Define factor that is not concerned with schedule control, Civil Engineering

Assignment Help:

Schedule control is concerned with all of the following except:

a. Influencing the factors which create schedule changes

b. Determining that the schedule has changed

c. Resource requirement updates

d. Managing changes when and as they occur.

Solution: C - Resource planning to meet new or additional requirements is a cost management process.


Related Discussions:- Define factor that is not concerned with schedule control

Regression, I would like to ask what is regression and its function?

I would like to ask what is regression and its function?

Foundation recommendation, what are the necessary data required for foundat...

what are the necessary data required for foundation recommendation other than SPT value ? why can''t we go for SPT value alone?

What do you mean by internal fiction, Q. What do you mean by Internal ficti...

Q. What do you mean by Internal fiction? Absorptive materials have some elastic fibrous or porous structures that would be extended and compressed at the time of sound wave pro

Classification of timber based on mode of growth, Classification Based on M...

Classification Based on Mode of Growth: On the basis of mode of growth trees are classified as (a) Exogeneous and (b) Endogeneous (a) Exogeneous Trees: These trees grow outwa

Dam, tupes of dam

tupes of dam

Horizontal curves - geometric design of roads, Horizontal Curves: Whe...

Horizontal Curves: When a vehicle of mass m moves on a curve of radius R with a speed of v (m/sec) (as shown in Figure 1) it is subjected to a centrifugal force equal to:

Explain the term- shrinkage of concrete, LOSS OF PRESTRESS DUE TO SHRINKAG...

LOSS OF PRESTRESS DUE TO SHRINKAGE OF CONCRETE We know that concrete shrinks in volume when it dries up. This volume reduction takes place in the form of reduction of all dime

Asdasd, #questiasdasdasdasdon..

#questiasdasdasdasdon..

What is meaning of maintenance period, Question If contractor is likely...

Question If contractor is likely for defective works for 12 years with pact under seal, then what is meaning of Maintenance Period? Answer Faulty works constitute a br

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd