Schedule control is concerned with all of the following except:

a. Influencing the factors which create schedule changes

b. Determining that the schedule has changed

c. Resource requirement updates

d. Managing changes when and as they occur.

Solution: C - Resource planning to meet new or additional requirements is a cost management process.


Related Discussions:- Define factor that is not concerned with schedule control

P.h.e, procedure for designing of sewage scheme

procedure for designing of sewage scheme

Foundation, Explain briefly shallow foundation?

Explain briefly shallow foundation?

Irrigation, what is a balancing depth

what is a balancing depth

Ild and rolling load, how to solve ild and rolling load problem for shear f...

how to solve ild and rolling load problem for shear force and bending moment with the diagram.

Determine the plastic limit of the soil, The liquid limit of a clay soil is...

The liquid limit of a clay soil is 56% and its plasticity index is 15%.  (a) Name the state of consistency is this material at a water content of 45% ? (b) Determine the plas

Problems in turbid water - underwater inspection of bridge, Define Problems...

Define Problems in turbid water - underwater inspection of bridge? There are three main problems, which limit the viewing performance of an underwater camera. These are: -

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd