Schedule control is concerned with all of the following except:

a. Influencing the factors which create schedule changes

b. Determining that the schedule has changed

c. Resource requirement updates

d. Managing changes when and as they occur.

Solution: C - Resource planning to meet new or additional requirements is a cost management process.


Related Discussions:- Define factor that is not concerned with schedule control

Calculate the most probable value, The most probable value of the following...

The most probable value of the following observations on the same angle (35º 17' 42" ; 35º 17' 38" ; 35º 18' 00" ; 35º 17'; 22"; 35º 17' 42");  is most nearly:   35º 17' 40.8

Tests on limestones, Tests on Limestones Practical tests are made on li...

Tests on Limestones Practical tests are made on lime stones to decide their suitability is following:     i.       Physical tests    ii.        Heat test    iii.

Fracking, cons and pros of fracking

cons and pros of fracking

Analysis of prestress and bending stresses, Normal 0 false fa...

Normal 0 false false false EN-IN X-NONE X-NONE

Define advantages and disadvantage black & white fathometer, Define Advanta...

Define Advantages and disadvantages Black & White Fathometer? Advantages of the black & white Fathometer are: - Inexpensive - Effective Disadvantages include the follo

Concrete, what is the heat of hydration and gel space ratio?

what is the heat of hydration and gel space ratio?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd