Define flare and vru system, Mechanical Engineering

Assignment Help:

Q. Define FLARE AND VRU SYSTEM?

VRU, HP and LP Flare systems are used to collect normal and emergency releases from the process and recycle or dispose of them in a safe manner.

The HP Flare system is responsible for collecting and disposing of process streams resulting from manual vents, emergency reliefs or upset conditions from diverse equipment throughout the facility.

Fluid from the flare header enters into the HP Flare Knockout Drum, where liquid and vapour are separated. The vapour flows to the HP Flare Stack where the HC gas is combusted into CO2 and H2O. The liquid from HP Flare KO Drum is sent to the Slop Tanks. Both the HP flare header into the drum and the line from the drum to the stack are sloped downwards towards the drum to prevent condensed liquid from accumulating in the flare header or entering the flare stack.

The VRU system is provided for all recoverable tank vapours and low pressure process vapours. Usually this includes vapours from the closed HC Drain Vessels, Evaporator Package, Surge Tank, Skim Tank, De-Oiled Water Tank, IGF Package, Desand Tank, Slop Tank, Dilbit Tank, Off-Spec Tank, Diluent Tank and Slop Treater Package (if any). The VRU Package increases the pressure of recovered vapours in order to mix them with the other vapours feeding the Mixed Fuel Gas Separator. (The description may be different in various SAGD plants). The VRU package may contain a VRU Suction Cooler, Scrubber, Scrubber Pumps, VRU Compressors, Compressor Cooler and Discharge Separator.

The vapour from VRU header flows to the cooler to cool down the vapour and collecting condensed liquids prior to compression. The liquid is pumped out to Slop Tank and vapour is sent to the compressor. The discharge gas flows to the Discharge Cooler and Separator (three phase) and the overhead gas is routed to the FG system and HC liquids are sent to Slop Tank.

The LP Flare Header collects gas from process sources that cannot withstand backpressure in excess of 3.45 kPag. Normally these vapours are recovered by the VRU but should the VRU System shut down or lack sufficient capacity for any reason, excess vapours are collected in the LP Flare header and sent to the LP KO Drum, where liquid and vapour are separated. Vapours flows to LP Flare Stack and liquids are removed from the LP KO Drum and sent to the Surge Tank or Slop Tank.


Related Discussions:- Define flare and vru system

Stenght of Material, Give the assumption of pure torsion derivation of shea...

Give the assumption of pure torsion derivation of shear stress produced in circular shaft subjected to torsion

Mircometer, How is a micrometer used?

How is a micrometer used?

Corrosion resistance of the austenitic stainless steels, The corrosion resi...

The corrosion resistance of the austenitic stainless steels (within the concentration and temperature conditions described above) relies on the formation and stability of a passive

Explain the conventional frame, Show schematic diagram showing the layout o...

Show schematic diagram showing the layout of transmission system of four-wheel driven car. Explain briefly the following types of frame: (a) Conventional frame (b) Integra

Condition for a heat transfer process to occur, What the necessary conditio...

What the necessary condition for a heat transfer process to occur?

Corrosion assessment for mvc evaporator system, Q. Corrosion Assessment for...

Q. Corrosion Assessment for MVC Evaporator System? Typical evaporator systems in SAGD plants operate under extremely severe corrosive conditions due to high chloride content, e

determine the mass of air, An amount of air contained in a rigid container...

An amount of air contained in a rigid container is at  T1 = 300 K.  After adding 450 kJ of heat, the air temperature increases to  T2 = 430 K.  Determine the mass of air,  m [kg],

Thermodynamics, why constant volume line has more slop tha constant pressur...

why constant volume line has more slop tha constant pressure line in T-S diagram

Material selection for insulation in personnel protection, Q. Material Sele...

Q. Material Selection for Insulation in Personnel Protection? Material for 15ºC to 650ºC temp range is Calcium Silicate (ASTM C533, Type 1), Manville Thermo-12 or approved equi

Principal stress and strain, The end gear is subjected to the loading given...

The end gear is subjected to the loading given in the picture below. If the bearings A & B exerts only Z & Y component of forces on the shaft, Verify the equilibrium torque T at ge

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd