Define decision base on an expected monetary value criterion, Operation Management

Assignment Help:

Page Engineering designs and constructs air conditioning and heating (HVAC) systems for hospitals and clinics. Currently the company's staff is overloaded with design work. There is a major design project due in 8 weeks. The penalty for completing the design late is $14,000 per week, since any delay will cause the facility to open later than anticipated, and cost the client significant revenue. If the company uses its inside engineers to complete the design, it will have to pay them overtime for all work. Page has estimated that it will cost $12,000 per week (wages and overhead), including late weeks, to have company engineers complete the design. Page is also considering having an outside engineering firm do the design. A bid of $92,000 has been received for the completed design. Yet another option for completing the design is to conduct a joint design by having a third engineering company complete all electromechanical components of the design at a cost of $56,600. Page would then complete the rest of the design and control systems at an estimated cost of $30,000.

Page has estimated the following probabilities of completing the project within various time frames when using each of the three options. Those estimates are shown in the following table:

Probability of Completing the Design

Option On-Time 1 wk. late 2 wks. Late 3 wks. Late

Internal Eng. 0.4 0.5 0.1 -------

External Eng. 0.2 0.4 0.3 0.1

Joint Design 0.1 0.3 0.4 0.2

What is the best decision based on an expected monetary value criterion?


Related Discussions:- Define decision base on an expected monetary value criterion

How performing the necessary paperwork, Annual demand for number 2 pencils ...

Annual demand for number 2 pencils at the campus store is normally distributed with mean 1,000 and standard deviation 250. The store purchases the pencils for 6 cents each and sell

Stepping stone method, Stepping Stone Method: Continue the above ex...

Stepping Stone Method: Continue the above example containing the initial basic feasible solution obtained by least cost rule. In this there six empty cell :91,1) )1

Explain what is the present value of the following annuities, What is the p...

What is the present value of the following annuities? a. $2,500 a year for 10 years discounted back to the present at 7% b. $70 a year for 3 years discounted back to the pres

Describe making better business decision, Making Better Business Decision: ...

Making Better Business Decision: Do you provide the quizzes/exams questions for this book? **You didn't answer my questions a Yes or No would have been sufficient. Please answer th

Describe customer service level for an inventory system, Discuss customer s...

Discuss customer service level for an inventory system within the context of quality management

Plant layout, A plant layout should be designed in such a manner that ...

A plant layout should be designed in such a manner that it will provide safety and security of employees at all costs. Optimum plant layout calls for high operating e

Explain how much water can be transported per hour, The network in figure b...

The network in figure below shows the pipeline transportation system for treated water from the treatment plant to a city water supply system. The arc capacities represent millions

Explain crossover point among the existing process, The local convenience s...

The local convenience store makes personal pan pizzas. Currently, their process makes complete pizzas, fully cooked, for the customer. This process has a fixed cost of $20,000, and

Explain network design is a key business decision, Network design is a key ...

Network design is a key business decision as well as a technological decision. Why? Provide an example of a company you believe has a good network design, providing supporting rati

Explain what type of strategy will you use to meet demand, Dell Computers i...

Dell Computers is known for revolutionizing the personal computer market using mass customization. This company can turn out a huge volume of computers while still having a variety

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd