Define factor that is not concerned with schedule control, Civil Engineering

Assignment Help:

Schedule control is concerned with all of the following except:

a. Influencing the factors which create schedule changes

b. Determining that the schedule has changed

c. Resource requirement updates

d. Managing changes when and as they occur.

Solution: C - Resource planning to meet new or additional requirements is a cost management process.


Related Discussions:- Define factor that is not concerned with schedule control

Physical tests on cement, Physical Tests on Cement (a) Soundness Test: ...

Physical Tests on Cement (a) Soundness Test: by sieve analysis, it is conducted. 100 gms of cement is taken and sieved throughout IS sieve No. 9 for fifteen minutes. Residue on

Surveying, how to defined work from whole to the part

how to defined work from whole to the part

Kerb overflow weirs – horizontal bars vs. vertical bars, Q. Kerb overflow w...

Q. Kerb overflow weirs – horizontal bars vs. vertical bars? Overflow weirs must be provided for steep roads (longitudinal gradient>5%), flat roads (longitudinal gradient Ess

Explain the frequency of inspection - underwater inspection, Explain the Fr...

Explain the Frequency of Inspection - Underwater Inspection? Underwater inspections must be done on every bridge identified for such inspection as per the Indian Railways Bridg

Steping footing, What are the types of foundation. With figure

What are the types of foundation. With figure

Plane table sureying, discuss the resection method of plane table sureying ...

discuss the resection method of plane table sureying in detail

Distomat., write a note on distomat

write a note on distomat

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd