Schedule control is concerned with all of the following except:
a. Influencing the factors which create schedule changes
b. Determining that the schedule has changed
c. Resource requirement updates
d. Managing changes when and as they occur.
Solution: C - Resource planning to meet new or additional requirements is a cost management process.
Construction black cotton soil
proof
What are the assumptions made in the theory of pure bending
What is DBM?Why use DBM where other binder courses are available?What is composition and advantages of using DBM?
Determine the Depth of Exploration The depth of exploration depends on the following factors: i) Size, type of the structure and loading intensity. ii) Design considerati
A credit card advertises a nominal rate of 18% compounded monthly. If no monthly payments are made, the effective annual interest rate is most nearly: The actual rate is, (18%
Q. Discontinuity of joint – position of bearing? Expansion joints in a bridge structures cater for movements inlongitudinal, transverse, vertical and rotational forms. Layout a
Q. Explain Flash Butt welding? In this process the ends of two rails are kept at fixed distance apart and a mould (designed to suit the rail section ) is fitted on. The rail en
Explain equation for Change Interval y = t + v / 2a + 64.4G Where: y = length of yellow interval (sec) t = driver perception/reaction time (1.0 sec generally used)
fly levelling
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd