Define factor that is not concerned with schedule control, Civil Engineering

Assignment Help:

Schedule control is concerned with all of the following except:

a. Influencing the factors which create schedule changes

b. Determining that the schedule has changed

c. Resource requirement updates

d. Managing changes when and as they occur.

Solution: C - Resource planning to meet new or additional requirements is a cost management process.


Related Discussions:- Define factor that is not concerned with schedule control

Beam to column connection, what are the characteristics of the beam to colu...

what are the characteristics of the beam to column connection?

Defect of timber, due to defectiveseasoning and conversion

due to defectiveseasoning and conversion

Demonstrate the economical design of concrete, Demonstrate the economical d...

Demonstrate the economical design of concrete A safe, serviceable and economical design of concrete structures requires a comprehensive knowledge of the loads expected to be a

High and narrow beams, Question Give a reason that why are high and na...

Question Give a reason that why are high and narrow beams not desirable in concrete piers? Answer Supported on past experience in other, high and narrow beams after

Brigdes, infomation about differnt brigdes

infomation about differnt brigdes

Precast concrete jacking pipes, Question While precast concrete jackin...

Question While precast concrete jacking pipes , from time to time grout holes are calculated inside these precast pipes. Give specific and key reasons? Answer Grout h

State the effect of shape on the bearing capacity, State the effect of shap...

State the effect of shape on the bearing capacity. Differentiate among safe bearing capacity and allowable soil pressure. Write critical notes on (i) foundations on black cot

survey, what is fore bearing and back bearin

what is fore bearing and back bearing

Define lead lag relationships - construction management, Define Lead Lag Re...

Define Lead Lag Relationships 1. A lead is when the successor task begins before the predecessor task is complete 2. A lag is when a successor task does not

Assignment, How to do assignment on the basis of azetropic mixture

How to do assignment on the basis of azetropic mixture

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd