Define factor that is not concerned with schedule control, Civil Engineering

Assignment Help:

Schedule control is concerned with all of the following except:

a. Influencing the factors which create schedule changes

b. Determining that the schedule has changed

c. Resource requirement updates

d. Managing changes when and as they occur.

Solution: C - Resource planning to meet new or additional requirements is a cost management process.


Related Discussions:- Define factor that is not concerned with schedule control

What is the station at point b, What is the station at Point B? SO...

What is the station at Point B? SOLUTION 3 Station at Point A = Sta 22+45  Station at Point B = (Sta 22+45) + 1028' = 2245'+1028' =3273'  = Sta 32+73

Elongation, Elongation of bar due to self weight

Elongation of bar due to self weight

Major drawbacks of using inverted siphons, Question What is key application...

Question What is key application of inverted siphons? What are major drawbacks of using inverted siphons ? Answer Inverted siphons are planned at locations in which sewer s

#transportation engineering sessional.., #how the result of DETERMINATION O...

#how the result of DETERMINATION OF THE 10 PERCENT FINES value can be interprited?

Retaioning walls, what are the uses of retaining wall?!

what are the uses of retaining wall?!

Surveying, how prepared for surveying?

how prepared for surveying?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd