combusted into CO2 and H2O. The liquid from HP Flare KO Drum is sent to the Slop Tanks. Both the HP flare header into the drum and the line from the drum to the stack are sloped downwards towards the drum to prevent condensed liquid from accumulating in the flare header or entering the flare stack.

The VRU system is provided for all recoverable tank vapours and low pressure process vapours. Usually this includes vapours from the closed HC Drain Vessels, Evaporator Package, Surge Tank, Skim Tank, De-Oiled Water Tank, IGF Package, Desand Tank, Slop Tank, Dilbit Tank, Off-Spec Tank, Diluent Tank and Slop Treater Package (if any). The VRU Package increases the pressure of recovered vapours in order to mix them with the other vapours feeding the Mixed Fuel Gas Separator. (The description may be different in various SAGD plants). The VRU package may contain a VRU Suction Cooler, Scrubber, Scrubber Pumps, VRU Compressors, Compressor Cooler and Discharge Separator.

The vapour from VRU header flows to the cooler to cool down the vapour and collecting condensed liquids prior to compression. The liquid is pumped out to Slop Tank and vapour is sent to the compressor. The discharge gas flows to the Discharge Cooler and Separator (three phase) and the overhead gas is routed to the FG system and HC liquids are sent to Slop Tank.

The LP Flare Header collects gas from process sources that cannot withstand backpressure in excess of 3.45 kPag. Normally these vapours are recovered by the VRU but should the VRU System shut down or lack sufficient capacity for any reason, excess vapours are collected in the LP Flare header and sent to the LP KO Drum, where liquid and vapour are separated. Vapours flows to LP Flare Stack and liquids are removed from the LP KO Drum and sent to the Surge Tank or Slop Tank.


Related Discussions:- Define flare and vru system

Assignment, history of electronics materials

history of electronics materials

Wilson-Hartnell Governor:, A Wilson-Hartnell governor is illustrated in giv...

A Wilson-Hartnell governor is illustrated in given Figure. In this, the balls are associated by two springs that are known as main springs. The main springs are symmetrically arran

Create a pay - off table, Bhasker operates a retail shop and sells the high...

Bhasker operates a retail shop and sells the high priced "Hot Food" thermoware. Each unit I priced at Rs.250. Experience has shown that the weekly demand schedule for items is as f

Find the tension in each wire, A 54 kg chandelier is suspended 1.5 m below ...

A 54 kg chandelier is suspended 1.5 m below a ceiling by 3 wires, each of which has the similar tension and the similar length of 2.0 m (see the drawing). Find the tension in every

What is the mean of off time, Q.What is the mean of Off time? It is the...

Q.What is the mean of Off time? It is the interval from the end of the hold time to the beginning of the squeeze time for the next (resistance) welding cycle. In automatic m

Projection welding, Projection Welding Projection welding is similar to...

Projection Welding Projection welding is similar to spot welding but for the fact that the welding takes place at the projections on the surface of the metals and flat shaped e

Arm programming, In order to get your first experience of ARM programming, ...

In order to get your first experience of ARM programming, this way you are familiar with the problem itself, its design, its flow of execution and you can use your own C code as ps

Determine the minimum required wire diameter, A large tower is to be suppor...

A large tower is to be supported by a series of steel wires; it is estimated that the load on each wire will be 13,300 N (3000 lb f ). Determine the minimum required wire diameter,

What is the chief advantage of CIDR over addressing scheme, What is the chi...

What is the chief advantage of CIDR over the original classful addressing scheme? CIDR stands for Classless Inter-Domain Routing is a new addressing scheme for the Internet, th

Determine the damping ratio and undamped natural frequency, With the assist...

With the assistance of the airplane information and the Dutch roll approximation values shown in Table Q3: Table Q3 (a)  Determine the Dutch roll eigenvalues. (b)  Dete

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd