Schedule control is concerned with all of the following except:
a. Influencing the factors which create schedule changes
b. Determining that the schedule has changed
c. Resource requirement updates
d. Managing changes when and as they occur.
Solution: C - Resource planning to meet new or additional requirements is a cost management process.
individual wall methods benefits?
how to analyse a frame
With a clear sketch indicate the system of protection of line for works of short duration where ‘ Stop dead restriction' need to be observed on a single line section on a BG track.
Question In all-purpose Specification for Civil Engineering Works, it details temperature requirements for bituminous material all through and after mixing. What is cause beh
symbols of electrical layout
how many types of drainage galleries and foundation treatment
Q. Define Shear slump and collapse slump in slump test? There are three kinds of slump which can take place in a slumps test, namely, true slump, shear slump and collapse slump
flow chart for wet process
Q. Explain Types Of Tiles? Different types of tiles available in the market for floor and walls & dado are as under - 1. Glazed tiles , 2. Ceramic tiles , 3. Granit
Q. What is Function of mortar in brick walls? A distinctive brick wall structure generally comprises the subsequent components: (i) Coping on top of the brick wall to prot
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd