Define factor that is not concerned with schedule control, Civil Engineering

Assignment Help:

Schedule control is concerned with all of the following except:

a. Influencing the factors which create schedule changes

b. Determining that the schedule has changed

c. Resource requirement updates

d. Managing changes when and as they occur.

Solution: C - Resource planning to meet new or additional requirements is a cost management process.


Related Discussions:- Define factor that is not concerned with schedule control

Softening point of bitumen, Hi, i need discussion for softening point of bi...

Hi, i need discussion for softening point of bitumen 7.5 ?C

NERNST EQUATION, HOW CAN I MAKE ASSIGNMENT ON THIS TOPIC

HOW CAN I MAKE ASSIGNMENT ON THIS TOPIC

Estimate the activity durations - construction management, Estimate the Act...

Estimate the Activity Durations The total labor cost for emergency bridge rehabilitation on an interstate highway is $5,716,440.  The average crew-hour cost is $15,879 for this

Highway economics, What is highway economics and what are its main contents...

What is highway economics and what are its main contents to study ?

Reason in checking the ratio, Reason in checking the ratio (i.e. design flo...

Reason in checking the ratio (i.e. design flow to full-bore flow > 0.5) in circular pipe design For checking of self-cleansing velocity for pipes, there is another criterion t

Shear force, what is shear failure and shear force please explian?

what is shear failure and shear force please explian?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd