Define critical path, Operation Management

Assignment Help:

Define Critical Path.

Critical Path: Computation of Earliest and Latest Values of the events of the specified network is as follows:- 

Event              EOT                 LOT

 1                      0                      0

 2                      6                      6

 3                      5                      6

 4                      9                      9

 5                      16                    16

Therefore critical path is 1→ 2 → 4 → 5.


Related Discussions:- Define critical path

Compute the movement cost or load, Registration at Southern University has ...

Registration at Southern University has always been a time of emotions, commotions and lines. Students must move among 4 stations to complete the process. Last semester's registrat

Explain advantages and disadvantages of membership, Define the use of regio...

Define the use of regional trade organizations in international business. Identify the Regional Trade Organization of which the United States is a member. What are some of the adva

Explain establishing team operating principles, Team operating principles a...

Team operating principles are sometimes included in a project charter to enhance team functioning. Which of the following statements accurately describes the value of establishing

Explain what is the present value of each investment, You must choose betwe...

You must choose between two passive investments. Investment A requires an initial investment of $50,000 but will return $71,000 in three years. Investment B requires an initial inv

Explain it projects that should be a part of bill''s it plan, List and desc...

List and describe (in two or three sentences each) three IT projects that should be a part of Bill's IT Plan - one project to support each area and/or process identified in above

After working for 30 years, In the table given below the Distribution Manag...

In the table given below the Distribution Manager is expected to service these DCs as per the demands placed. If the actual sales after completing week one is as follows, what woul

Comparison between method and work measurement, Comparison between method a...

Comparison between method and work measurement: Method  study  is the  principle   technique  for reducing  the work  involved  primarily by eliminating unnecessary  movement

Calculate the standard production, Calculate the standard production  per s...

Calculate the standard production  per shift  of 8 hours duration  with the followings data: Observed time  per unit 5 minutes  Rating  factor 120 %  Total allowances 33.3

Talent planning in operation, Talent Planning in Operation 1. Produce ...

Talent Planning in Operation 1. Produce a report on the topic Talent Planning in Operation. Please ensure that you address the following issues: Describe at le

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd