Define factor that is not concerned with schedule control, Civil Engineering

Assignment Help:

Schedule control is concerned with all of the following except:

a. Influencing the factors which create schedule changes

b. Determining that the schedule has changed

c. Resource requirement updates

d. Managing changes when and as they occur.

Solution: C - Resource planning to meet new or additional requirements is a cost management process.


Related Discussions:- Define factor that is not concerned with schedule control

Reinforcement of concrete in contact with internal vibrators, Reinforcement...

Reinforcement of concrete in contact with internal vibrators  At the time of concreting, if internal vibrators are placed accidentally in contact with some of the reinforcemen

Various operations involved in maintenance by beater packing, Q. Explain in...

Q. Explain in details the various operations involved in Through Packing - conventional Maintenance by beater packing. Explain the various operations as per the Permanent Way

Explain about best hydraulic section, Q. Explain about Best hydraulic secti...

Q. Explain about Best hydraulic section? The best hydraulic section of an open channel is considered by provision of maximum discharge with a given cross sectional area. Chann

Define the pre-tensioned concrete construction, Define the pre-tensioned co...

Define the pre-tensioned concrete construction We understand that in the pre-tensioned concrete construction, stretched tendons are provided in the concrete moulds at the time

Water bound macadam, Water Bound Macadam: Water Bound Macadam (WBM) i...

Water Bound Macadam: Water Bound Macadam (WBM) is a dense and compact course of a road pavement composed of stone aggregates held together by a film consisting of gravel or s

Point of virtual fixity of lateral loading for piles, Point of virtual fixi...

Point of virtual fixity and critical length of lateral loading for piles Some engineers can get confused about the difference between the two terms which are point of virtual

Define the arrow diagramming method, Define the Arrow Diagramming Method ...

Define the Arrow Diagramming Method Activity-on-Arrow (Branch) with nodes as dependencies Uses finish-to-start precedence only. The solution method for an activity on

Advantages of using top-down approach, Question What are major advantag...

Question What are major advantages of using top-down approach in basement construction? Answer The main advantages of top-down approach are listed below- (i) Stru

Explain about differential settlement, Q. Explain about Differential settle...

Q. Explain about Differential settlement? Structural stability is not very much affected by uniform settlement of a structural system. Major amount of damages will be taking pl

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd