Q. Define FLARE AND VRU SYSTEM?

VRU, HP and LP Flare systems are used to collect normal and emergency releases from the process and recycle or dispose of them in a safe manner.

The HP Flare system is responsible for collecting and disposing of process streams resulting from manual vents, emergency reliefs or upset conditions from diverse equipment throughout the facility.

Fluid from the flare header enters into the HP Flare Knockout Drum, where liquid and vapour are separated. The vapour flows to the HP Flare Stack where the HC gas is combusted into CO2 and H2O. The liquid from HP Flare KO Drum is sent to the Slop Tanks. Both the HP flare header into the drum and the line from the drum to the stack are sloped downwards towards the drum to prevent condensed liquid from accumulating in the flare header or entering the flare stack.

The VRU system is provided for all recoverable tank vapours and low pressure process vapours. Usually this includes vapours from the closed HC Drain Vessels, Evaporator Package, Surge Tank, Skim Tank, De-Oiled Water Tank, IGF Package, Desand Tank, Slop Tank, Dilbit Tank, Off-Spec Tank, Diluent Tank and Slop Treater Package (if any). The VRU Package increases the pressure of recovered vapours in order to mix them with the other vapours feeding the Mixed Fuel Gas Separator. (The description may be different in various SAGD plants). The VRU package may contain a VRU Suction Cooler, Scrubber, Scrubber Pumps, VRU Compressors, Compressor Cooler and Discharge Separator.

The vapour from VRU header flows to the cooler to cool down the vapour and collecting condensed liquids prior to compression. The liquid is pumped out to Slop Tank and vapour is sent to the compressor. The discharge gas flows to the Discharge Cooler and Separator (three phase) and the overhead gas is routed to the FG system and HC liquids are sent to Slop Tank.

The LP Flare Header collects gas from process sources that cannot withstand backpressure in excess of 3.45 kPag. Normally these vapours are recovered by the VRU but should the VRU System shut down or lack sufficient capacity for any reason, excess vapours are collected in the LP Flare header and sent to the LP KO Drum, where liquid and vapour are separated. Vapours flows to LP Flare Stack and liquids are removed from the LP KO Drum and sent to the Surge Tank or Slop Tank.


Related Discussions:- Define flare and vru system

Locomotive boiler4s, explain working and construction of locomotive boilers...

explain working and construction of locomotive boilers

Determine the forces in the members, A truss of 12 m span is loaded as show...

A truss of 12 m span is loaded as shown in figure below. Determine the forces in the members of the truss by method of sections.

Load on beam, Load on beam: A beam AB as shown in the figure give...

Load on beam: A beam AB as shown in the figure given below is hinged at A and supported at B by a vertical cord that passes over two frictionless pulleys C and

Example of simple exponential smoothing, Example of simple exponential smoo...

Example of simple exponential smoothing: A TV manufacturer utilizes simple exponential smoothing with α = 0.1 to forecast demand. For the first week of March, the forecast was

What is conformance testing, What is Conformance Testing Conformance Te...

What is Conformance Testing Conformance Testing : There was no mechanism for testing processors or resolving errors between two processors.

Alternating current -fundamentals of electricity , Alternating Current ( A...

Alternating Current ( AC ) : The electricity whose direction changes at regular interval is known as alternating current. I

Determine the component of force , Determine the component of force: ...

Determine the component of force: The force of 500N is acting at a point subtends an angle of 60° with the horizontal. Determine the component of force along X and Y dire

Problems on structural design of combined footings, Problems on Structural ...

Problems on Structural Design of Combined Footings a. Two columns 50 cm x 50 cm in size support service loads of 1200kN and 800kN.The centre to centre spacing between columns

Manual metal arc-welding, Manual Metal Arc Welding Manual metal arc (MM...

Manual Metal Arc Welding Manual metal arc (MMA) welding, is a type of manual arc welding process that uses a consumable electrode coated with flux to lay the weld. An electric

Determine the minimum required wire diameter, A large tower is to be suppor...

A large tower is to be supported by a series of steel wires; it is estimated that the load on each wire will be 13,300 N (3000 lb f ). Determine the minimum required wire diameter,

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd