VRU, HP and LP Flare systems are used to collect normal and emergency releases from the process and recycle or dispose of them in a safe manner.

The HP Flare system is responsible for collecting and disposing of process streams resulting from manual vents, emergency reliefs or upset conditions from diverse equipment throughout the facility.

Fluid from the flare header enters into the HP Flare Knockout Drum, where liquid and vapour are separated. The vapour flows to the HP Flare Stack where the HC gas is combusted into CO2 and H2O. The liquid from HP Flare KO Drum is sent to the Slop Tanks. Both the HP flare header into the drum and the line from the drum to the stack are sloped downwards towards the drum to prevent condensed liquid from accumulating in the flare header or entering the flare stack.

The VRU system is provided for all recoverable tank vapours and low pressure process vapours. Usually this includes vapours from the closed HC Drain Vessels, Evaporator Package, Surge Tank, Skim Tank, De-Oiled Water Tank, IGF Package, Desand Tank, Slop Tank, Dilbit Tank, Off-Spec Tank, Diluent Tank and Slop Treater Package (if any). The VRU Package increases the pressure of recovered vapours in order to mix them with the other vapours feeding the Mixed Fuel Gas Separator. (The description may be different in various SAGD plants). The VRU package may contain a VRU Suction Cooler, Scrubber, Scrubber Pumps, VRU Compressors, Compressor Cooler and Discharge Separator.

The vapour from VRU header flows to the cooler to cool down the vapour and collecting condensed liquids prior to compression. The liquid is pumped out to Slop Tank and vapour is sent to the compressor. The discharge gas flows to the Discharge Cooler and Separator (three phase) and the overhead gas is routed to the FG system and HC liquids are sent to Slop Tank.

The LP Flare Header collects gas from process sources that cannot withstand backpressure in excess of 3.45 kPag. Normally these vapours are recovered by the VRU but should the VRU System shut down or lack sufficient capacity for any reason, excess vapours are collected in the LP Flare header and sent to the LP KO Drum, where liquid and vapour are separated. Vapours flows to LP Flare Stack and liquids are removed from the LP KO Drum and sent to the Surge Tank or Slop Tank.


Related Discussions:- Define flare and vru system

Mechanical properties of materials, A tensile test on a specimen having an ...

A tensile test on a specimen having an initial diameter of 13.11 mm and an initial gauge length of 200.0 mm, gave the following data:

Bending stress, What is bending stress? The bending moment at section t...

What is bending stress? The bending moment at section tends to bend or deflect beam and internal stresses resist its bending. The process of bending stops when the cross sectio

Tolerances, difference between geometric and amnufacturing tolerances

difference between geometric and amnufacturing tolerances

Illustrate the universal support of data types, Universal Support of Data T...

Universal Support of Data Types To address inherent functional incompatibilities, we take the exact opposite route to the 'least common denominator' approach of previous soluti

What do you understand by interference, (a) Derive a mathematical expressio...

(a) Derive a mathematical expression for Maximum length of path of Contact, Maximum Length of Arc of Contact and Contact Ratio in case of Interference. (b) What do you understan

Resistance welding processes, RESISTANCE WELDING PROCESSES The followin...

RESISTANCE WELDING PROCESSES The following five are the main types of resistance welding: 1. Spot welding 2. Seam welding 3. Projection welding 4. Upset butt we

Vitrification-manufacturing methods of ceramics, Vitrification This is...

Vitrification This is liquid phase sintering. It is achieved via incorporating a component that melts to viscous liquid during sintering. Such viscous liquid solidifies in gla

Test the strength of binders, Strength tests : These tests are carried out ...

Strength tests : These tests are carried out to check the holding powers of various binders used in green moulding sand, dry moulding sand and core sand. These tests are performed

Magnitude, Magnitude, direction and position of resultant force: Q : ...

Magnitude, direction and position of resultant force: Q : A horizontal line PQRS is 12 m long, and PQ = QR = RS = 4m. Forces of 1000, 1500, 1000 and 500 N act at P ,

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd