Define flare and vru system, Mechanical Engineering

Assignment Help:

Q. Define FLARE AND VRU SYSTEM?

VRU, HP and LP Flare systems are used to collect normal and emergency releases from the process and recycle or dispose of them in a safe manner.

The HP Flare system is responsible for collecting and disposing of process streams resulting from manual vents, emergency reliefs or upset conditions from diverse equipment throughout the facility.

Fluid from the flare header enters into the HP Flare Knockout Drum, where liquid and vapour are separated. The vapour flows to the HP Flare Stack where the HC gas is combusted into CO2 and H2O. The liquid from HP Flare KO Drum is sent to the Slop Tanks. Both the HP flare header into the drum and the line from the drum to the stack are sloped downwards towards the drum to prevent condensed liquid from accumulating in the flare header or entering the flare stack.

The VRU system is provided for all recoverable tank vapours and low pressure process vapours. Usually this includes vapours from the closed HC Drain Vessels, Evaporator Package, Surge Tank, Skim Tank, De-Oiled Water Tank, IGF Package, Desand Tank, Slop Tank, Dilbit Tank, Off-Spec Tank, Diluent Tank and Slop Treater Package (if any). The VRU Package increases the pressure of recovered vapours in order to mix them with the other vapours feeding the Mixed Fuel Gas Separator. (The description may be different in various SAGD plants). The VRU package may contain a VRU Suction Cooler, Scrubber, Scrubber Pumps, VRU Compressors, Compressor Cooler and Discharge Separator.

The vapour from VRU header flows to the cooler to cool down the vapour and collecting condensed liquids prior to compression. The liquid is pumped out to Slop Tank and vapour is sent to the compressor. The discharge gas flows to the Discharge Cooler and Separator (three phase) and the overhead gas is routed to the FG system and HC liquids are sent to Slop Tank.

The LP Flare Header collects gas from process sources that cannot withstand backpressure in excess of 3.45 kPag. Normally these vapours are recovered by the VRU but should the VRU System shut down or lack sufficient capacity for any reason, excess vapours are collected in the LP Flare header and sent to the LP KO Drum, where liquid and vapour are separated. Vapours flows to LP Flare Stack and liquids are removed from the LP KO Drum and sent to the Surge Tank or Slop Tank.


Related Discussions:- Define flare and vru system

Thermal Systems Analysis and Design, Create Visual Basic function ffactor(R...

Create Visual Basic function ffactor(Re, rr) that calculates the Darcy-Weisbach friction factor in a pipe or duct, where Re is the Reynolds No. and rr is the relative roughness, us

Calculate the angle of heel, a) Derive a mathematical expression for stabil...

a) Derive a mathematical expression for stability of an automobile while accelarating in a curved path? b) A motorcycle and its rider together have a mass of 250Kg and their cen

Gathering lines, Gathering Lines: A gathering line, also called a lad...

Gathering Lines: A gathering line, also called a ladder track, is one into which a number of parallel tracks merge. This is shown in Figure. It is used in marshalling yards.

Evaluate the stress in the bolt, (a) A steel bolt 650 mm 2 cross-sectional...

(a) A steel bolt 650 mm 2 cross-sectional area passes centrally through a copper tube to 1200mm 2 cross-sectional area. The tube is 500mm long and closed by rigid washers, which

Calculate the period of vibration, (a) Show energy method and Rayleigh's me...

(a) Show energy method and Rayleigh's method for single degree of freedom system. Also discuss its application. (b) A sphere of diameter D floats half submerged in water. If the

Introduction to welding processes, 1.0     INTRODUCTION Welding is a mat...

1.0     INTRODUCTION Welding is a material joining process used in making welds and a weld is a localised coalescence of metals or non metals produced either by heating the mate

Cold service insulation on pipe, Q. Cold service insulation on pipe? Fa...

Q. Cold service insulation on pipe? Factory fabricated sectional pipe insulation shall be applied in staggered joint construction. On multiple layer construction, all joints sh

Electrical technology, Hi there could I please get a quote for the attached...

Hi there could I please get a quote for the attached Electrical assignment please. Particular attention needs to be taken in terms of the instructions

Determine sliding velocity, a) A pair of 20 degree full depth involute spur...

a) A pair of 20 degree full depth involute spur gears having 30 and 50 teeth respectively of module 4mm are in mesh. The smaller gear rotates at 1000 rpm. Determine- 1) Contact

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd