Define flare and vru system, Mechanical Engineering

Assignment Help:

Q. Define FLARE AND VRU SYSTEM?

VRU, HP and LP Flare systems are used to collect normal and emergency releases from the process and recycle or dispose of them in a safe manner.

The HP Flare system is responsible for collecting and disposing of process streams resulting from manual vents, emergency reliefs or upset conditions from diverse equipment throughout the facility.

Fluid from the flare header enters into the HP Flare Knockout Drum, where liquid and vapour are separated. The vapour flows to the HP Flare Stack where the HC gas is combusted into CO2 and H2O. The liquid from HP Flare KO Drum is sent to the Slop Tanks. Both the HP flare header into the drum and the line from the drum to the stack are sloped downwards towards the drum to prevent condensed liquid from accumulating in the flare header or entering the flare stack.

The VRU system is provided for all recoverable tank vapours and low pressure process vapours. Usually this includes vapours from the closed HC Drain Vessels, Evaporator Package, Surge Tank, Skim Tank, De-Oiled Water Tank, IGF Package, Desand Tank, Slop Tank, Dilbit Tank, Off-Spec Tank, Diluent Tank and Slop Treater Package (if any). The VRU Package increases the pressure of recovered vapours in order to mix them with the other vapours feeding the Mixed Fuel Gas Separator. (The description may be different in various SAGD plants). The VRU package may contain a VRU Suction Cooler, Scrubber, Scrubber Pumps, VRU Compressors, Compressor Cooler and Discharge Separator.

The vapour from VRU header flows to the cooler to cool down the vapour and collecting condensed liquids prior to compression. The liquid is pumped out to Slop Tank and vapour is sent to the compressor. The discharge gas flows to the Discharge Cooler and Separator (three phase) and the overhead gas is routed to the FG system and HC liquids are sent to Slop Tank.

The LP Flare Header collects gas from process sources that cannot withstand backpressure in excess of 3.45 kPag. Normally these vapours are recovered by the VRU but should the VRU System shut down or lack sufficient capacity for any reason, excess vapours are collected in the LP Flare header and sent to the LP KO Drum, where liquid and vapour are separated. Vapours flows to LP Flare Stack and liquids are removed from the LP KO Drum and sent to the Surge Tank or Slop Tank.


Related Discussions:- Define flare and vru system

Clutch free play adjustment of motorcycle, Clutch Free Play Adjustment : A...

Clutch Free Play Adjustment : A smooth operation of clutch ensures the smooth running of motorcycle; hence it is essential to maintain a proper clutch free play. STEPS

Pressure, relation between fluid pressure and velocity

relation between fluid pressure and velocity

Physics, Explain the super position of waves with neat diagrams

Explain the super position of waves with neat diagrams

Cases of equilibrium , Cases of equilibrium: What are cases of equili...

Cases of equilibrium: What are cases of equilibrium? Sol.: As a result of the acting forces, the body may be having one of the following states: (1) The body can mo

What is heat treatment and why is it done, What is heat treatment and why i...

What is heat treatment and why is it done? Heat treatment can be described as a combination of operations or processes in which cooling and heating of an alloy or metal is done

Analyze motion of the two bodies connected by string, Analyze motion of the...

Analyze motion of the two bodies connected by string: Analyze motion of the two bodies connected by string one of which is hanging free and other lying on smooth inclined pla

Orthographic projections, Orthographic Projections: As you learned pre...

Orthographic Projections: As you learned previously about the theory of projection of points, planes and lines, the next significant is the projection of solids that have thre

Effect of parameters in flash butt welding, Effect of parameters in flash b...

Effect of parameters in flash butt welding Flashing Feed Rate : If excessive, there is a probability of the parts freezing together without welding. If this is insuffic

General construction procedure of foundation, General Construction Procedur...

General Construction Procedure Well foundations may be constructed in slipways on barges, or on sand islands. The ones constructed in slipways are launched and towed to their

Reassembly position of critical parts services tips, Reassembly Position of...

Reassembly Position of Critical Parts:  Care should be taken to note the position of the unidirectional parts while dismantling the engine. This will ensure dimensions (depth, dis

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd